This Statement of Work (SOW) details a maintenance service for the NOAA Ship Bell M. Shimada's bow thruster control system. Tees White Gill will provide a service technician to perform a dockside groom of the bow thruster controls and HMI, verifying system performance and ensuring the latest firmware and software are installed. The work is scheduled to take two days and will be conducted either in Newport, OR or San Diego, CA, with the Shimada currently slated to be dockside in San Diego from March 15-20, 2025. All work must be completed according to ABS rules and performed by the Original Equipment Manufacturer (OEM) or under OEM direction. The port engineer for coordination is Jerry Sheehan, who can be contacted at jerome.sheehan@noaa.gov or 541-600-7992.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

BOW THRUSTER GROOM

NOAA Ship BELL M. SHIMADA – 2025

Page | 1

1. Scope

1.1. The NOAA Ship SHIMADA requires a groom of the bow

thruster controls and HMI.

2. References

2.1. Available upon request

3. Government Furnished Material

3.1. None

4. Requirements

4.1. Provide Tees White Gill service technician to perform

a dockside groom of the NOAA Ship Bell M. Shimada bow thruster control system.

4.2. Verify that the system is performing correctly and has

the latest firmware and software.

4.3. For bidding purposes, assume two (2) days on site.

4.4. All work on the Bow Thruster Control System shall be

accomplished by the OEM or under the direction of the OEM.

5. Key Performance Milestone Dates:

5.1. This work will be performed in either Newport, OR or

San Diego, CA depending on the Lasker’s production schedule.

5.2. The Shimada is currently scheduled to be dockside in

San Diego March 15-20. This window coincides with the tentative Lasker dates of March 24&25.

6. Quality assurance

6.1. All work to be completed as per ABS rules.

7. Notes

7.1. Schedule all work and specific address location with

the SHIMADA Port Engineer Jerry Sheehan. EML:

jerome.sheehan@noaa.gov Cell: 541-600-7992