AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICAITON NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicble)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICIATION NO.

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a)By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPIRATION DATA (If required)

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc. ) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION ( Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

NSN 7540-01-152-8070

Previous edition unusable

CONTINUATION PAGE

PAGE 2 OF 2 1305M219QNMAN0163/A0001

1305M219QNMAN0163

Amendment A0001

Question from Vendors in Regard to RFQ 1305M219QNMAN0163

1) Can you provide the current service bulletin level of the fleet?

Response: Attachment “SB Levels.pdf”

2) Under Section A.2 / Engine Build Requirements/ page 10; it reads CT Van e Class 13.20 with New PMA or P&WC Only. Can you verify this is a typo?

Response: Yes, it is a typo. The line should read "...New PMA or Pratt & Whitney

(PWC)..."

3) Is ITEM NO. 0001 asking for the price to include all information under section A. 2 of the

Statement of Work or is this amount to be what is defined as the Firm Fixed Price on page 8 under section A. 2? The same question on ITEM NO. 1001, 2001, and 3001.

Response: Item 0001, 1001, 2001 and 3001 is asking for a Firm Fixed Price (FFP) for the Inspection, Overhaul and Repair to zero-time as detailed in A.2, paragraph one. However, A.2, paragraphs two, three and four, detail/define repairs (Over and Above items) outside the FFP of 0001, 1001, 2001 and 3001.

4) ITEM NO. 1002 mentions CLIN 0004. Where is 0004?

Response: Corrected in RFQ (Rev.1)

5) ITEM NO. 2002 mentions CLIN 0006. Where is 0006?

6) ITEM NO. 3002 mentions CLIN 0008. Where is 0008?

7) Can you please verify the NTE amounts that are pre-filled are lined up with the correct Item

No?

Response: NTE amounts and alignment are verified; however, the NTE amounts are for planning purposes. The evaluated price will be the Labor Rates.

End of Amendment 0001

topmostSubform[0]:
Page1[0]:
IDCode[0]:
Page[0]: 1
Pages[0]: 2
AmendNo[0]: A0001
EffDate[0]: Jul 9, 2019
ReqNo[0]: NMAN6000-19-00818
ProjNo[0]:
IssCode[0]:
IssuedBy[0]: NOAA/ERAD

200 GRANBY STREET

NORFOLK VA 23510

AdmCode[0]:
AdminBy[0]: See Block 6
ContName[0]:
ContStrt[0]:
ContCnty[0]:
ContSt[0]:
ContZIP[0]:
Code[0]:
FacCode[0]:
SolChgYs[0]: Yes
SolChgNo[0]: Off
SolAmdNo[0]: 1305M219QNMAN0163
AmendDate[0]: Jun 12, 2019
ModNo[0]:
ModDate[0]:
NoCopies[0]:
Amended[0]: Yes
OffrExt[0]: Off
OffrNoEx[0]: No
ApprData[0]:
ChgeOrd[0]: Off
ChgeOrder[0]:
Modify[0]: Off
SuppAgre[0]: Off
SuppAuth[0]:
ModOthr[0]: Off
OthrSpec[0]:
NoReq[0]: Yes
Require[0]: Off