This is Amendment 0001 to solicitation 1305M225Q0027 for NEXRAD Optical Encoders, issued by NOAA's EAD-NWS office in Norfolk, VA. The amendment provides responses to four vendor questions about the optical encoder requirements.
The government clarifies that the encoders are custom manufactured to specifications rather than brand-specific, confirms that companies previously approved for first article testing need only propose 40 production units for Ordering Period 1, addresses a vendor's proposal to incorporate microprocessor/programmable logic changes to the Farrand Opto Encoders PN 20890-1 (stating changes can be proposed but aren't guaranteed to work until tested), and confirms that timing diagram specifications on page 3 of the SOW take precedence over Drawing 14636-5017. The amendment's effective date is February 13, 2025, and the original solicitation date was January 29, 2025.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment 0002.pdf | ||
| Amendment 0003.pdf | ||
| Statement_of_Work.pdf | ||
| Pricing_Schedule.xlsx | XLSX spreadsheet | |
| Sol_1305M225Q0027.pdf | ||
| Instructions_for_Shipment.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
1305M225Q0027 x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
EAD-NWS
NORFOLK VA 23510
FED BLDG 200 GRANBY ST SUITE 815
EAD-NWS
02/13/20250001
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
01/29/2025
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
SEE CONTINUATION PAGE
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
KEVIN J. BUUM
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
1305M225Q0027 0001
SF 30 Continuation Page
A. This modification incorporates the following changes:
1. Provide answers to the following questions:
VENDOR QUESTION GOVERNMENT RESPONSE
1. Could you confirm the preferred brand or manufacturer of the Optical Encoders?
These are custom manufactured to the specifications and are not brand name specific.
2. Could you confirm the quantity if a company has already been approved for first article testing (FAT) per Note 1 of the pricing schedule: “Offerors that have previously received first article acceptance from the ROC for these optical encoders shall propose only the unit price for a quantity of 40 production units in Ordering Period 1”
Yes, the quantity is 40 production units if a company has been approved for first article testing (FAT) for Ordering Period 1.
3. Historically NOAA has purchased Farrand Opto Encoders PN 20890-1. We would like to propose replacing the legacy components supporting the output interface and incorporate a microprocessor and/or programmable logic that would make this PN more manufacturable and increase reliability. Are we at liberty to incorporate these changes?
Your company can incorporate those proposed changes into your Technical Approach (for the 1st article test proposal), but the Government is unable to guarantee those changes will actually work in the system and may not be viable until we test them.
4. Can you provide clarification regarding the disparity between the timing diagram on page 3 of the Statement of Work (SOW) and timing diagram on page 7 of PN Drawing 14636-5017?
The correct specifications for the timing diagram are on page 3 of the SOW. Drawing 14636-5017 will be updated in the near future.