Lake Whitstine Weir draft specifications
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Final_Channel_Drawings_Signed_6.pdf | ||
| Final_Channel_Drawings_Signed_7.pdf | ||
| Final_Channel_Drawings_Signed_9.pdf | ||
| Final_Channel_Drawings_Signed_4.pdf | ||
| Final_Channel_Drawings_Signed_8.pdf | ||
| Final_Channel_Drawings_Signed_2.pdf | ||
| Final_Channel_Drawings_Signed_3.pdf | ||
| Final_Channel_Drawings_Signed_1.pdf | ||
| Final_Channel_Drawings_Signed_5.pdf | ||
| Whitstine_Weir_Final_Drawings_Signed.pdf | ||
| Departee_Channel_SpecPackage_Signed2.pdf |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
2–1(210–VI–NEH, May 2001)
1. Scope The work consists of clearing and grubbing and disposal of trees, snags, logs, brush, stumps, shrubs, and rubbish from the designated areas.
2. Protection of existing vegetation Trees and other vegetation designated to remain undisturbed shall be protected from damage throughout the dura-tion of the construction period. Any damages resulting from the contractor's operations or neglect shall be repaired by the contractor.
Earthfill, stockpiling of materials, vehicular parking, and excessive foot or vehicular traffic shall not be allowed within the drip line of vegetation designated to remain in place. Vegetation damaged by any of these or similar ac-tions shall be replaced with viable vegetation of the same species, similar condition, and like size unless otherwise approved by the contracting officer.
Any cuts, skins, scrapes, or bruises to the bark of the vegetation shall be carefully trimmed and local nursery ac-cepted procedures used to seal damaged bark.
Any limbs or branches 0.5 inch or larger in diameter that are broken, severed, or otherwise seriously damaged during construction shall be cut off at the base of the damaged limb or branch flush with the adjacent limb or tree trunk. All roots 1-inch or larger in diameter that are cut, broken, or otherwise severed during construction opera-tions shall have the end smoothly cut perpendicular to the root. Roots exposed during excavation or other opera-tions shall be covered with moist earth or backfilled as soon as possible to prevent the roots from drying out.
3. Marking The limits of the area(s) to be cleared and grubbed will be marked by stakes, flags, tree markings, or other suitable methods. Trees to be left standing and uninjured will be designated by special markings placed on the trunk about 6 feet above the ground surface.
4. Clearing and grubbing All trees not marked for preservation and all snags, logs, brush, stumps, shrubs, rubbish, and similar materials shall be cleared from within the limits of the designated areas. Unless otherwise specified, all stumps, roots, and root clusters that have a diameter of 1 inch or larger shall be grubbed out to a depth of at least 2 feet below subgrade for concrete structures and 1 foot below the ground surface at embankment sites and other designated areas.
5. Disposal All materials cleared and grubbed from the designated areas shall be disposed of at locations shown on the draw-ings or in a manner specified in section 7. The contractor is responsible for complying with all local rules and regu-lations and the payment of any and all fees that may result from disposal at locations away from the project site.
6. Measurement and payment Method 1—For items of work for which specific units prices are established in the contract, the cleared and grubbed area is measured to the nearest 0.1 acre. Payment for clearing and grubbing is made for the total area within the designated limits at the contract unit price. Such payment will constitute full compensation for all labor, equipment, tools, and all other items necessary and incidental to the completion of the work.
Construction Specification 2—Clearing and Grubbing
2–2 (210–VI–NEH, May 2001)
Method 2—For items of work for which specific unit prices are established in the contract, the length of the cleared and grubbed area is measured to the nearest full station (100 feet) along the line designated on the drawing or identified in the specifications. Payment for clearing and grubbing is made for the total length within the des-ignated limits at the contract unit price. Such payment will constitute full compensation for all labor, equipment, tools, and all other items necessary and incidental to the completion of the work.
Method 3—For items of work for which specific unit prices are established in the contract, each tree, stump, and snag having a diameter of 4 inches or larger and each log having a diameter of 4 inches or larger and a length of 10 feet are measured before removal. The size of each tree and snag is determined by measuring its trunk at breast height above the natural ground surface. The size of each log is determined by measuring the butt and by measur-ing its length from butt to tip. The size of each stump is measured at the top. Diameter is determined by dividing the measured circumference by 3.14.
Payment for clearing and grubbing of each tree, stump, and snag having a diameter of 4 inches or larger and each log having a diameter of 4 inches or larger and a length of 10 feet or larger is made at the contract unit price for its size designation as determined by the following schedule:
Measured diameter Size designation
(in) (in)
4 to 8 6 8 to 12 10 12 to 24 18 24 to 36 30 36 to 60 48 Over 60 60
The sum of such payments shall constitute full compensation for clearing and grubbing (including the clearing and grubbing of smaller trees, stumps, snags, logs, brush, shrubs, and roots), applicable permits and associated fees, and rubbish removal. Such payment shall constitute full compensation for all labor, equipment, tools, and all other items necessary and incidental to the completion of the work.
Method 4—For items of work for which specific lump sum prices are established in the contract, payment for clearing and grubbing is made at the contract lump sum price. Such payment shall constitute full compensation for all labor, equipment, tools, and all other items necessary and incidental to the completion of the work.
All Methods—The following provisions apply to all methods of measurement and payment. Compensation for any item of work described in the contract, but not listed in the bid schedule will be included in the payment for the item of work to which it is made subsidiary. Such items and the items to which they are made subsidiary are identi-fied in section 7.
7. Items of work and construction details
NRCS—July 2018 Clearing and Grubbing AR—Whitstine Weir 2—3
7. ITEMS OF WORK AND CONSTRUCTION DETAILS
Items of work to be performed in conformance with this specification and construction details therefore are:
A. Bid Item 2, Clearing and Grubbing
1) This item consists of clearing and grubbing the ingress‐egress routes, the footprint area of the weir, the channel transitions zones, and access lanes alongside the creek as shown in the drawings. Clearing and grubbing of the entire area of the work limits is not required or desired.
Clearing and grubbing area outside the limits shown in the drawings may be performed with the approval of the Engineer.
2) In Section 5, Disposal, all burnable materials may be piled, burned, and buried onsite, as consistent with law. The ultimate disposal of all materials shall be the responsibility of the Contractor. The drawings show the approximate location of one burn and bury site. Additional sites may be utilized with the approval of the Engineer.
3) In Section 6, Measurement and Payment, Method 4 will apply.
5–1(210–VI–NEH, January 2014)
The work consists of installing measures or performing work to control erosion and minimize the production of sediment and other pollutants to water and air from construction activities.
The following BioPreferred® product categories are applicable to this specification:
— mulch and compost materials
— erosion control materials
— fertilizers
— dust suppressants
— agricultural spray adjuvants
2. Material Silt fence shall conform to the requirement of Materials Specification 592, Geotextile. All other material furnished shall meet the requirements of the material specifications listed in section 8 of this specification.
3. Erosion and sediment control measures and works The measures and works shall include, but are not limited to, the following:
Staging of earthwork activities—The excavation and moving of soil materials shall be scheduled to minimize the size of areas disturbed and unprotected from erosion for the shortest reasonable time.
Seeding—Seeding to protect disturbed areas shall occur as soon as reasonably possible following completion of that earthwork activity.
Mulching—Mulching to provide temporary protection of the soil surface from erosion.
Diversions—Diversions to divert water from work areas and to collect water from work areas for treatment and safe disposition. They are temporary and shall be removed and the area restored to its near original condition when the diversions are no longer required or when permanent measures are installed.
Stream crossings—Culverts or bridges where equipment must cross streams. They are temporary and shall be removed and the area restored to its near original condition when the crossings are no longer required or when permanent measures are installed.
Sediment basins—Sediment basins collect, settle, and eliminate sediment from eroding areas from impacting properties and streams below the construction site(s). These basins are temporary and shall be removed and the area restored to its original condition when they are no longer required or when permanent measures are installed.
Sediment filters—Straw bale filters or geotextile silt fences trap sediment from areas of limited runoff. Sediment filters shall be properly anchored to prevent erosion under or around them. Silt fences shall be installed and main-tained in accordance with ASTM D6462. These filters are temporary and shall be removed and the area restored to its original condition when they are no longer required or when permanent measures are installed.
Waterways—Waterways for the safe disposal of runoff from fields, diversions, and other structures or measures.
These works are temporary and shall be removed and the area restored to its original condition when they are no longer required or when permanent measures are installed.
Construction Specification 5—Pollution Control
5–2 (210–VI–NEH, January 2014)
Other—Additional protection measures as specified in section 8 of this specification or required by Federal, State, or local government.
4. Chemical pollution The contractor shall provide watertight tanks or barrels or construct a sump sealed with plastic sheets to collect and temporarily contain chemical pollutants, such as drained lubricating or transmission fluids, grease, soaps, concrete mixer washwater, or asphalt, produced as a by-product of the construction activities. Pollutants shall be disposed of in accordance with appropriate state and Federal regulations. At the completion of the construction work, tanks, barrels, and sumps shall be removed and the area restored to its original condition as specified in sec-tion 8 of this specification. Sump removal shall be conducted without causing pollution.
Sanitary facilities, such as chemical toilets, or septic tanks shall not be located next to live streams, wells, or springs. They shall be located at a distance sufficient to prevent contamination of any water source. At the comple-tion of construction activities, facilities shall be disposed of without causing pollution as specified in section 8 of this specification.
5. Air pollution The burning of brush or slash and the disposal of other materials shall adhere to state and local regulations.
Fire prevention measures shall be taken to prevent the start or spreading of wildfires that may result from project activities. Firebreaks or guards shall be constructed and maintained at locations shown on the drawings.
All public access or haul roads used by the contractor during construction of the project shall be sprinkled or otherwise treated to fully suppress dust. All dust control methods shall ensure safe construction operations at all times. If chemical dust suppressants are applied, the material shall be a commercially available product specifically designed for dust suppression and the application shall follow manufacturer's requirements and recommendations.
A copy of the product data sheet and manufacturer's recommended application procedures shall be provided to the engineer 5 working days before the first application.
6. Maintenance, removal, and restoration All pollution control measures and temporary works shall be adequately maintained in a functional condition for the duration of the construction period. All temporary measures shall be removed and the site restored to near original condition.
7. Measurement and payment Method 1—For items of work for which specific unit prices are established in the contract, each item is measured to the nearest unit applicable. Payment for each item is made at the contract unit price for that item. For water or chemical suppressant items used for dust control for which items of work are established in section 8 of this speci-fication, measurement for payment will not include water or chemical suppressants that are used inappropriately or excessive to need. Such payment will constitute full compensation for the completion of the work.
Method 2—For items of work for which lump sum prices are established in the contract, payment is made as the work proceeds and supported by invoices presented by the contractor that reflect actual costs. If the total of all progress payments is less than the lump sum contract price for this item, the balance remaining for this item will be included in the final contract payment. Payment of the lump sum contract price will constitute full compensa-tion for completion of the work.
Method 3—For items of work for which lump sum prices are established in the contract, payment will be prorated and provided in equal amounts on each monthly progress payment estimate. The number of months used for pro-rating shall be the number estimated to complete the work as outlined in the contractor's approved construction schedule. The final month's prorate amount will be provided with the final contract payment. Payment as described will constitute full compensation for completion of the work.
5–3(210–VI–NEH, January 2014)
All Methods—The following provisions apply to all methods of measurement and payment. Compensation for any item of work described in the contract, but not listed in the bid schedule is included in the payment for the item of work to which it is made subsidiary. Such items, and the items to which they are made subsidiary, are identified in section 8 of this specification.
8. Items of work and construction details
NRCS—July 2018 Pollution Control AR—Whitstine Weir 5—4
8. ITEMS OF WORK AND CONSTRUCTION DETAILS
Items of work to be performed in conformance with this specification and construction details therefore
A. Subsidiary Item, Pollution Control
1) This item consists of the necessary measure and performance of work to control erosion and minimize the production of sediment and other pollutants to water and air from construction activities.
2) The Contractor shall develop and implement a Storm Water Pollution Prevention Plan (SWPPP) to control erosion and minimize the production of sediment and other pollutants during construction operations. The Plan shall meet the requirements of the National Pollution Discharge Elimination System (NPDES) and shall incorporate, as a minimum, the measures specified in section 3 of this specification and items shown on the drawings.
3) It is anticipated that the work limits and off‐site activities of the construction project will be eligible for automatic coverage under the General Permit No. ARR150000 administered by the Arkansas Department of Environmental Quality (ADEQ). In this case, the SWPPP should follow the format of the ADEQ template. However, it is the responsibility of the Contractor to comply with whatever rules and regulations of the NPDES that apply.
4) The SWPPP shall be submitted to the Contracting Officer for approval prior to commencing construction activities. However, NRCS approval of the SWPPP does not relieve the Contractor of responsibility of complying with all local, state, federal regulations for pollution control.
5) In Section 7, Measurement and Payment, no separate payment will be made for Pollution
Control. Compensation for this item will be included in the payment for Bid Item 1, Mobilization and Demobilization.
6–1(210–VI–NEH, January 2014)
The work consists of preparing the area for treatment; furnishing and placing seed, sprigs, mulch, fertilizer, inocu-lant, lime, and other soil amendments; and anchoring mulch in designated areas as specified.
The following BioPreferred® product categories are applicable to this specification:
— mulch and compost materials
— erosion control materials
— fertilizers
— agricultural spray adjuvants
2. Material Seed—All seed shall conform to the current rules and regulations of the state where it is being used and shall be from the latest crop available. It shall meet or exceed the standard for purity and germination listed in section 7.
Seed shall be labeled in accordance with the state laws and the U.S. Department of Agriculture rules and regula-tions under the Federal Seed Act in effect on the date of invitations for bids. Bag tag figures are evidence of purity and germination. No seed will be accepted with a test date of more than 9 months before the delivery date to the site.
Seed that has become wet, moldy, or otherwise damaged in transit or storage will not be accepted. The percent of noxious weed seed allowable shall be as defined in the current State laws relating to agricultural seeds. Each type of seed shall be delivered in separate sealed containers and fully tagged unless exception is granted in writing by the contracting officer.
Fertilizer—Unless otherwise specified, the fertilizer shall be a commercial grade fertilizer. It shall meet the standard for grade and quality specified by State law. Where fertilizer is furnished from bulk storage, the contrac-tor shall furnish a supplier's certification of analysis and weight. When required by the contract, a representative sample of the fertilizer shall be furnished to the contracting officer for chemical analysis.
Inoculants—The inoculant for treating legume seeds shall be a pure culture of nitrogen-fixing bacteria prepared specifically for the species and shall not be used later than the date indicated on the container or as otherwise specified. A mixing medium, as recommended by the manufacturer, shall be used to bond the inoculant to the seed.
Two times the amount of the inoculant recommended by the manufacturer shall be used except four times the amount shall be used when seed is applied using a hydraulic seeder. Seed shall be sown within 24 hours of treat-ment and shall not remain in the hydraulic seeder longer than 4 hours.
Lime and other soil amendments—Lime shall consist of standard ground agriculture limestone, or approved equiv-alent. Standard ground agriculture limestone is defined as ground limestone meeting current requirements of the State Department of Agriculture. Other soil amendments shall meet quality criteria and application requirements specified in section 7.
Mulch tackifiers—Asphalt emulsion tackifiers shall conform to the requirements of ASTM D 977, Specification for Emulsified Asphalt. The emulsified asphalt may be rapid setting, medium setting, or slow setting. Nonasphaltic tackifiers required because of environmental considerations shall be as specified in section 7.
Straw mulch material—Straw mulch shall consist of wheat, barley, oat or rye straw, hay, grass cut from native grasses, or other plants as specified in section 7. The mulch material shall be air-dry, reasonably light in color, and shall not be musty, moldy, caked, or otherwise of low quality. The use of mulch that contains noxious weeds is not permitted. The contractor shall provide a method satisfactory to the contracting officer for determining weight of mulch furnished.
Construction Specification 6—Seeding, Sprigging, and Mulching
6–2 (210–VI–NEH, January 2014)
Other mulch materials—Mulching materials, such as wood cellulose fiber mulch, mulch tackifiers, synthetic fiber mulch, netting, and mesh, are other mulching materials that may be required for specialized locations and conditions. These materials, when specified, must be accompanied by the manufacturer's recommendations for methods of application.
3. Seeding mixtures, sod, sprigs, and dates of planting The application rate per acre for seed mixtures, sprigs, or sod and date of seeding or planting shall be as shown on the plans or as specified in section 7.
4. Seedbed preparation and treatment Areas to be treated shall be dressed to a smooth, firm surface. On sites where equipment can operate on slopes safely, the seedbed shall be adequately loosened (4 to 6 inches deep) and smoothed. Depending on soil and mois-ture conditions, disking or cultipacking, or both, may be necessary to properly prepare a seedbed. Where equip-ment cannot operate safely, the seedbed shall be prepared by hand methods by scarifying to provide a roughened soil surface so that broadcast seed will remain in place.
If seeding is to be accomplished immediately following construction operations, seedbed preparation may not be required except on a compacted, polished, or freshly cut soil surface.
Rocks larger than 6 inches in diameter, trash, weeds, and other debris that will interfere with seeding or mainte-nance operations shall be removed or disposed of as specified in section 7.
Seedbed preparation shall be discontinued when soil moisture conditions are not suitable for the preparation of a satisfactory seedbed as determined by the contracting officer's technical representative (COTR).
5. Seeding, sprigging, fertilizing, mulching, and stabilizing All seeding or sprigging operations shall be performed in such a manner that the seed or sprigs are applied in the specified quantities uniformly in the designated areas. The method and rate of seed application shall be as specified in section 7. Unless otherwise specified, seeding or sprigging shall be accomplished within 2 days after final grading is completed and approved.
Fertilizer, lime, and other soil amendments shall be applied as specified in section 7. When specified, the fertilizer and soil amendments shall be thoroughly incorporated into the soil immediately following surface application.
The rate, amount, and kind of mulching or mesh shall be as specified in section 7. Mulches shall be applied uni-formly to the designated areas. They shall be applied to areas seeded not later than 2 working days after seeding has been performed. Straw mulch material shall be stabilized within 24 hours of application using a mulch crimper or equivalent anchoring tool or by a suitable tackifier. When the mulch crimper or equivalent anchoring tool is used, it shall have straight blades and be the type manufactured expressly for and capable of firmly punching the mulch into the soil. Where the equipment can be safely operated, it shall be operated on the contour. Hand methods shall be used where equipment cannot safely operate to perform the work required.
The tackifier shall be applied uniformly over the mulch material at the specified rate, or it shall be injected into the mulch material as it is being applied. Mesh or netting stabilizing materials shall be applied smoothly, but loosely on the designated areas. The edges of these materials shall be buried or securely anchored using spikes or staples as specified in section 7.
The contractor shall maintain the mesh or netting areas until all work under the contract has been completed and accepted. Maintenance shall consist of the repair of areas damaged by water erosion, wind, fire, or other causes.
Such areas shall be repaired to reestablish the intended condition and to the design lines and grades required by the contract. The areas shall be refertilized, reseeded, and remulched before the new application of the mesh or netting.
6–3(210–VI–NEH, January 2014)
6. Measurement and payment Method 1—For items of work for which specific unit prices are established in the contract, each area treated is measured as specified in section 7 and the area calculated to the nearest 0.1 acre. Payment for treatment is made at the contract unit price for the designated treatment, which will constitute full compensation for completion of the work.
When specified as an item of work, mesh or netting is measured to the nearest square yard of surface area covered and accepted. Payment is made at the contract unit price and will constitute full compensation for completion of the work.
Method 2—For items of work for which specific lump sum prices are established in the contract, the quantity of work will not be measured for payment. Payment for this item is made at the contract lump sum price for the item and will constitute full compensation for the completion of the work.
Method 3—For items of work for which lump sum prices are established in the contract, payment is made as the work proceeds. Progress payments will be determined as specified in section 7. Payment of the lump sum contract price will constitute full compensation for completion of the work.
All Methods—The following provisions apply to all methods of measurement and payment. Compensation for any item of work described in the contract, but not listed in the bid schedule is included in the payment for the item of work to which it is made subsidiary. Such items and the item(s) to which they are made subsidiary are identified in section 7.
7. Items of work and construction details
NRCS—July 2018 Seeding, Sprigging, and Mulching AR—Whitstine Weir 6—4
7. ITEMS OF WORK AND CONSTRUCTION DETAILS
Items of work to be performed in conformance with this specification and construction details therefore
A. Bid Item 8, Seeding, Sprigging, and Mulching
1) This item consists of furnishing and applying fertilizer, seed, and straw mulch to all areas disturbed during construction of the weir, including but not limited to the channel banks, the work areas immediately adjacent to the weir, the ingress‐egress routes, and the high‐ground equipment yard. Significant earthwork activity to grade, smooth, and restore the surface topography is addressed in a separate bid item.
2) Fertilizer shall be uniformly applied at the rate of 300 pounds per acre of l0‐20‐20, or equivalent.
The fertilizer shall be applied prior to seeding and shall be thoroughly mixed into the top layer of soil by disking or other approved methods. Disking and mixing deeper than approximately two inches shall not be permitted.
3) The seeding mixtures shall be Certified Seed (blue tag) for those seeds regulated by the Arkansas State Plant Board. The following grass mixture is a soil stabilization mix that will prevent erosion and provide wildlife habitat until native grasses and forbs occupy the disturbed areas. The following grass mixture shall be seeded regardless of the time of year that construction is completed:
Annual Ryegrass, 40 lbs per acre Oats, 40 lbs per acre Arrowleaf Clover, 15 lbs per acre
4) All legume seed shall be inoculated with the appropriate commercial culture.
5) All seed mixtures shall be seeded with a broadcast seeder, grassland drill, or other method that will obtain a uniform distribution of seed and provide ¼ to ½‐inch of cover. Seedbed will be left firm by using a drag or roller.
6) Straw mulch shall be applied at the rate of 2 tons per acre.
7) Mulch shall be stabilized by the use of one (1) pass of a mulch crimper or by a suitable tackifier.
a. When a crimper is used, it shall have straight blades and be of type manufactured expressly for and capable of firmly attaching the mulch to the soil and shall be operated on the contour. Crimping shall be performed within 24 hours of mulch application. A disk harrow shall not be used for mulch stabilization.
b. When an asphalt emulsion is used as a tackifier, the rate shall be ninety (90) gallons per ton of mulch. Asphalt emulsion shall conform to ASTM‐D‐977, Emulsified Asphalt. Emulsion asphalt may be rapid setting, medium setting, or low setting.
8) In Section 6, Measurement and Payment, Method 2 will apply. One lump sum payment shall constitute full compensation for all materials and work described in this bid item.
7–1(210–VI–NEH, January 2009)
The work consists of performing all surveys, measurements, and computations required by this specification.
2. Equipment and material Equipment for construction surveys shall be of a quality and condition to provide the required accuracy. The equip-ment shall be maintained in good working order and in proper adjustment at all times. Records of repairs, calibra-tion tests, accuracy checks, and adjustments shall be maintained and be available for inspection by the engineer.
Equipment shall be checked, tested, and adjusted as necessary in conformance with manufacturer's recommenda-tions.
Material is field notebooks, stakes, templates, platforms, equipment, spikes, steel pins, tools, and all other items necessary to perform the work specified.
3. Quality of work All work shall follow recognized professional practice and the standards of the industry unless otherwise specified in section 9 of this specification. The work shall be performed to the accuracy and detail appropriate for the type of job. Notes, sketches, and other data shall be complete, recorded neatly, legible, reproducible and organized to facilitate ease in review and allow reproduction of copies for job documentation. Survey equipment that requires little or no manual recording of field data shall have survey information documented as outlined in section 9 of this specification.
All computations shall be mathematically correct and shall include information to identify the bid item, date, and who performed, checked, and approved the computations. Computations shall be legible, complete, and clearly document the source of all information used including assumptions and measurements collected.
If a computer program is used to perform the computations, the contractor shall provide the engineer with the software identification, vendor's name, version number, and other pertinent data before beginning survey activities.
Computer generated computations shall show all input data including values assigned and assumptions made.
The elevations of permanent and temporary bench marks shall be determined and recorded to the nearest 0.01 foot. Differential leveling and transit traverses shall be of such precision that the error of vertical closure in feet shall not exceed plus or minus 0.1 times the square root of the traverse distance in miles. Linear measurements shall be accurate to within 1 foot in 5,000 feet, unless otherwise specified in section 9 of this specification. The an-gular error of closure for transit traverses shall not exceed 1 minute times the square root of the number of angles turned.
The minimum requirements for placing slope stakes shall be at 100-foot stations for tangents, as little as 25 feet for sharp curves, breaks in the original ground surface and at any other intermediate stations necessary to ensure accurate location for construction layout and measurement. Slope stakes and cross sections shall be perpendicular to the centerline. Significant breaks in grade shall be determined for cross sections. Distances shall be measured horizontally and recorded to the nearest 0.1 foot. Side shots for interim construction stakes may be taken with a hand level.
Unless otherwise specified in section 9 of this specification, measurements for stationing and establishing the loca-tion of structures shall be made to the nearest 0.1 foot.
Construction Specification 7—Construction Surveys
7–2 (210–VI–NEH, January 2009)
Elevations for concrete work, pipes, and mechanical equipment shall be determined and recorded to the nearest
0.01 foot. Elevations for earth work shall be determined and recorded to the nearest 0.1 foot.
4. Primary control The baselines and bench marks for primary control, necessary to establish lines and grades needed for construc-tion, are shown on the drawings and have been located on the job site.
These baselines and bench marks shall be used as the origin of all surveys, layouts, and measurements to establish construction lines and grades. The contractor shall take all necessary precautions to prevent the loss or damage of primary control points. Any stakes or control points lost or damaged by construction activity will be reestablished by the contractor or at contractor expense.
5. Construction surveys Before work starts that requires contractor performed surveys, the contractor shall submit in writing for the engi-neer's review: the name, qualifications, and experience of the individuals to be assigned to the survey tasks.
Method 1—Contractor performed surveys shall include:
• checking and any supplemental or interim staking
• performing quantity surveys, measurements, and computations for progress payment
• other surveys as described in section 9 of this specification
Method 2—Contractor performed surveys shall consist of all work necessary for:
• establishing line and grade for all work
• setting slope stakes for all work
• checking and any supplemental or interim staking
• establishing final grade stakes
• performing quantity surveys, measurements, and computations for progress payment
• other surveys as described in section 9 of this specification
Method 3—Contractor performed surveys shall consist of all work necessary for:
• establishing line and grade for all work
• setting slope stakes for all work
• checking and any supplemental or interim staking
• establishing final grade stakes
• performing quantity surveys, measurements, and computations for progress payments
• performing original (initial) and final surveys for determinations of final quantities
• other surveys as described in section 9 of this specification.
6. Staking The construction staking required for the item shall be completed before work on any item starts. Construction staking shall be completed as follows or as otherwise specified in section 9 of this specification:
Clearing and grubbing—The boundary of the area(s) to be cleared and grubbed shall be staked or flagged at a maximum interval of 200 feet, closer if needed, to clearly mark the limits of work. When contractor staking is the basis for determining the area for final payment, all boundary stakes will be reviewed by the engineer before start of this work item.
7–3(210–VI–NEH, January 2009)
Excavation and fill—Slope stakes shall be placed at the intersection of the specified slopes and ground line.
Slope stakes and the reference stakes for slopes shall be marked with the stationing, required cut or fill, slope ratio, and horizontal distance from the centerline or other control line. The minimum requirements for placing slope stakes is outlined in section 3, Quality of work.
Structures—Centerline and offset reference line stakes for location, alignment, and elevation shall be placed for all structures.
7. Records All survey data shall be recorded in fully identified standard hard-bound engineering survey field notebooks with consecutively numbered pages. All field notes and printed data shall include the purpose or description of the work, the date the work was performed, weather data, sketches, and the personnel who performed and checked the work. Electronically generated survey data and computations shall be bound, page numbered, and cross ref-erenced in a bound field notebook containing the index for all survey activities. All work shall follow recognized professional practice.
The construction survey records shall be available at all times during the progress of the work for examination and use by the engineer and when requested, copies shall be made available. The original field notebooks and other re-cords shall be provided to and become the property of the owner before final payment and acceptance of all work.
Complete documentation of computations and supporting data for progress payments shall be submitted to the en-gineer with each invoice for payment as specified in section 9 of the specification. When the contractor is required to conduct initial and final surveys as outlined in section 5, Construction Surveys, notes shall be provided as soon as possible after completion to the engineer for the purpose of determining final payment quantities.
8. Payment Method 1—For items of work for which lump sum prices are established in the contract, payment is made as the work proceeds, after presentation of correct and accurate invoices by the contractor showing related costs and evi-dence of the charges of suppliers, subcontractors, and others for supplies furnished and work performed. Invoices for the total amount of the contract price will not be accepted until all surveys are complete and required docu-mentation has been determined complete. If the total of such payments is less than the lump sum contract price for this item, the unpaid balance will be included in the final contract payment. Payment of the lump sum contract price will constitute full compensation for completion of all work under the bid item.
Method 2—For items of work for which lump sum prices are established in the contract, payment is made as the work proceeds with progress payment amounts determined as a percentage of the total work planned as projected from the contractor's approved construction schedule. Payment of the lump sum contract price will constitute full compensation for completion of all work under this bid item.
All Methods—Payment will not be provided under this item for the purchase price of materials or equipment hav-ing a residual value.
Compensation for any item of work described in the contract, but not listed in the bid schedule will be included in the payment for the item of work to which it is made subsidiary. Such items and the item to which they are made subsidiary are identified in section 9 of this specification.
9. Items of work and construction details
NRCS—July 2018 Construction Surveys AR—Whitstine Weir 7—4
9. ITEMS OF WORK AND CONSTRUCTION DETAILS
Items of work to be performed in conformance with this specification and construction details therefore are:
A. Subsidiary Item, Contractor Surveys
1) This item consists of any necessary supplemental or intermittent survey work.
2) In Section 4, Primary Control, a single permanent benchmark, suitable for occupation by a GPS base station, has been established in the vicinity of the work site. The approximate location and position coordinates are indicated on the drawings.
3) NRCS will establish and stake the plan view axes of the weir. Stationing and elevation of each stake will be marked on the stake.
4) In Section 5, Construction Surveys, Method 2 shall apply. The contractor will perform any necessary supplemental or intermittent surveys, measurements, and computations for checking progress and quantity estimates for progress payments.
5) In Section 9, Payment, no separate payment will be made for contractor performed construction surveys. Compensation for surveys will be included in the payment for Bid Item 6, Rock Riprap, R150.
8–1(210–VI–NEH, May 2001)
The work consists of the mobilization and demobilization of the contractor's forces and equipment necessary for performing the work required under the contract. It does not include mobilization and demobilization for specific items of work for which payment is provided elsewhere in the contract. Mobilization will not be considered as work in fulfilling the contract requirements for commencement of work.
2. Equipment and material Mobilization shall include all activities and associated costs for transportation of contractor's personnel, equip-ment, and operating supplies to the site; establishment of offices, buildings, and other necessary general facilities for the contractor's operations at the site; premiums paid for performance and payment bonds including coinsur-ance and reinsurance agreements as applicable; and other items specified in section 4 of this specification.
Demobilization shall include all activities and costs for transportation of personnel, equipment, and supplies not required or included in the contract from the site; including the disassembly, removal, and site cleanup of offices, buildings, and other facilities assembled on the site specifically for this contract.
This work includes mobilization and demobilization required by the contract at the time of award. If additional mobilization and demobilization activities and costs are required during the performance of the contract as a result of changed, deleted, or added items of work for which the contractor is entitled to an adjustment in contract price, compensation for such costs will be included in the price adjustment for the item or items of work changed or added.
3. Payment Payment will be made as the work proceeds, after presentation of paid invoices or documentation of direct costs by the contractor showing specific mobilization and demobilization costs and supporting evidence of the charges of suppliers, subcontractors, and others. When the total of such payments is less than the lump sum contract price, the balance remaining will be included in the final contract payment. Payment of the lump sum contract price for mobilization and demobilization will constitute full compensation for completion of the work.
Payment will not be made under this item for the purchase costs of materials having a residual value, the purchase costs of materials to be incorporated in the project, or the purchase costs of operating supplies.
4. Items of work and construction details
Construction Specification 8—Mobilization and Demobilization
NRCS—July 2018 Mobilization and Demobilization AR—Whitstine Weir 8—2
4. ITEMS OF WORK AND CONSTRUCTION DETAILS
Items of work to be performed in conformance with this specification and construction details therefore
A. Bid Item 1, Mobilization and Demobilization
1) This item consists of the mobilization of the Contractor's forces and equipment necessary for performing the work required under this contract and demobilization upon completion.
2) Items of work subsidiary to this bid item are:
a. Pollution Control
3) In Section 3, Payment, one lump sum payment will constitute full compensation for all materials and work described in this Bid Item.
B. Bid Item 7, Ingress‐Egress and Site Restoration
1) This item consists of the construction of ingress‐egress roads, as necessary, across the area of the work limits and maintaining the ingress‐egress roads in a trafficable condition during construction.
2) The Contractor shall submit to the Engineer, for approval, a written plan outlining how the Contractor will transport construction materials from the public roads across the fields to the weir footprint. The plan shall necessarily account for the egress of vehicles to meet NDPES requirements.
3) This item also includes maintaining in a trafficable condition the gravel portion of Goat Neck Road, an Independence County Road, from the junction of Goat Neck Road with Meadow Lake Road to the ingress‐egress road on the south side of Departee Creek.
4) Furthermore, this item includes all site closure activities except the vegetation establishment addressed in a separate bid item. Site closure activities include, but are not limited to—
a. the excavation of any non‐soil materials (such as rock or gravel that provides a traffic surface) from the ingress‐egress roads or work areas and disposal to an off‐site location,
b. the backfilling and closing of any on‐site burn pits,
c. the grading and smoothing of any onsite borrow pits or spoil piles,
d. the grading and smoothing of the disturbed top‐of‐bank areas along the channel, and
e. the grading and smoothing of the areas of the work limits and the high ground equipment yard to a condition and topography substantially similar to that preceding construction activities.
Soil material from the channel excavation may be used in site restoration activities. The suitability of material for specific purposes shall be determined by the Engineer.
5) In Section 3, Payment, one lump sum payment will constitute full compensation for all materials and work described in this Bid Item.
21–1(210–VI–NEH, May 2001)
Construction Specification 21—Excavation
1. Scope The work shall consist of the excavation required by the drawings and specifications and disposal of the excavated materials.
2. Classification Excavation is classified as common excavation, rock excavation, or unclassified excavation in accordance with the following definitions or is designated as unclassified.
Common excavation is defined as the excavation of all materials that can be excavated, transported, and unloaded using heavy ripping equipment and wheel tractor-scrapers with pusher tractors or that can be excavated and dumped into place or loaded onto hauling equipment by excavators having a rated capacity of one cubic yard or larger and equipped with attachments (shovel, bucket, backhoe, dragline, or clam shell) appropriate to the material type, character, and nature of the materials.
Rock excavation is defined as the excavation of all hard, compacted, or cemented materials that require blasting or the use of ripping and excavating equipment larger than defined for common excavation. The excavation and removal of isolated boulders or rock fragments larger than 1 cubic yard encountered in materials otherwise con-forming to the definition of common excavation shall be classified as rock excavation. The presence of isolated boulders or rock fragments larger than 1 cubic yard is not in itself sufficient cause to change the classification of the surrounding material.
For the purpose of these classifications, the following definitions shall apply:
Heavy ripping equipment is a rear-mounted, heavy duty, single-tooth, ripping attachment mounted on a track type tractor having a power rating of at least 250 flywheel horsepower unless otherwise specified in section 10.
Wheel tractor-scraper is a self-loading (not elevating) and unloading scraper having a struck bowl capacity of at least 12 cubic yards.
Pusher tractor is a track type tractor having a power rating of at least 250 flywheel horsepower equipped with ap-propriate attachments.
Unclassified excavation is defined as the excavation of all materials encountered, including rock materials, regard-less of their nature or the manner in which they are removed.
3. Unclassified excavation Excavation designated as unclassified excavation shall include all materials encountered regardless of their nature or the manner in which they are removed. When excavation is unclassified, none of the definitions or classifications stated in Section 2, Classification, shall apply.
4. Blasting The transportation, handling, storage, and use of dynamite and other explosives shall be directed and supervised by a person(s) of proven experience and ability who is authorized and qualified to conduct blasting operations.
Blasting shall be done in a manner as to prevent damage to the work or unnecessary fracturing of the underlying rock materials and shall conform to any special requirements in section 10 of this specification. When specified in section 10, the contractor shall furnish the engineer, in writing, a blasting plan before blasting operations begin.
21–2 (210–VI–NEH, May 2001)
5. Use of excavated material Method 1—To the extent they are needed, all suitable material from the specified excavations shall be used in the construction of required permanent earthfill or rockfill. The suitability of material for specific purposes is deter-mined by the engineer. The contractor shall not waste or otherwise dispose of suitable excavated material.
Method 2—Suitable material from the specified excavations may be used in the construction of required earthfill or rockfill. The suitability of material for specific purposes is determined by the engineer.
6. Disposal of waste materials Method 1—All surplus or unsuitable excavated materials are designated as waste and shall be disposed of at the locations shown on the drawings.
Method 2—All surplus or unsuitable excavated materials are designated as waste and shall be disposed of by the contractor at sites of his own choosing away from the site of the work. The disposal shall be in an environmentally acceptable manner that does not violate local rules and regulations.
7. Excavation limits Excavations shall comply with OSHA Construction Industry Standards (29CFR Part 1926) Subpart P, Excavations, Trenching, and Shoring. All excavations shall be completed and maintained in a safe and stable condition through-out the total construction phase. Structure and trench excavations shall be completed to the specified elevations and to the length and width required to safely install, adjust, and remove any forms, bracing, or supports necessary for the installation of the work. Excavations outside the lines and limits shown on the drawings or specified herein required to meet safety requirements shall be the responsibility of the contractor in constructing and maintaining a safe and stable excavation.
8. Borrow excavation When the quantities of suitable material obtained from specified excavations are insufficient to construct the speci-fied earthfills and earth backfills, additional material shall be obtained from the designated borrow areas. The extent and depth of borrow pits within the limits of the designated borrow areas shall be as specified in section 10 or as approved by the engineer.
Borrow pits shall be excavated and finally dressed to blend with the existing topography and sloped to prevent ponding and to provide drainage.
9. Overexcavation Excavation in rock beyond the specified lines and grades shall be corrected by filling the resulting voids with portland cement concrete made of materials and mix proportions approved by the engineer. Concrete that will be exposed to the atmosphere when construction is completed shall meet the requirements of concrete selected for use under Construction Specification 31, Concrete for Major Structures, or 32, Structure Concrete, as appropriate.
Concrete that will be permanently covered shall contain not less than five bags of cement per cubic yard.