This is Amendment 0001 to RFQ 1305M326Q0357 issued by the National Oceanic and Atmospheric Administration (NOAA) through the Western Administrative Division (WAD-NWS) located in Seattle, Washington, effective August 10, 2026. The amendment modifies the solicitation and is not extended.

The amendment accomplishes three primary objectives: (1) adds an optional but highly encouraged site visit opportunity for each of two NEXRAD locations—KRGX Reno on August 27, 2026 from 0900-1300 PT and KLRX Battle Mountain on August 28, 2026 at 0900 PDT—with contractors required to email Joshua Davis, Facilities Operations Specialist, at joshua.davis@noaa.gov to register attendance; (2) addresses a late-received question regarding the 240-calendar-day period of performance, clarifying that while the timeline accommodates winter weather contingencies, active work is substantially shorter and strictly limited to non-winter months with completion required before early/mid-autumn weather impacts or deferred until mid-to-late spring; and (3) updates the Statement of Work (SOW) resulting from the amendment. The solicitation involves road repair work at two Nevada NEXRAD sites as documented in the attached Performance Work Statements (PWS LKN-RDA & REV Road Repair and PWS LKN-RDA & REV Road Repair A0001) and applicable Davis-Bacon Act wage determinations for Washoe County and Lander County. Contractors must acknowledge receipt of this amendment prior to the hour and date specified in the base solicitation by completing the required forms or providing separate written communication referencing the solicitation and amendment numbers.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: is not is required copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7.ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

PAGESOF

Contractor

The hour and date specified for receipt of Offers to sign this document and return

CASEY MORRISON

See continuation page

WAD-NWS

7600 SAND POINT WAY NE BLDG 1

SEATTLE WA 98115

WAD-NWS

1305M326Q0357

08/10/2026

08/10/2026

1 3

1305M326Q0357 0001

The purpose of Amendment 0001 is to:

1. Include an additional site visit for each site (see info below),

2. Answer a late question received after the question and answer (Q&A) period closed that is in the Government's best interest.

3. Update the SOW as resultant from the amendment.

Highlights have been added to PWS to delineate changes/revisions from this Amendment.

SITE VISIT:

Site visits are optional, but highly encouraged. Visits are only allowed on the following specified date:

KRGX Reno NEXRAD: August 27, 2026 from 0900 - 1300 PT KLRX Battle Mountain NEXRAD: August 28, 2026 at 0900 PDT

To attend the site visit, Contractors must email the following point of contact and indicate which day(s) and time(s) they plan to attend:

Joshua Davis, Facilities Operations Specialist (FOS), COR Phone: (385) 465-4701 Email: joshua.davis@noaa.gov

When responding, please include “RFQ 1305M326Q0357 Site Visit” in the subject line. It is the Contractor’s responsibility to arrive on time and ensure to check in with the COR to register attendance.

No additional site visits will be accommodated. Any delays need to be communicated directly to the point of contact provided above.

QUESTION & ANSWER:

Question 1: Is this project anticipated to take two hundred forty (240) Calendar days or is that a buffer for weather and other delays?

Answer: While the period of performance is set at 240 days to accommodate winter weather contingencies (e.g., snow), the active work required is substantially shorter.

Note: On-site performance is strictly limited to non-winter months. Work must be completed before early/mid-autumn weather impacts (such as snow or COR-determined heavy frost) or deferred until after winter conditions clear in mid-to-late spring.

Section 3 - Line Items and Attachments

List of Line Items

Table has been revised and now reads as follows:

List of Attachments

1305M326Q0357 0001

Attachment Number Title

1 PWS LKN-RDA & REV Road Repair 1 PWS LKN-RDA & REV Road Repair A0001 2 DBA WD NV20260110 Mod1 7.30.26 Washoe County 3 DBA WD NV20260097 Mod1 7.30.26 Lander County

Amendment of solicitation/modification of contract
Contract ID code
Amendment/modification number
Effective date
Requisition/purchase requisition number
Project number
Issued by
Code
Administered by
Code
Name and address of contractor
Code
Facility code
Amendment of solicitation number
Dated
Modification of contract/order number
Dated
This item only applies to amendments of solicitations
Accounting and appropriation data
This item applies only to modifications of contracts/orders.
This change order is issued pursuant to:
The above numbered contract/order is modified to reflect the administrative changes
This supplemental agreement is entered into pursuant to authority of:
Other
Important:
Description of amendment/modification
Name and title of signer
Contractor/offeror
Date signed
Name and title of contracting officer
Signature of Contracting Officer
Date signed
Previous edition unusable
Standard form 30 (rev. 11/2016)