1305M326Q0190__ATTACHMENT_1__STATEMENT_OF_WORK.pdf
PDF 199 KB Posted
- Solicitation number
- 1305M326Q0190
About this file
This is a Statement of Work for roof replacement services at the Nashville National Weather Service Weather Forecast Office in Old Hickory, Tennessee.
The contractor must remove the existing asphalt shingle roof and install a new baked enamel standing seam metal roof with 16-inch or equivalent on-center seams. Work includes removal of existing shingles, felt, and decking as needed; installation of new decking, felt, flashing, edging, caulking, and snow/ice retention products. Roofing materials must comply with UL 263 Fire Resistant Rating, UL2218 Class 4 Hail Resistant Rating, UL 580 Class 90 100 mph Wind Rating, ASTM E-1680 Air Penetration approval, and ASTM E-1646 Water Infiltration approval. Minimum panel thickness is 24-gage with 1.5-inch minimum seam height. The metal roof panels must be painted a color to be determined after award and include minimum 15 lb. self-adhesive insulation sheets. The contractor must also remove and reinstall the existing lightning protection system in compliance with NFPA Code requirements, with certification from an Underwriters Laboratories third-party inspector. A minimum five-year workmanship warranty and twenty-year material and labor warranty on paint and materials are required.
The contractor must submit roof design and specifications within 21 calendar days of Notice to Proceed and complete all work within 60 days. Key personnel requirements include a Project Manager and Onsite Manager. The contractor is responsible for obtaining all permits and licenses, coordinating work to avoid disruption to the 24-hour National Weather Service operations, performing work during regular hours (0700-1700 Monday-Friday), observing federal holidays, and maintaining site cleanliness and restoration. All work must comply with OSHA safety requirements, local and state codes, and standard roofing industry practices. Sexual assault and sexual harassment training and security processing are required within 30 days of award. The Government Point of Contact will be provided at award.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
1. BACKGROUND
The Nashville National Weather Service (NWS) Weather Forecast Office (WFO) located in Old Hickory, Tennessee is in need of the complete removal of the existing roof and the installation of a new standing seam metal roof.
The NWS is a 24-hour, 365-day operation, and is a public safety agency. The existing roofing at Nashville NWS needs immediate replacement. High winds caused by the recent storms have torn away large sections of shingles on the main office building. This damage now compromises the building’s ability to be weather proof. It is recommended that a standing seam metal roof be installed as a replacement on the main office.
2. REQUIREMENTS
Replace the existing asphalt shingle roof at the Nashville NWS with a baked enamel standing seam metal roof. This roof will replace the existing composition shingle roof and includes, but is not limited to: removal of existing shingles, felt, existing decking if needed, installation of new decking, felt, flashing and edging, caulking, snow/ice retention products, and standing seam metal roof. The required metal roof panel installation is 16” or equivalent on center seams.
Roof panel color will be similar to existing red metal flashing & selected by the local office staff. All work to be completed in a professional manner according to standard industry practices. Any alteration or deviation from specifications involving additional costs, changes to material, or cosmetic changes will require prior written approval from the National Weather Service. A minimum five-year workmanship warranty and a minimum twenty-year warranty on paint and materials is required as part of the included pricing.
General Requirements:
A. The roof replacement includes, but is not limited to, the following, as needed: removal and replacement parapet caps, copings, felts, insulation, flashings, metal edging, corroded steel roof decking, caulking, and sealing of all metal seams as needed. This will include the removal of the existing roofing system down to the wood decking, plus the design and installation of a new metal roof system. This project may require the removal and replacement of the existing lightning protection system around the roof.
Reinstallation of lightning protection shall be certified by a qualified contractor.
B. The Contractor shall provide all supervision, labor, tools, materials and equipment to perform the work as stated.
C. The Contractor shall reuse and modify the existing Building Lightning Protection Systems to the extent necessary to be compliant per the NFPA Code Compliant Building Lightning Protection System.
D. The Contractor shall complete all work in a professional and workmanlike manner, per Manufacturers' specifications and requirements and in accordance with roofing industry standards and practices. The installation shall be in accordance with the latest edition of Local, State and Federal Codes identified with the approved Metal Roof System Manufacturer.
E. The Contractor shall comply with the requirements and specifications in this Statement of Work. If there is conflict between requirements within the Statement of Work or the approved Metal Roof System, the Contractor shall comply with the most stringent requirement, unless the Contractor, through direct negotiation with the Government Point of Contact, receives written approval from the Government Point of Contact and Contracting Officer to comply with the less stringent of the conflicting requirement.
G. All alterations or deviations from either this Statement of Work, established specifications or from the approved Roofing System Designer that will involve additional costs, changes to material, or cosmetic changes shall require prior written approval from the Government Point of Contact and the Contracting Officer before they are performed by the Contractor.
H. Contractor shall provide all rigging needed to remove and replace the roof without damaging any existing buildings or landscaping. Contractor shall be responsible for restoring work site to original condition.
I. Contractor shall coordinate daily work activities and schedule with the Weather Forecast Office
Facilities Engineering Technician (FET), Electronic Systems Analyst (ESA), and the Meteorologist-In- Charge (MIC), so as to not interfere with or disrupt the operations of the National Weather Service.
J. Lightning Protection System Requirements, Designs, Shop Drawings and Details, and Construction
Requirements:
1. The Contractor shall remove the existing Building Lightning Protection System from the NWS office.
2. The Contractor shall reuse and modify the existing Building Lightning Protection Systems to the extent necessary to bring the existing Lightning Protection Systems up to current NFPA Code requirements. Certification documentation from an Underwriters Laboratories Inc. third party inspector should be submitted to the Government Point of Contact verifying that the reinstalled Lightning Protection System has been reinstalled to current NFPA Standards.
3. The Contractor shall submit Lightning Protection System Shop Drawings, and Lightning Protection
System Installation Details and Instructions to the Government Point of Contact for review and approval.
K. Roof Warrantees:
1. 5 Year Workmanship Warranty by Roof Installation Contractor:
a. The Contractor shall provide, at a minimum, a five-year written workmanship/labor warranty, including coverage to building and contents resulting from failure to prevent penetration of water.
2. 20 Year Material and Labor, No Cost, Watertight (Water Tightness) Warranty by Manufacturer:
a. The Contractor shall, at a minimum, provide a twenty-year Manufacturer’s Material and Labor, No Cost to Owner, Watertight (Water Tightness) Warranty. A written warranty is required.
b. Please note that the roofing material Manufacturer’s Representative must inspect and certify the installation of the Roofing System is in order for the Manufacturer of the roofing materials to issue the required Manufacturer's Watertight (Water Tightness) Roof Warranty.
L. Submittals:
The Contractor shall provide all submittals to the Government Point of Contact within 21 calendar days after the issuance of the Notice to Proceed.
The Contractor shall provide the roof design to the Government Point of Contact for review and obtain written approval prior to start of onsite roof demolition work.
The Contractor shall provide one set of the documentation/items listed below:
1. Roof Designer Qualifications and Experience.
2. Roof Contractor/Installer Qualifications and Experience.
3. Manufacturer's Engineered Roof Design and all Engineered Roof Design Calculations to substantiate the entire roof system design.
4. Manufacturer's detailed Roof Design Drawings, Shop Drawings, and Manufacturer's Roof Installation Details and Instructions.
5. Primer and Paint for metal roofing items.
6. Caulking for metal items.
7. Roof Insulation Material.
8. Roof Insulation Fasteners.
9. Modified cap FR (Fire Retardant) sheet.
10. Self-Adhesive High Temperature Underlayment as needed.
11. Contractor's Construction Performance Plan and Schedule.
Within 30 calendar days after contract award and prior to the start of work, prepare and submit to the Contracting Officer a Baseline Construction Schedule in the form of a in accordance with the terms in Contract Clause FAR 52.236-15 Schedules for Construction Contracts, except as modified in this contract. The approval of a Baseline Construction Schedule is a condition precedent to:
• The Contractor starting demolition work or construction stage(s) of the contract.
• Processing Contractor's invoice(s) for construction activities/items of work.
• Review of any schedule updates.
Submittal of the Baseline Construction Schedule, and subsequent schedule updates, is understood to be the Contractor's certification that the submitted schedule meets the requirements of the Contract Documents, represents the Contractor's plan on how the work will be accomplished, and accurately reflects the work that has been accomplished and how it was sequenced (as-built logic).
12. New Roof Lightning Protection System Shop Drawings, and Lightning Protection System
Installation Details and Instructions.
13. All Required Written Roof Warranties from the Manufacturer and Roof Installation Contractor to be provided after final construction acceptance inspection.
14. Required Construction Permits from local regulatory and code compliance authorities.
M. Disposal of Construction Debris:
1. The Contractor shall properly remove and dispose of all construction materials and/or demolition debris as required by Local, State, and Federal Regulations.
2. The Contractor shall salvage all recyclable metals and removed roofing materials and deliver metals to a recycle company for proper disposal and salvage.
N. Site Cleanup and Restoration:
1. The Contractor shall be responsible for all "Contractor Caused" damage to the worksite and for restoring work site to original condition to the satisfaction of the Contracting Officer Representative.
2. Provide all rigging and equipment needed to remove and replace the roof without causing any damage to existing building, adjacent buildings, sidewalks, asphalt areas, living plants, sprinkler systems, trees, or landscaping.
3. The Contractor shall repair to the satisfaction and approval of the Contracting Officer Representative all Grass Areas, Shrubs, Plants, Sidewalks, Sprinkler Systems, Asphalt Parking Areas, and etc. when damaged by the Contractor during construction.
4. All disputes regarding "Contractor Caused" damage shall be documented in writing and with digital pictures by the Contractor. The Contractor shall send all such documentation to the Contracting Officer for review and final decision.
O. Licenses, Permits, and Fees:
The Contractor shall be responsible for obtaining and paying for all licenses, permits, and fees required for completing all required work. Please note that this is a Federal Government Owned Facility and that all local licenses, permits, and fees are controlled and governed by Public Law 100.
P. Local, State, and Federal, Health and Safety Compliance and Code Compliance:
1. Comply with all Local, State, and Federal environmental, health, and safety regulations while conducting this work.
2. In addition, the Contractor shall ensure that all work follows all applicable Local, State, and Federal
Codes.
Q. Safety and Safety Plan:
1. Safety: The Contractor shall observe and institute all applicable OSHA safety requirements and procedures to prevent accidents and injuries to both Contractor and Government employees and shall comply with 40 CFR 1926 Subpart M for fall protection requirements for all workers on this project.
2. The Contractor shall designate one person as Safety Coordinator for purposes of communication between the Contractor and the National Weather Service. The Primary Contact shall be determined in a separate letter.
3. The Contractor shall not be allowed to flame torch cut any metals upon or within the roof structure of the building.
R. Key Personnel
1. The Contractor shall provide the following Key Personnel positions prior to the start of the project.
These positions can be the occupied by the same person but must be able to fulfill both positions. If Key Personnel changes are made, the Government Point of Contact must be notified in writing prior to the change.
• Project Manager – Must be able to represent the contractor in regards to contract requirements and/issues.
• Onsite Manager – Must be at the location of project whenever work is being performed by contractor or subcontractors. Communication to the Government Point of Contact must be through this position.
S. Closeout Submittals – Prior to submitting final invoice the Contractor all closeout submittals are required. Specifications 07 78 00 incorporated as reference.
PART 1 GENERAL
1.1 DEFINITIONS
1.1.1 As-Built Drawings
SECTION 01 78 00
CLOSEOUT SUBMITTALS
As-built drawings are the marked-up drawings, maintained by the Contractor on-site, that depict actual conditions and deviations from the contract documents. These deviations and additions may result from coordination required by, but not limited to: contract modifications; official responses to submitted Requests for Information (RFI's); direction from the Government Point of Contact; design that is the responsibility of the Contractor, and differing site conditions. Maintain the as-builts throughout construction as red-lined hard copies on site.
These files serve as the basis for the creation of the record drawings.
1.1.2 Record Drawings
The record drawings are the final compilation of actual conditions reflected in the as-built drawings.
1.2 SOURCE DRAWING FILES
Request the full set of electronic drawings, in the source format, for Record Drawing preparation, after award and at least 30 days prior to required use.
1.2.1 Terms and Conditions
Data contained on these electronic files must not be used for any purpose other than as a convenience in the preparation of construction drawings and data for the referenced project. Any other use or reuse is at the sole risk of the Contractor and without liability or legal exposure to the Government. The Contractor must make no claim and waives to the fullest extent permitted by law, any claim or cause of action of any nature against the Government, its agents or sub consultants that may arise out of or in connection with the use of these electronic files. The Contractor must, to the fullest extent permitted by law, indemnify and hold the Government harmless against all damages, liabilities or costs, including reasonable attorney's fees and defense costs, arising out of or resulting from the use of these electronic files. These electronic CAD drawing files are not construction documents. Differences may exist between the CAD files and the corresponding construction documents. The Government makes no representation regarding the accuracy or completeness of the electronic CAD files, nor does it make representation to the compatibility of these files with the Contractor hardware or software. In the event that a conflict arises between the signed and sealed construction documents prepared by the Government and the furnished Source drawing files, the signed and sealed construction documents govern.
The Contractor is responsible for determining if any conflict exists. Use of these Source Drawing files does not relieve the
Contractor of duty to fully comply with the contract documents, including and without limitation, the need to check, confirm and coordinate the work of all contractors for the project. If the Contractor uses, duplicates or modifies these electronic source drawing files for use in producing construction drawings and data related to this contract, remove all previous indicia of ownership (seals, logos, signatures, initials and dates).
1.3 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government.
Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-03 Product Data Warranty Management Plan Warranty Tags Spare Parts Data SD-08 Manufacturer's Instructions Posted Instructions SD-10 Operation and Maintenance Data Operation and Maintenance Manuals; G SD-11 Closeout Submittals As-Built Drawings; G Record Drawings; G As-Built Record of Equipment and Materials
1.4 SPARE PARTS DATA
Submit two copies of the Spare Parts Data list.
a. Indicate manufacturer's name, part number, and stock level required for test and balance, pre-commissioning, maintenance and repair activities. List those items that may be standard to the normal maintenance of the system.
1.5 WARRANTY MANAGEMENT
1.5.1 Warranty Management Plan
Develop a warranty management plan which contains information relevant to FAR 52.246-21 Warranty of Construction. At least 30 days before the planned pre-warranty conference, submit one set of the warranty management plan. Include within the warranty management plan all required actions and documents to assure that the Government receives all warranties to which it is entitled. The plan narrative must contain sufficient detail to render it suitable for use by future maintenance and repair personnel, whether tradesmen, or of engineering background, not necessarily familiar with this contract. The term "status" as indicated below must include due date and whether item has been submitted or was accomplished. Submit warranty information, made available during the construction phase, to the Contracting Officer for approval.
Assemble approved information in a binder and turn over to the Government upon acceptance of the work.
The construction warranty period must begin on the date of project acceptance and continue for the full product warranty period. Conduct a joint 9 month warranty inspection, measured from time of acceptance; with the Contractor, Contracting Officer and the Customer Representative. The warranty management plan must include, but is not limited to, the following:
a. Roles and responsibilities of personnel associated with the warranty process, including points of contact and telephone numbers within the organizations of the Contractors, subcontractors, manufacturers or suppliers involved.
b. For each warranty, the name, address, telephone number, and e-mail of each of the guarantor's representatives nearest to the project location.
c. A list and status of delivery of Certificates of Warranty for extended warranty items, including roofs, HVAC balancing, pumps, motors, transformers, and for commissioned systems, such as fire protection and alarm systems, sprinkler systems, and lightning protection systems.
d. As-Built Record of Equipment and Materials list for each warranted equipment, item, feature of construction or system indicating:
(1) Name of item.
(2) Model and serial numbers.
(3) Location where installed.
(4) Name and phone numbers of manufacturers or suppliers.
(5) Names, addresses and telephone numbers of sources of spare parts.
(6) Warranties and terms of warranty. Include one-year overall warranty of construction, including the starting date of warranty of construction. Items which have warranties longer than one year must be indicated with separate warranty expiration dates.
(7) Cross-reference to warranty certificates as applicable.
(8) Starting point and duration of warranty period.
(9) Summary of maintenance procedures required to continue the warranty in force.
(10) Cross-reference to specific pertinent Operation and Maintenance manuals.
(11) Organization, names and phone numbers of persons to call for warranty service.
(12) Typical response time and repair time expected for various warranted equipment.
e. The plans for attendance at the 4 and 9 month post-construction warranty inspections conducted by the Government.
f. Procedure and status of tagging of equipment covered by warranties longer than one year.
g. Copies of instructions to be posted near selected pieces of equipment where operation is critical for warranty or safety reasons.
1.5.2 Performance Bond
The Performance Bond must remain effective throughout the construction and warranty period .
a. In the event the Contractor fails to commence and diligently pursue any construction warranty work required, the Contracting Officer will have the work performed by others, and after completion of the work, will charge the remaining construction warranty funds of expenses incurred by the Government while performing the work, including, but not limited to administrative expenses.
b. In the event sufficient funds are not available to cover the construction warranty work performed by the Government at the Contractor's expense, the Contracting Officer will have the right to recoup expenses from the bonding company.
c. Following oral or written notification of required construction warranty repair work, respond in a timely manner. Written verification will follow oral instructions. Failure to respond will be cause for the Contracting Officer to proceed against the Contractor.
1.5.3 Pre-Warranty Conference
Prior to contract completion, and at a time designated by the Contracting Officer, meet with the Contracting Officer to develop a mutual understanding with respect to the requirements of this section. At this meeting, establish and review communication procedures for Contractor notification of construction warranty defects, priorities with respect to the type of defect, reasonable time required for Contractor response, and other details deemed necessary by the Contracting Officer for the execution of the construction warranty. In connection with these requirements and at the time of the Contractor's quality control completion inspection, furnish the name, telephone number and address of a licensed and bonded company which is authorized to initiate and pursue construction warranty work action on behalf of the Contractor. This point of contact must be located within the local service area of the warranted construction, be continuously available, and be responsive to Government inquiry on warranty work action and status. This requirement does not relieve the Contractor of any of its responsibilities in connection with other portions of this provision.
1.5.4 Warranty Tags
At the time of installation, tag each warranted item with a durable, oil and water resistant tag approved by the Contracting Officer. Attach each tag with a copper wire and spray with a silicone waterproof coating.
Also, submit two record copies of the warranty tags showing the layout and design. The date of acceptance and the QC signature must remain blank until the project is accepted for beneficial occupancy. Show the following information on the tag.
Model number Serial number Contract number Warranty period from/to Inspector's signature Construction Contractor Address Telephone number Warranty contact Address Telephone number Warranty response time priority code
WARNING - PROJECT PERSONNEL TO PERFORM ONLY OPERATIONAL MAINTENANCE DURING
THE WARRANTY PERIOD.
PART 3 EXECUTION
3.1 AS-BUILT DRAWINGS
Provide and maintain two black line print copies of the PDF contract drawings for As-Built Drawings. Maintain the as-builts throughout construction as red-lined hard copies on site and red-lined PDF files. Submit As-Built Drawings 30 days prior to Beneficial Occupancy Date (BOD).
3.1.1 Markup Guidelines
Make comments and markup the drawings complete without reference to letters, memos, or materials that are not part of the As-Built drawing. Show what was changed, how it was changed, where item(s) were relocated and change related details. These working as-built markup prints must be neat, legible and accurate as follows:
a. Use base colors of red, green, and blue. Color code for changes as follows:
(1) Special (Blue) - Items requiring special information, coordination, or special detailing or detailing notes.
(2) Deletions (Red) - Over-strike deleted graphic items (lines), lettering in notes and leaders.
(3) Additions (Green) - Added items, lettering in notes and leaders.
b. Provide a legend if colors other than the "base" colors of red, green, and blue are used.
c. Add and denote any additional equipment or material facilities, service lines, incorporated under As-Built Revisions if not already shown in legend.
d. Use frequent written explanations on markup drawings to describe changes. Do not totally rely on graphic means to convey the revision.
e. Use legible lettering and precise and clear digital values when marking prints. Clarify ambiguities concerning the nature and application of change involved.
f. Wherever a revision is made, also make changes to related section views, details, legend, profiles, plans and elevation views, schedules, notes and call out designations, and mark accordingly to avoid conflicting data on all other sheets.
g. For deletions, cross out all features, data and captions that relate to that revision.
h. For changes on small-scale drawings and in restricted areas, provide large-scale inserts, with leaders to the applicable location.
i. Indicate one of the following when attaching a print or sketch to a markup print:
1) Add an entire drawing to contract drawings
2) Change the contract drawing to show changes on the drawing.
3) Provided for reference only to further detail the initial design.
j. Incorporate all shop and fabrication drawings into the markup drawings.
3.1.2 As-Built Drawings Content
Show on the as-built drawings, but not limited to, the following information:
a. The actual location, kinds and sizes of all sub-surface utility lines. In order that the location of these lines and appurtenances may be determined in the event the surface openings or indicators become covered over or obscured, show by offset dimensions to two permanently fixed surface features the end of each run including each change in direction on the record drawings. Locate valves, splice boxes and similar appurtenances by dimensioning along the utility run from a reference point. Also record the average depth below the surface of each run.
b. The location and dimensions of any changes within the building structure.
c. Layout and schematic drawings of electrical circuits and piping.
d. Correct grade, elevations, cross section, or alignment of roads, earthwork, structures or utilities if any changes were made from contract plans.
e. Changes in details of design or additional information obtained from working drawings specified to be prepared or furnished by the Contractor; including but not limited to shop drawings, fabrication, erection, installation plans and placing details, pipe sizes, insulation material, dimensions of equipment, and foundations.
f. The topography, invert elevations and grades of drainage installed or affected as part of the project construction.
g. Changes or Revisions which result from the final inspection.
h. Where contract drawings or specifications present options, show only the option selected for construction on the working as-built markup drawings.
i. If borrow material for this project is from sources on Government property, or if Government property is used as a spoil area, furnish a contour map of the final borrow pit/spoil area elevations.
j. Systems designed or enhanced by the Contractor, such as HVAC controls, fire alarm, fire sprinkler, and irrigation systems.
k. Changes in location of equipment and architectural features.
l. Modifications.
m. Actual location of anchors, construction and control joints, etc., in concrete.
n. Unusual or uncharted obstructions that are encountered in the contract work area during construction.
o. Location, extent, thickness, and size of stone protection particularly where it will be normally submerged by water.
3.2 RECORD DRAWINGS
3.3 OPERATION AND MAINTENANCE MANUALS
Provide project operation and maintenance manuals as specified in Section 01 78 23 OPERATION AND MAINTENANCE DATA. Provide four electronic copies of the Operation and Maintenance Manual files.
Submit to the Contracting Officer for approval within 30 calendar days of the Beneficial Occupancy Date (BOD). Update and resubmit files for final approval at BOD.
3.4 CLEANUP
Leave premises "broom clean." Clean interior and exterior glass surfaces exposed to view; remove temporary labels, stains and foreign substances; polish transparent and glossy surfaces; vacuum carpeted and soft surfaces.
Clean equipment and fixtures to a sanitary condition. Replace filters of operating equipment. Clean debris from roofs, gutters, downspouts and drainage systems. Sweep paved areas and rake clean landscaped areas. Remove waste and surplus materials, rubbish and construction facilities from the site..
The Contractor must:
A. Remove existing composition shingles, felt and any rotted decking.
B. Detach lighting rods at ridge and reinstall on metal roof with galvanic insulating pads at terminal bases.
C. Roofing materials must comply with local building codes and have the following requirements:
a. UL 263 Fire Resistant Rating
b. UL2218, Class 4 Hail Resistant Rating
c. UL 580, Class 90, 100 mph Wind Rating
d. ASTM E-1680 Air Penetration Approved
e. ASTM E-1646 Water Infiltration Approved
D. Minimum seam height 1.5” and uniform across the roof
E. Minimum 24-gage panel thickness, 16” or equivalent, seam spacing maximum
F. Metal roof panels to be factory fabricated or fabricated onsite
G. Metal roof panels to be painted with color TBD after award
H. Install minimum 15 lb. self-adhesive insulation sheets and valley metal.
I. Install decking as needed to replace water damaged sections
J. Install drip edging and z-bar flashing
K. Install flashing at penetrations.
L. Caulk parapet wall flashing at seams.
M. Install snow/ice retention products.
N. Caulk parapet wall flashing at seams.
3. DELIVERABLES
The Contractor must provide all deliverables listed in the table below within the time frame indicated.
Number Item Quantity Due Date Deliver To Reference
Sexual Assault and Sexual Harassment Training
1 per contractor employee
Within 30 days of award
Contracting Officer
NAM 1330-
52.222-70
Security Processing Requirements for Contractor/ Subcontractor Personnel Working on a Department of Commerce Site
1 per contractor employee
As determined Contractor/ Subcontractor personnel shall undergo security processing
Government Point of Contact
CAR 1352.237-
3 Roof Design 1 Each 21 days from NTP Government Point of Contact
PWS Section 6 Submittals
4 Safety Data Sheet 1 Each Before Start of Work Government Point of Contact
PWS Safety & Security Section
6 Invoice 1 Each After Completion of Work
Government Point of Contact PWS Section 9
Other deliverables described in this Statement of Work may be required to be submitted within a different time frame that shall be adhered to by the Contractor. If the Contractor has any questions as to due dates of deliverables, the Contractor shall discuss with the Government Point of Contact.
4. SAFETY AND SECURITY
All rules concerning safety, not smoking and the security of the property must be observed at all times.
Safety Data Sheet (SDS) must be provided by the Contractor to the Government Point of Contact, where the information will be kept on file in accordance with applicable guidelines of the OSHA Hazard Communications Standard. Requirements pertaining to recordkeeping will be strictly followed.
Working in Occupied Building
The Contractor will be working in an existing building which is occupied. Do not enter the building without prior approval of the Government Point of Contact. The existing buildings and their contents must be kept secure at all times.
Provide dust covers or protective enclosures to protect existing work that remains, during the construction period.Leave attached equipment in place, and protect it against damage, or temporarily disconnect, relocate, protect, and reinstall it at the completion of the work.
5. WORKING HOURS
Regular working hours are from 0700 to 1700 Monday through Friday except Federal holidays and other days specifically designated by the designated representative. “Regular Working Hours” means hours a Contractor can expect to be allowed to perform work on site, or be able to contact the office. Anything outside regular working hours must be done by permission of the Government Point of Contact.
Observance of Legal Holidays and Site Closure Information The Contractor shall observe any federal holidays set forth in the Department of Labor Wage Determinations, if the holiday falls within the period of performance of this contract.
When any holiday falls on a Saturday, the preceding Friday is observed; when any holiday falls on a Sunday, the following Monday is observed. All personnel assigned to this contract shall limit their observation of holidays to those set forth above.
In each instance, the Contractor agrees to continue to provide sufficient personnel to perform requirements of any critical tasks already in operation or scheduled, and shall be guided by the instructions issued by the Government Point of Contact. In the event of a site dismissal or closure due to weather, emergency or other circumstances, the Contractor is instructed to contact the Government Point of Contact for guidance.
Contractor agrees to observe all Federal Holidays, and any other day off work designated by Federal Statute, Executive Order, or Presidential Proclamation. Federal Holidays include: New Year's Day, Birthday of Martin Luther King, Jr., Washington’s Birthday, Memorial Day, Juneteenth National Independence Day, Independence Day, Labor Day, Columbus Day, Veterans Day, Thanksgiving Day, and Christmas Day.
If a holiday falls on a Saturday, for most Federal employees, the preceding Friday will be treated as a holiday for pay and leave purposes. (See 5 U.S.C. 6103(b).) If a holiday falls on a Sunday, for most Federal employees, the following Monday will be treated as a holiday for pay and leave purposes. (See Section 3(a) of Executive Order 11582, February 11, 1971.) See also our Federal Holidays – "In Lieu Of" Determination Fact Sheet at https://www.opm.gov/policy-dataoversight/pay-leave/work-schedules/fact-sheets/Federal- Holidays-In-Lieu-Of-Determination
6. PERIOD OF PERFORMANCE
Completion of this project shall be no later than 60 days from the Notice to Proceed. If any delays are expected, the Contractor shall notify the Government Point of Contact as soon as possible to coordinate the modification to the schedule.
7. PLACE OF PERFORMANCE
Nashville National Weather Service Weather Forecast Office 500 Weather Station Road Old Hickory, TN 37138-1145
8. INVOICING
The Contractor will invoice once all work is completed and accepted and shall submit the invoice through the Invoice Processing Platform (IPP) website. The invoice shall include:
a. Name and address of the contractor, which must be the same as that on the Purchase Order
b. Invoice date and invoice number
c. Purchase Order number and associated line-item number from the Purchase Order https://www.opm.gov/policy-dataoversight/pay-leave/work-schedules/fact-sheets/Federal-Holidays-In-Lieu-Of-Determination https://www.opm.gov/policy-dataoversight/pay-leave/work-schedules/fact-sheets/Federal-Holidays-In-Lieu-Of-Determination
9. GOVERNMENT POINT OF CONTACT
To be provided in Award.