DOC Solicitaion 1331L520R13OS0016 Armored Vehicle DOC Responses to Questions

No. Document Section Page Question/Comment DOC Responses

Requirements Specifications 4.3 3

"Floor armored using ballistic steel that acts as an absorbent for mild blast throughout": Ballistic steel is not ideal for this application. We use 3/16” mild steel in the floor to mitigate blast. Ballistic steel can shatter from explosives and is common place for only ballistic protection and not blast.

Please confirm they want ballistic steel in the floor.

3/16" mild steel is acceptable.

Requirements Specifications 4.3 3

"Certification that B6 armoring was professionally installed": We can give them an in-house certificate since we are the professionals doing the work unless they have another certification authority they prefer to use. Our industry does not have any major regulating body in the US so this is vague.

An in-house certification is acceptable.

3 RFP 3.3 11

"Price Volume: Quantity =1, Unit=EA, Price =?": Are you requesting a purchase price, a lease price or a finance price? We can provide three different lease options, a closed-end lease, and open-end lease with a residual balloon and an open-end $1.00 buyout/finance lease. We can also just supply a purchase price

Please provide purchase pricing.

Requirement Specifications 4.3 of Requirment 2 and 3 Is there a Specific make, model, and output for the Siren and public address system?

There is not a specific model.