Install a new hydraulic winch system to operate th Federal contract opportunity
Solicitation number
1333MK25Q0039
Issued by
Department of Commerce National Oceanic and Atmospheric Administration

About this file

This is a Combined Synopsis/Solicitation (Best Value) from NOAA for the procurement and installation of a new hydraulic winch system for the NOAA Ship PISCES, located in Norfolk, VA. The scope includes installing a hydraulic winch to raise and lower the Forward Mast, with specific requirements for a PullMaster PL2 winch with 10 horsepower HPU or equivalent.

The contractor must provide all parts, labor, rigging, welders, and expertise required, with detailed technical specifications including a 480 VAC motor, 6 GPM pump output, 22-gallon reservoir capacity, and 316 stainless steel components. Key requirements include ABS-certified welders, adherence to hot work policies, and installation of hydraulic piping and electrical systems. Quotes must be submitted electronically to JAMES.PRITCHARD@NOAA.GOV by 1200 hrs EST, January 24, 2025. The evaluation will emphasize past performance, technical capabilities, and winch/HPU specifications over price. Bidders must provide three similar past performance references, detailed cost breakdown, liability insurance, and material specifications.

View the file

Other files for this federal contract opportunity

Other files attached to Install a new hydraulic winch system to operate th, newest first.
File Type Posted
Sol_1333MK25Q0039_Amd_0001.pdf PDF
002_SOW_PISCES_Forward_Mast_Winch_Installation.pdf PDF
Sol_1333MK25Q0039.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NOAA Ship PISCES

Combined Synopsis/Solicitation (Best Value)

The National Oceanic and Atmospheric Administration (NOAA), Office of Marine and Aviation Operations/Marine Operations Center –NOAA Ship Pisces requires a new hydraulic winch and install.

NOAA Ship PISCES Forward Mast Winch Installation

1. SCOPE:

1.1. Procure and install a hydraulic winch to raise and lower the Forward Mast on NOAA Ship PISCES.

2. REFERENCES

2.1. Drawing M282-085-FA02 “General Arrangements”

2.2. Hot Work Permit

3. GOVERNMENT FURNISHED MATERIAL

3.1. None

4. REQUIREMENTS

4.1. Contractor is responsible to provide all parts, labor, rigging, welders, machinists, ship fitters, pipe fitters, sub-contractor support, supervision, and expertise required to accomplish the work. Temporary relocations of all interferences are the responsibility of the contractor as well as maintenance of workplace cleanliness and final cleaning of the work area. Government will furnish the services of ABS. All welders must be ABS certified.

4.2. Contractor shall adhere to the ship’s Hot Work policy and complete the Hot Work Chit of Reference 2.2 for all hot work. Contractor shall also follow all ship lock-out / tag-out procedures. Contractor is responsible to temporarily remove all materials in the Forward Scientific Bosun Stores (1-4-0) as needed to make the space safe for hot work as certified by a Marine Chemist. Temporarily stage the removed equipment in the ship’s Scullery.

4.3. Use of ship’s power is permitted. Provide a minimum of 24 hours notice to the COR to coordinate any lifts using the ship’s cranes.

4.4. Procure a new independent standalone hydraulically operated winch with associated HPU capable of raising and lowering the Forward Mast on NOAA Ship PISCES. One such acceptable winch currently installed on the sister ship HENRY BIGELOW is the PullMaster PL2 with an associated 10 horsepower HPU (Model 10ELPUFD from Pine Hill Equipment). Salient characteristics of the new winch / HPU for the Forward Mast rigging system is provided below:

Electric Motor Specifications:

• 480 VAC, 60Hz, 3-phase, totally enclosed fan cooled

• 10 Horsepower

• Maximum of 13 Amps

• IP-55 rated, 12 lead reconnectable

• Motor is painted in three coat marine enamel white

Pump Specs Specifications:

• Typical output up to 6 GPM and pressure up to 2250 PSI

• Standard pump circuit is open center

• Pump is painted in three coat marine enamel white

Reservoir Specifications:

• Reservoir is fabricated entirely in 50 series aluminum

• Reservoir has minimum 22 gallon capacity

• Reservoir is pre-piped with 25 micron return filter

• Reservoir has appropriate high speed craft/marine baffling and a clean out door

• Reservoir has oil level sight glass

• Reservoir has a marine desiccant breather cap, which doubles as the fill port

• Reservoir has restriction indicator for tank

• Reservoir has a drain port with a magnetic plug

General Specifications:

• All fasteners are 316 stainless steel.

• Each unit is fully run and output tested to the values required for the equipment it will run.

• Any fitting and hoses included are USCG approved, all JIC fittings are provided to connect to installers plumbing and hoses.

• Unit is shipped dry.

• All PHE power units are compatible with biodegradable oil.

• All power units have bolt down brackets with weldable steel tap feet.

Winch Control Features:

• HPU provided with a fully proportional 10 GPM electric control valve, mounted and plumbed

• HPU provided with a high pressure filter, mounted and plumbed to protect proportional valve

• 24VDC power supply mounted and wired to the HPU in a NEMA 4 enclosure that will be prewired with an appropriate amount of cable

• Contains a marine grade proportional controller that will be mounted at a place of convenience on deck.

• Technical manual (one paper copy and PDF)

Winch Specifications:

• Pullmaster PL2 Winch or approved equal

• 2000 lb. line pull single parted

• Winch includes fittings, gear oil, primary painting and weldable steel subframes

• 150 feet of line capable of 2,000 lb single line pull

4.5. Disassemble and remove necessary portions of the existing storage shelf in the Forward Scientific Bosun Stores Room (1-4-0) to make room for the new HPU foundation. Modify the storage shelf as necessary to retain the lower shelves.

4.6. Relocate the Forepeak Tank TLI to the adjacent angle iron stiffener for the Chain Locker.

4.7. Open and gas free the Chain Locker (2-5-0) for hot work. Note that anchor chains will remain in place for duration of work.

4.8. Fabricate a new steel foundation in the Forward Bosun Stores Room on the main deck to support the new winch HPU. The foundation shall be of adequate strength to support the HPU in rough seas. Recommended location for planning purposes is on the port side of the Chain Locker adjacent to the forward bulkhead.

Location for

HPU

Foundation

Relocate TLI to angle iron

Photos of the installed HPU on the BIGELOW

4.9. Install the new HPU onto the foundation and bolt into place using contractor furnished 316 stainless steel hardware.

4.10. On the FWD Capstan port bollard on the F’scl deck at Frame 1, fabricate a new foundation for the winch and weld to the deck on the forward 01 deck near the forward mast. The new foundation shall be fabricated out of 316 stainless steel.

Photos of the installed Pullmaster PL2 Winch on the BIGELOW

4.11. Provide and install three (QTY 3) Schedule 80 316 stainless steel pipes from the HPU control valve to/from the Main Deck penetrations for hydraulic hose connections. The pipe deck penetrations shall go through 316 stainless steel pipe collars. The collars shall be welded to the deck, top and bottom, and the pipes shall be welded to the collars, top and bottom. Deck penetrations shall extend a minimum of 6 inches above the deck before the first fitting. All welds shall be continuous welds to make watertight. Secureall piping with pipe hangers at no more than 6 feet intervals to properly support the pipes while the system is in use. Complete NDT testing on all deck penetrations in the presence of ABS.

4.12. Provide and install properly rated, tested, and tagged hydraulic hoses to connect each pipe connection to the hydraulic winch and HPU control valve respectively. Hose end fittings shall be 316 stainless steel. All exterior fittings shall be wrapped with Denso tape after a successful leak test.

Photos of the installed winch hose connections / deck connections on the BIGELOW

4.13. Flush the hydraulic piping and pressure tested to 2700 psi.

4.14. Install cable to run the HPU electrical motor controller and wire to circuit breaker panel P-412, breaker 10, located in the ladderwell, Access 2-16-2, on the main deck forward of the mess deck. Note that the cable will pass through a watertight bulkhead. Ensure that the cable runs through an existing MCT and properly repack the MCT after the cable has been run through it.

4.15. Procure and install a properly sized motor starter for the HPU electrical motor.

4.16. Mount the proportional controller on the forward 01 deck, starboard side, on the bulwark at a location to be determined by ship's force and the COR.

4.17. Run the electrical cable that is supplied with the HPU up to the forward 01 deck, starboard side, and connect it to the proportional controller. Properly secure the electrical cable throughout the run to the 01 deck. Provide and install (weld) a 316 stainless steel kick pipe to run the electrical cable up to the deck. The kick pipe welds and cable penetration must be watertight and tested in the presence of ABS.

1333MK25Q0039 Hydraulic Winch – Pisces

4.18. Fill the HPU reservoir with contractor furnished hydraulic oil and install wire rope on the winch.

4.19. Repair all disturbed insulation. Preserve all new and

disturbed steel areas on the interior and exterior of the ship. The top coat shall match the surrounding color.

4.20. Procure the services of a certified OEM technician to

commission the Winch system.

4.21. Demonstrate winch operation to raise and lower the winch to the COR.

4.22. Technical Evaluation Criteria:

4.22.1. Bidder must provide relevant past performance

accomplishing similar work on government/NOAA vessels.

4.22.2. Bidder’s quote must specify the proposed HPU and winch type with lead times and provide cut sheets showing technical specifications for the selected winch and HPU.

4.22.3. A higher emphasis will be placed on past performance, contractor technical capabilities, and winch/HPU technical specifications/quality over price.

5. QUALITY ASSURANCE

5.1. Perform an operational test on the HPU and winch to test for leaks and ensure proper operation with the OEM. Repair any leaks and deficiencies.

5.2. Perform a NDT or soap and blow testing on all deck penetrations as required by the local ABS surveyor.

5.3. Provide ABS approved welder’s certifications and ABS approved weld procedures to the local surveyor and COR.

6. NOTES

6.1. PISCES is located at the following address:

Marine Operations

1333MK25Q0039 Hydraulic Winch – Pisces

Center, Atlantic NOAA Ship PISCES 439 West York Street Norfolk, VA 23510

(viii) All applicable provisions and clauses are attached in a separate document.

(ix) Defense Priorities and Allocations Systems (DPAS) and assigned ratings is not applicable.

(x) Offers shall be submitted electronically to JAMES.PRITCHARD@NOAA.GOV no later than 1200 hrs EST, January 24, 2025.

NOTICE TO OFFERORs: Instructions for submitting quotations under this request for quote must be followed. Failure to provide all information to aid in the evaluation may be considered non-responsive. Offers that are non-responsive may be excluded from further evaluation and rejected without further notification to the offeror. All quotes must be submitted to the above Smart Sheet Link.

Quotes at a minimum must include the following:

1. The Request for Quote (RFQ) number;

2. The Name, Address, Telephone Number, and SAM Unique Identifier of the Offeror;

3. A statement specifying the extent of agreement with all terms, conditions, and provisions included in the RFQ. Quotes that reject the terms and conditions of the RFQ may be excluded from consideration;

4. Acknowledgment of Solicitation Amendments (SF-30), if any.

5. Demonstrate understanding of the statement of work/need with a detailed material specification or data sheet, pictures of the item, and authorized OEM letter to sell or distribute their products.

6. An itemized/detail breakdown cost of the quote that will reflect the entire price under this RFQ. (That would include, if applicable, the following: Material Cost, Labor, Travel, Freight/Delivery, Etc.).

7. A copy of the liability insurance (please ensure is up to date). (For Services Only)

8. Please provide at least three detail jobs with references performed within the past three years that are the same or similar in scope.

9. Vendor shall provide a point of contact that includes name, telephone number, emails, contract value and a detail description of the work performed.

(xi) Contact James Pritchard at 208-827-1265 or james.pritchard@@noaa.gov for information regarding this solicitation.

mailto:JAMES.PRITCHARD@NOAA.GOV

1. SCOPE:
2. REFERENCES
3. GOVERNMENT FURNISHED MATERIAL
4. REQUIREMENTS
4.22. Technical Evaluation Criteria:
5. QUALITY ASSURANCE
6. NOTES