Sol_1305M326Q0236_Amd_0004.pdf
PDF 239 KB Posted
- Attached to
- GROUNDSKEEPING SERVICES AT NWS IN UPTON, NY Federal contract opportunity
- Solicitation number
- 1305M326Q0236
About this file
This is Amendment 0004 to a solicitation for groundskeeping and landscaping services at Brookhaven National Laboratory (BNL) in Boulder, Colorado. The solicitation number is 1305M326Q0236, with an effective date of June 4, 2026, and the amendment was issued by WAD-SAP on June 18, 2026.
The solicitation encompasses comprehensive grounds maintenance services from April 1 through November 30 annually, including weekly mowing and trimming to maintain grass heights between 2 and 2.5 inches, seasonal bed cleanup, mulch application and maintenance (4 inches in beds, 6 inches on tree mounds), annual flower plantings three times per year, irrigation startup and maintenance, fertilization, weeding control using preferred organic methods when practical, and removal of all green waste from campus. The contractor must provide weekly service visits with frequency adjustments as needed to meet performance standards. Services must commence within ten business days of award, with work not requiring site access beginning within three business days. All contractor personnel must be 18 years of age, U.S. citizens, REAL ID compliant, and complete BNL Contractor/Vendor Orientation and badging within ten days of award. The contractor must employ a Site Manager capable of arriving on-site within 30 minutes when summoned. Contractor pricing must comply with DOL Wage Determination 2015-4157 Rev 31. The amendment clarifies that the existing irrigation system is fully functional at award, contractor-provided sprinkler head replacements are routine maintenance, no on-site storage is available, all green waste must be hauled off-campus, mulch depths must be maintained through replenishment or replacement as needed each season, and organic herbicide treatments are preferred but EPA-approved traditional herbicides are acceptable when applied in compliance with all applicable regulations.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 1305M326Q0236__ATTACHMENT_1_Statement_of_Work_REVISED_061826_0004.pdf | ||
| Sol_1305M326Q0236_Amd_0003.pdf | ||
| 1305M326Q0236__ATTACHMENT_1_Statement_of_Work_REVISED_061226_0003.pdf | ||
| Sol_1305M326Q0236_Amd_0002.pdf | ||
| 1305M326Q0236__ATTACHMENT_1_Statement_of_Work_REVISED_060926_0002.pdf | ||
| Sol_1305M326Q0236_Amd_0001.pdf | ||
| Sol_1305M326Q0236.pdf | ||
| 1305M326Q0236__ATTACHMENT_3_Wage_Determination_2015-4157_Rev_31_Dated_051326.pdf | ||
| 1305M326Q0236__ATTACHMENT_1_Statement_of_Work.pdf | ||
| 1305M326Q0236__ATTACHMENT_2_Site_Photo.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: is not is required copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7.ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
PAGESOF
Contractor
The hour and date specified for receipt of Offers to sign this document and return
KERRI COFFEY
See continuation page
WAD-SAP
325 BROADWAY, SOU6
BOULDER CO 80305
WAD-SAP-B
1305M326Q0236
06/04/2026
06/04/2026
1 8
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
NSN 7540-01-152-8067
1305M326Q0236/0004
AMENDMENT NUMBER 0004 (06/18/2026):
THE STATEMENT OF WORK HAS BEEN REVISED.
QUOTERS SHOULD DISREGARD ANY PREVIOUS VERSIONS
OR REVISIONS OF ATTACHMENT 1 STATEMENT OF WORK.
QUOTERS SHOULD REFERENCE ATTACHMENT 1
STATEMENT OF WORK_REVISED_061826.
QUOTES RECEIVED THAT ARE NOT RESPONSIVE TO
ATTACHMENT 1 STATEMENT OF WORK_REVISED_061826
MAY BE EXCLUDED FROM EVALUATION WITHOUT
NOTIFICATION TO THE QUOTER.
1) VENDOR QUESTION: Wage-rate basis. The solicitation incorporates DOL Wage
Determination 2015-4157 Rev 31 (e.g., Laborer, Grounds Maintenance at $21.71/hr plus $5.55
H&W), while the in-text RFO 52.222-42 references an equivalent "Laborer NA-02, $18.40-$21.45/hr plus 30%." Please confirm that contractor pricing must be based on the incorporated Wage Determination rates and that the 52.222-42 NA-02 statement is informational only and not the required pricing floor.
RESPONSE: Please thoroughly read the clause
RFO 52.222-42. It is identifying the class of service employee and states the wages and fringe benefits payable if they were employed by the contracting agency. The Contractor is responsible for determining the correct wage for employees in accordance with local, state and federal laws, regulations and rules.
2) VENDOR QUESTION: Service-visit frequency.
Does the Government have an expected minimum number of on-site service visits per week (or per month) during the April 1 to November 30 season, or is the contractor free to propose any frequency that meets the weekly performance standards in the SOW?
RESPONSE: The Contractor shall provide service visits once per week during the April 1 through
November 30 performance period; however, shall adjust the frequency of mowing and trimming operations in order to maintain the height of the grass between 2” and 2 ½”.
3) VENDOR QUESTION: Site access and badging
vs. start date. Every worker must be a U.S.
Continued...
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C) citizen, complete BNL Contractor/Vendor
Orientation, be REAL-ID compliant, and be badged within 10 days, while SOW Sec. 9 requires services to begin within three business days of award. What is the typical elapsed time and any fee for BNL orientation and badging, can crews complete badging in time to meet the start requirement, and is escort available if badging is incomplete at start?
RESPONSE: The Contractor shall provide groundskeeping and landscaping services within ten (10) business days of Date of Award. The badging office is located off campus in
Building 101 and can be accessed by contractors without gate clearance. No escort services are available Contractor employees/subcontractors.
All required BNL badging information, guidance and direct registration links will be provided to the Contractor after award.
4) VENDOR QUESTION: Catch-up services (SOW
Sec. 3A). The SOW requires all non-mowing services that were to be performed in April, May, and June 2026 to be completed within two weeks of award. Please itemize, or confirm the contractor should price, the specific catch-up services (e.g., spring bed cleanup, first mulch placement, irrigation start-up, first annual planting, first fertilization), and confirm whether these are within the Base CLIN price or separately compensated.
RESPONSE: Please review the response to
Question 1 under Amendment Number 0002
(06/09/2026).
5) VENDOR QUESTION: Material quantities. Can the Government provide the approximate total bed square footage / mulch cubic-yardage
(4-inch minimum in beds, 6-inch on tree mounds) and the approximate number of annual plants per planting cycle (three plantings per year across the four beds, island, and signage areas), so material costs can be priced accurately?
RESPONSE: The Government will not provide specific quantities or estimates for mulch, planting materials, or related landscaping requirements. Quoters are responsible for determining material quantities necessary to
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C) meet the requirements of the Statement of Work.
It is highly recommended that Quoters visit and inspect the place of performance to determine quantities for their quotes.
6) VENDOR QUESTION: Winter scope. Please confirm that snow and ice removal is entirely outside the scope of this contract and that no services are required December 1 through March
31.
RESPONSE: There is no snow and/or ice removal stated in the Statement of Work.
7) VENDOR QUESTION: Irrigation system. Is the existing irrigation system fully functional at award? Are replacement sprinkler heads and controller repairs the Contractor's cost, and is there a cap or threshold above which repairs become a separate Government-funded action versus routine maintenance?
RESPONSE: The existing irrigation system is fully functional. The Contractor shall replace sprinkler heads that are malfunctioning or damaged, clean dirty or clogged sprinkler heads, and adjust sprinkler heads to ensure they are spraying in the correct direction to water plants, groundcover, flower beds and trees. The Contractor should notify the
Government Point of Contact of any irrigation system damage, malfunctioning issues, or deficiencies to so that these issues can be addressed.
8) VENDOR QUESTION: On-site storage and debris haul. Is any on-site storage (shed or staging area) available for contractor equipment or materials, or must all equipment be transported in and out each visit? Please confirm that all green-waste must be hauled off the BNL campus.
RESPONSE: No on-site storage, staging area, or equipment/material laydown space will be provided. Contractors shall transport all equipment and materials to and from the site as required. Yes, all green waste generated during contract performance must be removed from the campus and properly disposed of by the
Contractor.
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
9) VENDOR QUESTION: Site Manager proximity
(SOW Sec. 5A). The SOW requires a Site Manager located within 30 minutes of the site. Must the
Site Manager be within 30 minutes during all service hours, or only able to arrive within 30 minutes when summoned?
RESPONSE: The Site Manager is not required to remain on-site or within a 30-minute radius at all times. However, the Site Manager must be able to arrive at the site within 30 minutes if summoned by the Government.
NO OTHER CHANGES.
AMENDMENT NUMBER 0003 (06/12/2026):
1) QUOTE DUE DATE HAS BEEN CHANGED TO
WEDNESDAY, JUNE 24, 2026, 10:00AM MDT.
2) THE STATEMENT OF WORK HAS BEEN REVISED.
QUOTERS SHOULD DISREGARD ATTACHMENT 1 STATEMENT
OF WORK AND ATTACHMENT 1 STATEMENT OF
WORK_REVISED_060926.
QUOTERS SHOULD REFERENCE ATTACHMENT 1 STATEMENT
OF WORK_REVISED_061226.
QUOTES RECEIVED THAT ARE NOT RESPONSIVE TO
ATTACHMENT 1 STATEMENT OF WORK_REVISED_061226
MAY BE EXCLUDED FROM EVALUATION WITHOUT
NOTIFICATION TO THE QUOTER.
IT IS HIGHLY RECOMMENDED THAT QUOTERS VISIT AND
INSPECT THE PLACE OF PERFORMANCE.
NO OTHER CHANGES.
AMENDMENT NUMBER 0002 (06/09/2026):
THE STATEMENT OF WORK HAS BEEN REVISED.
VENDORS SHOULD DISREGARD ATTACHMENT 1 STATEMENT
OF WORK AND REFERENCE ATTACHMENT 1 STATEMENT OF
WORK_REVISED_060926.
QUOTES RECEIVED THAT ARE NOT RESPONSIVE TO
ATTACHMENT 1 STATEMENT OF WORK_REVISED_060926
MAY BE EXCLUDED FROM EVALUATION WITHOUT
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
NOTIFICATION TO THE QUOTER.
IT IS HIGHLY RECOMMENDED THAT QUOTERS VISIT AND
INSPECT THE PLACE OF PERFORMANCE.
1) VENDOR QUESTION: Initial "Catch-Up"
Services: Section 3.A of the SOW states the
Contractor shall provide all missed services from April, May, and June 2026 (excluding mowing) within two weeks of award. To ensure accurate pricing for this surge, could the
Government provide a definitive list of the specific seasonal tasks (e.g., specific fertilization applications, spring cleanup, or bed preparation) that were not performed during those months?
RESPONSE:
The Contractor shall be responsible for bringing the grounds to the required maintenance standards within two weeks of award. Quoters are encouraged to make a site visit to review the site conditions and price their proposals accordingly. All seasonal services required by the Statement of Work that would normally have occurred during April, May, and June 2026, excluding mowing, should be assumed to be included in the catch-up effort.
Also be aware that the standard Fall clean-up was not completed, and the rock beds around the building have been severely neglected requiring a backfill of new rock material.
2) VENDOR QUESTION: Annual Bed Planting
Density: Section 7.B.13 requires the planting of annual flowers three times per year in four beds. To ensure all quoters are pricing this requirement consistently, what is the
Government’s expected quantity of plants or bulbs per bed for each of the three seasonal rotations?
RESPONSE:
Quoters shall provide sufficient quantities of annual flowers and/or bulbs to achieve a full, professional, and aesthetically pleasing appearance in each bed. No specific plant count is prescribed because it can differ depending
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C) on type of plants. Quoters are encouraged to make a site visit to review the site to be able to obtain bed sizes and conditions that would be useful in determining what is needed to fulfill the Statement of Work. Pricing should include all labor, materials, and plantings necessary to meet the Statement of Work for each of the three seasonal rotations.
3) VENDOR QUESTION: Irrigation System
Liability: The SOW requires the Contractor to perform irrigation startup by May 15 and replace failing heads as needed. Since the anticipated award date is after the May 15 deadline, will the Government provide a system status report upon award? Additionally, is the replacement of failing heads and lines considered part of the firm-fixed-price, or will repairs of pre-existing failures be handled via a separate mechanism?
RESPONSE:
PLEASE REVIEW ATTACHMENT 1 STATEMENT OF
WORK_REVISED_060926, SECTION 7 PERFORMANCE
STANDARDS AND GUIDELINE REUQIREMENTS,
SUB-SECTION B, ITEM NUMBER 15.
4) VENDOR QUESTION: Security Badging vs. Start
Date: Section 9 states work must begin within three business days of award, while Section 5.E notes the badging process takes ten days. Can the Government clarify if the performance start date will be adjusted to account for the
Brookhaven National Laboratory (BNL) badging and orientation timeline for new personnel?
RESPONSE:
The Contractor shall initiate the badging and orientation process immediately upon award.
Work that does not require site access may begin within the required three business days.
The Government will coordinate access requirements and reasonable accommodation of the BNL badging and orientation process to ensure contract performance can commence as quickly as possible. All Contractor staff working on the site must be 18 of age prior to commencement work date and REAL ID compliant.
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
5) VENDOR QUESTION: Mulch Application
Requirements: Section 7.B.8 requires mulch depth of 4 inches in beds and 6 inches for tree mounds. Is it the Government’s intent for the
Contractor to apply a full 4–6 inches of new mulch annually, or to maintain that depth through replenishment?
RESPONSE:
The Contractor shall maintain stated mulch depths throughout the performance period. Each season the Contractor will assess conditions and provide replenishment or complete replacement as needed.
6) VENDOR QUESTION: Preferred Weeding
Treatment: Section 7.B.12 states that an organic alternative treatment such as "Go
Green" is preferable for rock beds. Is the use of an organic treatment a mandatory requirement, or will traditional EPA-approved herbicides also be considered acceptable?
RESPONSE:
Organic treatment methods are preferred for use in rock beds whenever practical. However, traditional EPA-approved herbicides may be used when applied in accordance with all applicable federal, state, local, and site-specific requirements. Contractors should ensure that any products used are appropriate for the application and do not adversely affect surrounding vegetation or site operations.
NO OTHER CHANGES.
AMENDMENT NUMBER 0001 (06/09/2026):
CHANGES WERE MADE TO THE DATES IN THE BASE
PERIOD AND OPTION PERIODS IN ORDER TO PROVIDE
CLARIFICATION.
NO OTHER CHANGES.
| Amendment of solicitation/modification of contract |
| Contract ID code |
| Amendment/modification number |
| Effective date |
| Requisition/purchase requisition number |
| Project number |
| Issued by |
| Code |
| Administered by |
| Code |
| Name and address of contractor |
| Code |
| Facility code |
| Amendment of solicitation number |
| Dated |
| Modification of contract/order number |
| Dated |
| This item only applies to amendments of solicitations |
| Accounting and appropriation data |
| This item applies only to modifications of contracts/orders. |
| This change order is issued pursuant to: |
| The above numbered contract/order is modified to reflect the administrative changes |
| This supplemental agreement is entered into pursuant to authority of: |
| Other |
| Important: |
| Description of amendment/modification |
| Name and title of signer |
| Contractor/offeror |
| Date signed |
| Name and title of contracting officer |
| Signature of Contracting Officer |
| Date signed |
| Previous edition unusable |
| Standard form 30 (rev. 11/2016) |
| Continuation sheet |
| Reference Number |
| Name of Offeror or Contractor |
| OPTIONAL FORM 336 (4-86)) |
Sponsored by GSA FAR (48 CFR) 53.110
File details come from the government source that posted it. Updated .