1305M223QNMAN01727_A0004.pdf

PDF 283 KB Posted

Attached to
Telescoping Crane for the NOAA Ship Nancy Foster
Solicitation number
1305M223QNMAN01727
Issued by

About this file

This document is an amendment to a solicitation for the construction and installation of a telescoping crane for the NOAA Ship Nancy Foster. The amendment includes the revised request for quotation, specification revision 1, and answers inquiries from interested parties. The National Oceanic and Atmospheric Administration (NOAA) within the Department of Commerce requires the telescoping crane to meet ABS SVR geometric properties and requirements. The crane must be installed during the ship's regularly scheduled maintenance period in 2024, though installation is not part of this requirement and the contractor will only oversee and direct the installation phase. The response deadline and award date are not specified.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1

1. CONTRACT ID CODE

I

PAGE OF PAGES

I

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER

5. PROJECT NUMBER (If applicable)

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE I

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) SA. AMENDMENT OF SOLICITATION NUMBER

□ SB. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

CODE I FACILITY CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

D The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers D is extended. D is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning _____ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor D is not D is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in Item SA or 1 OA, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED

(Signature of person authorized to sign)

Previous edition unusable

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16B. UNITED STATES OF AMERICA 16C. DATE SIGNED

(Signature of Contracting Officer)

STANDARD FORM 30 (REV.11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

…continued from Block 14.

1. Question: Will be the electrical standards they use in Europe meet IEC International

Standards, as opposed to NEMA or ASTM standards?

Answer: IEC International Standards, as opposed to NEMA or ASTM standards, are acceptable.

2. Question: In lieu of API, will the Government be willing to accept the applicable European

Standards?

Answer: The Government will accept EN 13852 (latest revision) as a substitute for API-2C.

Clarification: Please note that installation is not part of this requirement. Only oversight and direction during the installation phase. Installation will be completed during the ship's regularly scheduled maintenance period in 2024.

Check Box1: Off
Check Box2: Off
Check Box3: Off
Check Box4: Yes
Check Box5: Yes
Check Box6: Off
Check Box7: Off
Check Box8: Off
Check Box9: Off
Check Box10: Off
Check Box11: Yes
Text12: A0004
Text13: 12/13/2022
Text14: NM-AN2120-22-01727
Text16: 1
Text17: 2
Text18: AJ930073
Text19: NOAA/ERAD

200 GRANBY STREET

NORFOLK, VA 23510

Jessica Loftus Jessica.Loftus@noaa.gov

Text20: See Block 6
Text21:
Text22: 1305M223QNMAN01727
Text23: 11/14/2022
Text24:
Text25:
Text26: 1
Text27: 1
Text28: Telescoping Crane for the NOAA Ship Nancy Foster

This amendment is being issued to include the REVISED RFQ, Specification Rev 1, and to answer inquiries from Interested Parties.