| File | Type | Posted |
|---|---|---|
| 03 STATEMENT OF WORK NCNT2000-21-00644_Rev1.pdf | ||
| 05 Contractor Past Performance Reference Sheet.pdf | ||
| 02 OPEN MARKET CONTRACT CLAUSES.pdf | ||
| 01 RFQ combined.pdf | ||
| 04 WD format.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
Questions and Answers Solicitation 1305M2-21-Q-00644, Amendment 0001
Vendor Question 1 Page 7 of 22 (of the Statement of Work) states contractor shall furnish all vehicles, vessels, equipment, tools, materials, and supplies necessary to perform the tasks specified in this SOW. Additionally, page 19 of 22 details consumables such as cleaning materials and supplies, lubricants, glues, sealants, adhesives, caulks, cleaners, wire ties, wire connectors, fuses, light bulbs, electrical wire, misc. screws and fasteners. (Note, screws and fasteners can be broad and costly.) Are these items out of pocket to the contractor or will the contractor be reimbursed for these items if receipts are provided?
Government Responses to Vendor Question 1 Standard items such as cleaning materials and supplies, lubricants, glues, sealants, adhesives, caulks, cleaners, wire ties, wire connectors, fuses, light bulbs, electrical wire, misc. screws and fasteners (emphasis on miscellaneous) would be out of pocket to the contractor as these are simply the cost of operational expenses. When we require specific hardware for repairs or installation we will supply these to the contractor.
Vendor Question 2 Additional items required for the contractor to provide are on page 19 of 22 (of the Statement of Work) which include all 316L stainless steel replacement fasteners, brackets, and clamps, marine quality treated lumber, and PVC or metallic conduit. Again, brackets, clamps, etc. are broad terms that could be specialized parts. Are these items out of pocket to the contractor or will the contractor be reimbursed for these items if receipts are provided?
Government Responses to Vendor Question 2 Same answer as number 1. If we require specific hardware for repairs or installation we will supply these to the contractor.
Vendor Question 3 Page 8 of 22 (of the Statement of Work) mentions the Pre-trip meeting and a least seven meetings that the contractor shall request and participate in. Is this a typo referred to seven days? Are the seven meetings mandatory?
Government Responses to Vendor Question 3 This is a typographical error and should read: “The Contractor shall request, and participate in, a Pre-Trip Meeting with the COR and TR at least seven (7) days prior to the beginning of the field trip for each visit.” YES, these meetings are mandatory.
Vendor Question 4 Page 11 of 22 (of the Statement of Work) notes in the deliverables that a monthly report is required by the 10th of each month. Is this necessary if no service or maintenance was required during particular month? Would the eSite, maintenance, and real-time reports suffice?
Government Responses to Vendor Question 4 If there is no maintenance in a given month, a response in the TOMIS entry for that month’s report stating that no maintenance was performed, will suffice.
Vendor Question 5 Page 17 and 18 of 22 (of the Statement of Work) states the items that the government will furnish on an “as needed” basis. Will the contractor receive any of the government furnished property ahead as a standard to keep in stock? YES (a spares kit will be supplied to the Contractor). If so, will the contractor be required to provide a monthly inventory account as stated on page?
Government Responses to Vendor Question 5
YES.
Vendor Question 6 The price sheet details “base year, option year one, option year two, and option year three.” With the uncertain world economy, do the optional years need to be priced out now or can this information be provided at the end of the base year?
Government Responses to Vendor Question 6 Option years must be priced within the response to the solicitation.
Vendor Question 7 The solicitation refers to various software. Will all the necessary software be provided free of charge?
Government Responses to Vendor Question 7
YES.
Vendor Question 8 The second to last paragraph on page 9 of 22 (of the Statement of Work) discusses replacing batteries, solar panels, I-beams, sleds, etc. Please confirm all the items listed in the paragraph will be provided to contractor.
Government Responses to Vendor Question 8.
Yes, these items will be provided to Contractor, if required for a repair.
Vendor Question 9 The solicitation refers to the TOMIS several times. Will training be provided?
Government Responses to Vendor Question 9
YES.
Vendor Question 10 Is there any costs associated with TOMIS training?
Government Responses to Vendor Question 10
NO.
Vendor Question 11 The rate sheet description line items details buoy mounted current meter but where is the line item for the semi-annual maintenance checks for station locations listed in Appendix A?
Government Responses to Vendor Question 11 Only the buoy mounted systems have semi-annual maintenance. All other stations are unscheduled maintenance only (e.g. as-needed). In other words, please note that the unscheduled maintenance is not guaranteed.
| topmostSubform[0]: |
| Page1[0]: |
| AmendmentNo[0]: Amendment 0001 |
| Code[0]: |
| Code[1]: |
| AccountingData[0]: |
| A13[0]: |
| C13[0]: |
| D13[0]: |
| NameandTitleSigner[0]: |
| NameandTitleOfficer[0]: |
| Description[0]: |
The Request for Quotations is hereby amended as follows:
1. The Quote Submission Date is changed to 11am, EDT, June 22, 2021.
2. Questions and Answers are provided on page two of this amendment.
3. All other terms and conditions remain unchanged.
| FacilityCode[0]: |
| Code[2]: |
| IssuedBy[0]: NOAA/Eastern Acquisition Division |
200 Granby Street Suite 865 Norfolk, VA 23510
| NameandAddress[0]: |
| AdministeredBy[0]: |
| ContractIDCode[0]: |
| ReqNumber[0]: |
| AmendmentNo[1]: 1305M2-21-Q-00644 |
| ModificationNo[0]: |
| ProjectNo[0]: |
| Page[0]: 1 |
| Pages[0]: 3 |
| EffectiveDate[0]: 06/17/2021 |
| Dated9B[0]: |
| Dated10B[0]: |
| CheckBox9[0]: Off |
| CheckBox10[0]: Off |
| CheckBox11[0]: 1 |
| CheckBox13A[0]: Off |
| CheckBox13B[0]: Off |
| CheckBox13C[0]: Off |
| CheckBox13D[0]: Off |
| IsNot[0]: Off |
| Is[0]: 1 |
| Extended[0]: 1 |