13-3.1 SOW P-005458 - AMAS.docx

DOCX document 50 KB Posted

Attached to
Asbestos and Mold Abatement Services
Solicitation number
P-005458
Issued by
Philadelphia County, Philadelphia City, Pennsylvania

About this file

This is a Statement of Work for Solicitation P-005458 issued by the Philadelphia Housing Authority (PHA), a Pennsylvania-based agency responsible for managing approximately 80,000 residents across 30 conventional developments and 5,500 scattered site units. PHA seeks a qualified vendor to provide asbestos abatement and mold remediation services across all PHA-owned properties in accordance with the City of Philadelphia Asbestos Control Regulation and applicable federal and state protocols. The contractor must possess Pennsylvania and City of Philadelphia certification as an asbestos abatement company with demonstrated experience in public schools, residential, and commercial buildings. Required qualifications include OSHA training and current certifications for confined space work, mold remediation training per ANSI/IICRC S520 standards, and access to specialized equipment including decontamination stations, negative air pressure systems, and containment materials. The scope encompasses asbestos projects ranging from small to major classifications, including NESHAP-level work, with the contractor responsible for all regulatory notifications, waste disposal in accordance with federal and local regulations, and coordination with PHA's third-party Asbestos Project Inspector and air monitoring firm.

Pricing is structured on a unit-cost basis with separate line items for small, minor, and major asbestos projects categorized by material type (pipe insulation/fireproofing removal measured in linear feet and floor tile removal measured in square feet), project management hourly rates, and mold removal services differentiated by area size (less than 10 square feet and greater than 10 square feet). The bid sheet establishes pricing for a Base Year 1 and 2 period, followed by three separate Option Year pricing schedules, allowing for contract term flexibility. Monthly invoicing is required with itemized descriptions of work performed. PHA's operating budget exceeds $300 million annually with additional Section 8 revenues and comprehensive grant rehabilitation activity of approximately $75 million per year, providing substantial funding capacity for abatement services from federal HUD sources and other federal, state, and private funding streams.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation P-005458 Abatement Services

Asbestos and Mold Abatement Contractor

FOR

SOLICITATION NUMBER P-005458

Abatement Services

I. INTRODUCTION

The Philadelphia Housing Authority (PHA) is organized under the Laws of the Commonwealth of Pennsylvania to develop, acquire, lease and operate low-rent housing programs. The PHA is the largest housing agency in the commonwealth, and the fourth largest in the Nation. It has approximately 80,000 residents in 30 conventional developments and approximately 5,500 scattered site units. The US Department of Housing and Urban Development (HUD) is the primary funding agency for the Authority's housing operations, housing choice program, as well as all new construction, modernization and rehabilitation of the Philadelphia Housing Authority's housing units. PHA has an operating budget in excess of $300 million/year plus additional Section 8 revenues and comprehensive grant rehabilitation activity of approximately $75 million per year. PHA also receives Federal Title, Office of Aging, and other Federal, State, and private funding for operation of various social services for public housing residents.

PHA reserves the right to procure supplies or services on behalf of its affiliated entities and subsidiaries including several limited partnerships (Related Entities). In such case, PHA will generally advise the Contractor that the contract or task/delivery order is being issued on behalf of a Related Entity and provide any special instructions. However, failure of PHA to do so does not negate the Contractor's obligation to provide the supply or service ordered.

II. PURPOSE

PHA has determined a need for a vendor that is highly trained with demonstrated experience to perform mold remediation/ abatement and asbestos abatement (removal) throughout all properties owned by the Philadelphia Housing Authority. Asbestos abatement will be based off of The City of Philadelphia Asbestos Control Regulation.

III. MINIMUM QUALIFICATIONS

Firms submitting proposals must meet the minimum qualifications listed below:

· Proposers must meet all minimum submission requirements set forth in this statement of work.

· Proposers must have the expertise and knowledge, and regularly engaged in the containment, remediation, demolition and abatement of mold

· Proposers must be trained, certified, and experienced in mold remediation in accordance with industry standards including ANSI/IICRC S520.

· The competent person shall have completed OSHA, mold abatement and remediation training, have met all training requirements and have all required and current documentation as such.

· Proposers must have access to all necessary equipment and have the organizational capacity and technical competence necessary to do the work properly and expeditiously following local, federal and State abatement protocol including The City of Philadelphia Asbestos Control Regulation AND School District of Philadelphia.

· Proposers must possess valid and current accreditations for work in confined spaces (per OSHA 29 CFR 1910.146) be a Certified Asbestos Abatement Company in the State of Pennsylvania and City of Philadelphia with experience of asbestos abatement for Public Schools (School District of Philadelphia), residential and commercial buildings and adhering to The Philadelphia Asbestos Control Regulations.

IV. DESCRIPTION OF WORK

A. GENERAL – Asbestos Abatement The Asbestos Abatement Contractor shall be used for asbestos projects and cleanup of fiber release episodes. The contractor is also responsible for the proper disposal of all asbestos containing waste. Asbestos abatement protocol will be determined by Project Standards via City of Philadelphia’s Asbestos Control Regulation for friable and non-friable ACM’s and PACM’s in vacant or occupied buildings. Project Standards range from Small to Major (including NESHAP) Asbestos Projects. The Asbestos Abatement Contractor selected shall maintain a file containing all submittals for performance of asbestos removal. These submittals include: regulatory notification, equipment lists, work procedures, documentation of worker training and medical examination, respiratory protection plan, landfill and transporter of waste and insurance certificate. Required submittals shall be reviewed by the Asbestos Consultant prior to performance of the abatement work. In addition, PHA will be hiring a 3rd party Asbestos Project Inspector (API) and asbestos/air monitoring firm for abatement activity oversight and conducting air sampling.

The Asbestos Abatement contractor will be responsible for the following:

1. Necessary equipment for asbestos abatement activities

a. -Decon stations, Asbestos dumpster, Asbestos signage, PPE, containment, glove bags, flame-retardant poly, dry-ice, negative air pressure, scaffolding, power tools/etc

2. Submitting necessary permits and asbestos notifications to the Department of Public Health (Air Management Services)

3. Notifying PHA and API of any emergency items immediately.

4. Thoroughly abate asbestos containing material and have efficient post abatement activities for PASSING air clearance and visual by API for all Project size standards (small to major Projects)

5. Must dispose waste in accordance to Federal, Local and State regulations

B. General – Mold Abatement The contractor shall provide removal and cleaning of various items, building components that are showing visible signs of microbiological contamination (i.e., mold/fungal growth/ bacterial contamination), excessive water saturation or moisture intrusion.

The Mold Abatement contractor will be responsible for the following:

1. All removal and cleanup activities will be performed under full containment of the work area. Personnel protective equipment will include a respirator with HEPA air filter, disposable suit, gloves and goggles.

2. Determine the extent of mold contamination and the underlying cause

3. Obtain necessary permits for work

4. Must dispose waste in accordance to Federal, Local and State regulations

5. Contract must notify PHA for Lead Paint Component Status that will be disturbed during removal per EPA’s RRP Rule

V. PRICING/BILLING

A. Pricing The bid shall include an hourly rate plus quantity of ACM abatement based on Small to Major Asbestos projects. This price must be inclusive of all labor and overhead cost.

B. Billing/Invoicing Invoices shall be submitted on a monthly basis. The invoices should include the list of areas of ACM abatement with quantities.

C. Bid Sheet Unit pricing Base Year 1 and 2:

· Small Asbestos Project for ACM pipe insulation/ fireproofing removal (MAX. 3LF) $___________

· Small Asbestos Project for ACM floor tile removal (MAX. 12SF) $___________

· Minor Asbestos Project for ACM pipe insulation/ fireproofing removal (min. 3LF)$___________
· Minor Asbestos Project for ACM floor tile removal (min. 12SF)$___________
· Major Asbestos Project for ACM pipe insulation/ fireproofing removal (min. 40LF)$___________
· Major Asbestos Project for ACM floor tile removal (min. 80LF)$___________
· Project Managementper hour $___________
· Mold removal – less than 10SF$___________
· Mold removal – more than 10SF$___________

Unit pricing Option Year 1

· Small Asbestos Project for ACM pipe insulation/ fireproofing removal (MAX. 3LF) $___________

· Small Asbestos Project for ACM floor tile removal (MAX. 12SF) $___________

· Minor Asbestos Project for ACM pipe insulation/ fireproofing removal (min. 3LF)$___________
· Minor Asbestos Project for ACM floor tile removal (min. 12SF)$___________
· Major Asbestos Project for ACM pipe insulation/ fireproofing removal (min. 40LF)$___________
· Major Asbestos Project for ACM floor tile removal (min. 80LF)$___________
· Project Managementper hour $___________
· Mold removal – less than 10SF$___________
· Mold removal – more than 10SF$___________

Unit pricing Option Year 2

· Small Asbestos Project for ACM pipe insulation/ fireproofing removal (MAX. 3LF) $___________

· Small Asbestos Project for ACM floor tile removal (MAX. 12SF) $___________

· Minor Asbestos Project for ACM pipe insulation/ fireproofing removal (min. 3LF)$___________
· Minor Asbestos Project for ACM floor tile removal (min. 12SF)$___________
· Major Asbestos Project for ACM pipe insulation/ fireproofing removal (min. 40LF)$___________
· Major Asbestos Project for ACM floor tile removal (min. 80LF)$___________
· Project Managementper hour $___________
· Mold removal – less than 10SF$___________
· Mold removal – more than 10SF$___________

Unit pricing Option Year 3

· Small Asbestos Project for ACM pipe insulation/ fireproofing removal (MAX. 3LF) $___________

· Small Asbestos Project for ACM floor tile removal (MAX. 12SF) $___________

· Minor Asbestos Project for ACM pipe insulation/ fireproofing removal (min. 3LF)$___________
· Minor Asbestos Project for ACM floor tile removal (min. 12SF)$___________
· Major Asbestos Project for ACM pipe insulation/ fireproofing removal (min. 40LF)$___________
· Major Asbestos Project for ACM floor tile removal (min. 80LF)$___________
· Project Managementper hour $___________
· Mold removal – less than 10SF$___________
· Mold removal – more than 10SF$___________

C-3 Solicitation No. P-005458 – Abatement Services image1.png