Amend 1 Site Showing Tech Notes QA.pdf

PDF 391 KB Posted

Attached to
Cedar Creek Watershed 16 & 16A Remedial Repair -NRCS Texas
Solicitation number
12FPC326Q0043
Issued by

About this file

This file contains Questions and Answers (Q&A) and Site Showing Technical Notes for a federal construction contract opportunity for remedial dam repairs at Cedar Creek Watershed Sites 16 and 16A, located in Rockwall County, Texas. The solicitation number is 12FPC326Q0043, issued by the USDA Natural Resources Conservation Service (NRCS) under the Watershed and Flood Prevention Program (WFPO).

The estimated price range for both projects is between $1,000,000 and $5,000,000. Key deadlines are: questions due at 3:00 PM CT on August 13th, and quotes due by 5:00 PM CT on August 28th (extended by Amendment 1). Submission requirements include a completed Schedule of Items, Vendor Information Sheet, bid bond (20% of total price or $3 million, whichever is less), active SAM registration, SF 1442 form, technical approach demonstrating capability to meet schedule requirements and SOW specifications, and past performance/customer references. A performance and payment bond of 100% of project cost must be provided within 10 calendar days of award. The contract specifies 169 performance days for Cedar Creek 16 and 175 performance days for Cedar Creek 16A, with a maximum of 60 work hours per week. Primary work includes structure removal, excavation, earthfill with Class A compaction, seeding and mulching, construction surveys, mobilization/demobilization, water removal, rock riprap placement, concrete work, and field fence construction. All work must comply with OSHA standards, TPDES environmental requirements, and SWPPP procedures. The contractor must establish written quality control plans, maintain daily QC reports, and provide equipment with backup alarms, seat belts, and rollover protective structures.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers

Cedar Creek Watershed Site 16 & 16A Remedial Dam Repairs

Please see attached Site Showing Technical Notes for additional information.

Question: Could the Government please clarify what is required for submission?

On pages 18 and 19 of 24, the Government states (emphasis mine):

Technical Approach:

The technical approach will evaluate the ability of the offeror to provide a sound and compliant approach that meets all requirements and shows a thorough understanding of them. It is the contractor's responsibility to ensure their quotation clearly demonstrates their capability to meet these requirements. All offerors must provide the following minimum information and documentation with their quotations to be considered responsive and have their offers evaluated:

• Ability of the offeror to meet the schedule requirements listed in the Statement of Work

(SOW).

• Detailed explanation of any requirement listed in the SOW that cannot be successfully accomplished by the offeror.

Past Performance:

The Government may utilize any references provided by the Contractor, along with information available from past contracts/orders with the USDA and any information found using sources such as Federal Government sources or the Contractor Performance Assessment Reporting System (CPARS) to determine if the Contractor has acceptable or neutral Past Performance.

However, on page 22 of 24, the Government lists the four items that are required for submission:

1. Completed Schedule of items (Page 8)

2. Completed Vendor Information Sheet;

3. Submit the required bid guarantee, Bid Bond (see provision 52.228-1)

4. Active/complete registration in SAM (including designation as a Small Business).

None of these four items are a technical approach, past performance/CPARS, or customer references.

Anwer: Yes, a technical approach is required to substantiate your ability to perform the work.

These four points were added to provide clarification/reminders or ‘Additional Information for Offerors’ to ensure that the other aspects often overlooked were also included. Listing the technical approach appeared redundant, moving forward I will list the technical approach here as well.

Question: Could you please confirm that questions are due at 3pm CT on August 13th, and that the proposal itself is due at 4pm CT on August 25th?

Answer:

Questions are due at 3pm CT on August 13th, and the quote is due date is extended on amendment 1 to 5pm CT on August 28th.

Question:

Is there no SF 1442 and certifications section?

Answer:

SF 1442 is incorporated on Amendment 1: Please complete and include with your response.

Question: Is there no bid bond requirement?

Question: There is no where in the solicitation that specifies about the bid bond information, can you please provide the information of how much and to whom it is for?

Answer: Yes, a bid bond is required, FAR Clause 52.228-1 Bid Guarantee (Sep 1996), 52.228-15 Performance and Payment Bonds-Construction (Jun 2020), and 52.228-14, Irrevocable Letter of Credit, is in the solicitation.

A bid bond/guarantee shall be 20% of the total price or $3 Million, whichever is less, is required to be submitted with quotes. The bid bond must be executed by a surety company authorized to operate in the state where the project is located. The bid bond guarantees that the bidder will not withdraw its bid during the acceptance period and, if awarded the contract, will execute all required contractual documents and provide the necessary performance and payment bonds within the specified timeframe

Payment Bond (SF-25A), Irrevocable Letter of Credit (ILC), or a Tripartite Escrow Agreement in the amount of 100% of the project cost will be required within 10 calendar days of award of the contract.

Question: Cedar Creek 16A - What do we do with the gate at Sta. 20+65?

Answer: Replace gate and pipe fence.

Question: Cedar Creek 16A - Is the gate at Sta 20+65 a property line?

Answer: Yes, it is a property line.

Question: Cedar Creek 16 & 16A - Will we get paid for the extra width of each lift on the upstream repair due to the width of the 34” plow equipment?

Answer: We pay to neat-line and grades of the compacted Class A material and not for contractor convenience.

NATURAL RESOURCES CONSERVATION SERVICE

An Equal Opportunity Provider and Employer

Subject: Date: August 7th,2026 Agreements – Site Showing Technical Notes for Cedar Creek Watershed Site 16 & 16A Remedial Dam Repairs IFB No. 12FPC326Q0043

To: Kyle Hied, Contracting Officer, FPAC

(submitted by email attachment) A site showing was held on the subject site on Aug 06th, 2026. The Natural Resources Conservation Service (NRCS) was represented by Joe Forrest, Watershed Construction Engineer, Samuel Drummond, Project Engineer and Contracting Officer’s Representative (COR), and Jerry Creasser, Watershed Construction Inspector, Owen Cantrell Kaufman Van Zandt SWCD. NRCS is to provide quality assurance inspection and construction oversight for this project.

The site showing began with a meeting at the USDA Service Center, 8620 FM 741, Forney, Texas TX 75126 at 10:00 A.M. followed by a visit to both sites. The following was reviewed and submitted to the CO to be added by amendment to the Invitation for Bids (IFB).

Cedar 16 & 16A is a federal contract and is responsible for soliciting and awarding a contract for this project. The contract is receiving funding from the USDA – Natural Resources Conservation Service as authorized under the Watershed and Flood Prevention Program (WFPO).

Welcome – Introductions: Sponsor's Representatives; Owen Cantrell Kaufman- Van Zandt SWDC, Sam Drummond, COR/GR, Joe Forrest, Watershed Project Engineer, and Jerry Creasser, Watershed Construction Inspector.

Estimated Price Range for both projects – Between $1,000,000 - $5,000,000 Please provide the following information by amendment to the information for bidders.

CHANGES AND CORRECTIONS

The items listed below are changes/corrections to the information for bidders. Please make these pen and ink changes to your bid documents.

CHANGES TO THE BID SCHEDULE

SOW 2.4 Location and Hours of Work Work under this contract is performed on site of Cedar Creek Dams 16/16A located in Rockwall County, Texas. Construction schedule will be required, prior to issuance of Notice to Proceed (NTP).

Estimated performance time is 169 days (Cedar 16) and 175 days (Cedar 16A), not to include move in.

344 performance workdays from date of award for dam 16 and dam 16A. Work must be substantially complete prior to mobilization/demobilization to second dam.

SOW 2.4 states “The Contractor shall be responsible for establishing their work hours under this contract, Maximum 60 hours a week (6 days at 10 hours days)

Work Performance on Holidays The Contractor shall not perform work on the following holidays except in the case of emergency as permitted elsewhere in this contract:

• New Year's Day

• Independence Day

An Equal Opportunity Provider and Employer

• Labor Day

• Thanksgiving Break: Nov 25 -Nov 29

• Christmas Break: Dec 20 – Jan 3 The contract performance time has been established to allow for the non-working holidays stated above.

The Contractor may be permitted to work the following remaining designated Federal holidays provided a letter of request is submitted to the Project Engineer/Contracting Officer Representative at least five

(5) days in advance of the holiday.

• Birthday of Martin Luther King, Jr.'s

• Washington's Birthday

• Memorial Day

• Juneteenth Independence Day

• Columbus Day

• Veterans Day

CHANGES TO THE CONSTRUCTION SPECIFICATIONS

Cedar Creek 16 page ii.5 Remove 179 calendar days with 169 Performance Days Cedar Creek 16A page ii.5 Remove 185 calendar days with 175 Performance Days

Cedar Creek 16 and 16A Repair.

Sheet ii - Definitions:

Remove All Contracting Local Organization (CLO) and replace it with Federal Contracting Official.

CS 7.9.a(5)(b) replace Three (3) PRMs with Four (4) PRMs - Cedar Creek 16 CS 8.4.2(b) remove Contracting Local Organization CS 21 Excavation Remove 21.10.e.(1) & (2) Subsidiary Item Excavation, Rock Riprap

CHANGES TO THE DRAWINGS

N/A

SPECIAL EMPHASIS ITEMS

Special emphasis items that were discussed or otherwise provided at the site showing are discussed below.

452.236-76 – SAMPLES AND CERTIFICATES

Certificates and test data shall be submitted to show compliance of materials and construction specified in the contract requirements. Materials or equipment for which samples, certifications or test data are required shall not be used in the work until approved in writing by the Contracting Officer.

Materials which require material certifications are:

Construction Entrance Materials (Rock, Geotextile) Silt Fence Rock Riprap Vegetation; seed, fertilizer, hydromulch, hay, tackifier (as applicable)

An Equal Opportunity Provider and Employer

Supplement to OSHA Part 1926 and 1910 Construction Industry Standards and Interpretations The Contractor shall comply with all applicable OSHA safety standards. All or part of the work may be suspended for noncompliance. The GR and Inspector will have delegated authority to suspend work for any noncompliance posing a serious or imminent danger to the health or safety of the Contractor’s employees or others such as employees of the CLO or NRCS and the public.

The Supplement to OSHA 1910 and 1926 emphasizes specific safety items which must be understood by the Contractor prior to bidding this job. Among these items are the requirements for:

1. Written plan for accident prevention and safety (CO must approve prior to beginning work)

2. First Aid Training certificates

3. First aid facilities – on site

4. Safety Meetings, weekly “tool box” and monthly

5. Dust control

6. Rollover protective structures

7. Backup alarms

8. Restroom Facilities

9. Scaffolding and Fall Protection Hard hats must be worn on the job site at all times.

Equipment must be outfitted with working backup alarms, seat belts, and approved roll-over protective structures (ROPS). All equipment will be inspected at the job site by the Construction Inspector prior to use on the project.

DRAWINGS

Drawing TX-EN-0812, Cover + Sheets 1 thru 10 for the Hickory Creek Site 16 Remedial Repair was reviewed. Performance time for this site is 169 calendar days (holidays and weather days not included) Drawing TX-EN-0813, Cover + Sheets 1 thru 10 for the Hickory Creek Site 16A Remedial Repair was reviewed. Performance time for this site is 175 calendar days (holidays and weather days not included)

An Equal Opportunity Provider and Employer

SPECIFICATIONS AND SWPPP

There are two types of specifications in this contract: (1) Construction Specifications and (2) Material Specifications. The construction specifications are composed of two parts. The first part is called the closed specification and is the standard NRCS construction specification that begins with the SCOPE and ends with MEASUREMENT AND PAYMENT or PAYMENT. The second part is called the open specification and consists of the ITEMS OF WORK AND CONSTRUCTION DETAILS that are written specifically for this job.

The specifications are summarized below. However, all language of the specifications apply to the contract.

CS 2 – CLEARING AND GRUBBING

Subsidiary Item – Clearing and Grubbing This item shall consist of all clearing and grubbing within the work limits required for construction of the works of improvement as shown on the drawings.

In Section 5, Disposal, all materials removed from the cleared and grubbed areas shall be either burned and buried on-site or mulched on-site at areas designated or approved by the Contracting Officer. All disposal methods shall be in accordance with state and local regulations. Cedar Creek 16A will need Clearing and Grubbing for the campsite and stockpile location.

Compensation for this item is to be included in Bid Item 6 – Mobilization and Demobilization, Bid Item 8 – Excavation Common, Upstream Embankment & Bid Item 9 – Excavation Downstream Embankment.

CS 3 – STRUCTURE REMOVAL

Bid Item 1 -Cedar Creek 16 Lump Sum Structure Removal, Principal Spillway This item shall consist of the removal and disposal of one (1) 42-inch I.D., 20-foot concrete pipe section, two (2) 42-inch I.D., 10-foot concrete pipe sections, concrete bedding, concrete support blocks, and the reinforced concrete pipe support.

All unusable material and rubble shall be disposed of at an offsite location of the contractor’s choosing as approved by the contracting officer and in accordance with all local and state regulations.

Bid Item 1 - Cedar Creek 16A Lineal Feet Structure Removal, Fences This item shall consist of the removal of all designated fences in the construction area. The actual limits of required fences to be removed will be marked of designated at the time of showing of the site to prospective bidders

CS 5 – POLLUTION CONTROL

Bid Item 2 – Cedar Creek 16 & 16A - Lump Sum This item includes work required to maintain sediment filters, installation of the stabilized construction entrance, installation of the rock sediment filter, and creating and implementing a SWPPP. Geotextile used for the construction entrance shall be non-woven and conform to Material Specification 592.

Site 16 and 16A is subject to the Texas pollutant Discharge Elimination System (TPDES) requirements administered by the Texas Commission on Environmental Quality (TCEQ). Rules for the TPDES

An Equal Opportunity Provider and Employer process relative to construction sites are contained in TPDES General Permit No. TXR150000. In conformance with the general permit, a Storm Water Pollution Prevention Plan (SWPPP) is required.

The Contractor shall prepare a SWP3 in accordance with the TPDES general permit requirements.

The SWP3 shall include a detailed work sequence outline that defines the delineates the proposed construction operation and includes the minimum pollution control practices indicated on the construction drawings, as well as any additional measures that may be required to meet TPDES requirements. The amended SWP3 shall be signed by the Contractor and submitted to the Contracting Officer prior to issuance of the Notice to Proceed. A copy of the approved SWP3, as amended, will be maintained at the construction site by the Contractor. A copy of the permit shall be attached to SWP3.

All applicable TCEQ rules and regulations concerning the TPDES and the SWPPP must be followed.

The disturbed area of the construction site is greater than 5 acres. TPDES requires a small construction site notice as part of the General Permit.

Bid Item 3 – Silt Fence Lineal FT Cedar Creek 16 and 16A This item consists of furnishing and installing silt fence to the lengths and locations designated on the Drawings and otherwise needed to control sediment from leaving the construction site.

In Section 3, Erosion and Sediment Control Measures and Works, Sediment Filters shall be limited to geotextile silt fence.

Silt fence material shall meet the requirements of Material Specification 592.

CS 6 – SEEDING, SPRIGGING, AND MULCHING

Bid Item 4 - Cedar Creek 16 & 16a – Per Acre This item shall consist of preparing the seedbed and furnishing and applying seed, hay mulch, tackifier, and fertilizer to all disturbed areas as shown on the drawings.

In Section 5, Seeding, Sprigging, Fertilizing, Mulching, and Stabilizing, straw mulch material shall consist of coastal bermudagrass or a native bluestem mix and the rate of application shall be 2-1/2 tons per acre. Mulches shall be stabilized by a mechanical crimper or by a non-asphaltic tackifier applied at a rate consistent with either 40 pounds per acre or as recommended by the manufacturer, whichever is greater. Tackifier, if applicable, shall be approved by the COR prior to placement.

The grass seed shall be drilled or broadcast onto a firm, clean seedbed. A grass seed drill equipped with depth control bands, grain drill with a grass seed attachment, or Brillion (type) seeder shall be used.

The seed shall consist of the mix listed in Section 7.a.(4) applied at the listed rates of pure live seed per acre. Seeding shall be conducted between December 15 and September 1.

Fertilizer shall be of the pelleted form and shall be uniformly mixed. The rate of application of the fertilizer shall be thirty pounds of nitrogen (N), forty pounds of phosphorous (P) and thirty pounds of potassium (K) per acre). Rate is based on pure nutrient weights.

In Section 6, Measurement and Payment, Method 1 shall apply and will be made at the contract unit price with the vegetated area being measured to the nearest 0.1 acre.

CS 7 – CONSTRUCTION SURVEYS

Bid Item 5 – Cedar Creek 16 & 16A Lump Sum In Section 5, Construction Surveys, Method 2 shall apply. The Contractor is responsible for the layout of all the work and for checking all work and shall include but not limited to: (a) Those required to check

An Equal Opportunity Provider and Employer all excavation and earthfill slopes as work progresses to ensure such slopes are maintained at those specified. (b) Earthfill and excavated slopes shall be checked at least each five feet of vertical interval and corrected to planned slopes. (c) Those required to set “bluetops” for subgrades and finished grades of all excavations, earthfills, and appurtenances to the work.

The Contractor must submit to the CO in writing the names, qualifications and experience of the surveyor personnel for approval prior to commencement of work. The Contractor must provide original field notebooks and other records to the COR before final payment and acceptance of work.

Initial and final surveys for determinations of final quantities will be performed by the Government. All surveys shall proceed from points established by the Government. The benchmarks are shown on the drawings.

In Section 8, Payment, Method 2 shall apply with payment made as the work proceeds with progress payment amounts determined as a percentage of the total work planned as projected from the Contractor’s approved construction schedule.

Subsidiary Item – Permanent Reference Markers (PRMs) This item shall consist of all work and materials (except the benchmark cap) required for the establishment of permanent reference markers cast in-place with non-reinforced concrete cylinders.

The cap for the PRM will be furnished by the NRCS prior to casting/pouring the concrete. A minimum of four (4) PRMs shall be required per each site.

Compensation for this item is to be included in Bid Item 2 – Construction Surveys.

CS 8 – MOBILIZATION AND DEMOBILIZATION

Bid Item 6 – Cedar Creek 16 & 16A – Lump Sum The Contractor shall construct a temporary construction entrance and site access at the approximate location as shown on the drawings. The entrance shall comply with Kaufman County for Cedar Creek 16 and Rockwall County for Cedar Creek 16A requirements for temporary construction driveways and to the requirements as contained within this specification and as shown on the drawings.

As a part of this bid item, the Contractor shall furnish and install electrical service to the Government supplied field trailer. The service shall be adequate to address all anticipated electrical loads and meet the minimum voltage and amperage requirements indicated by the selected trailer and trailer manufacturer recommendations. The Contractor shall be responsible for supply of power to the Government’s field office throughout the contract period. If a portable generator is used to supply electrical power, the Contractor shall be responsible for the complete operation and maintenance of the generator. The generator shall remain in operating condition 24 hours per day.

The Contractor shall prohibit livestock entry to the work area. All temporary fencing shall remain in place and maintained during the entire contract period, or as approved by the Engineer.

Section 3, PAYMENT, states, "Payment will be made as the work proceeds, after presentation of paid invoices …. by the Contractor showing specific mobilization and demobilization costs and supporting evidence of the charges of suppliers, subcontractors, and others." The Contractor may be asked to provide proof of the total direct cost and will have to submit paid invoices for the purchase of bonds and mobilization supplies to be reimbursed for these items prior to acceptance of invoice. Note there is no receipt for clearing and grubbing. Survey of clearing and grubbing will be needed to calculate acreage and the NRCS will use current cost from similar projects for cost per acre for payment.

As part of demobilization, the access road shall be bladed to be smooth and shall be left in a rut-free condition. The temporary construction entrance and its improvements shall be removed and the area

An Equal Opportunity Provider and Employer bladed and shaped to restore the area to its original condition. All temporary fencing installed shall be completely removed and the materials disposed of in an approved manner.

CC 16 - RESTRICTING ACCESS OVER DALLAS WATER UTILITY (DWU) IS REQUIRED. I do have a point of contact.

John.cernero@dallas.gov (214) 948-4543 Guadalupe.bailey@dallas.gov (214) 670-6010

CS 9 – TRAFFIC CONTROL

Subsidiary Item – Traffic Control In section 4, the Contractor shall furnish a written plan showing the proposed method of signing, barricading for traffic control, use of flaggers, etc. to be approved by this contract’s Engineer and Hemphill County (if necessary).

Compensation for this item is to be included in Bid Item 3 – Mobilization and Demobilization.

CS 11 – REMOVAL OF WATER

Bid Item 7 – Cedar Creek 16 & 16A – Lump Sum This item of work requires the Contractor to submit a written plan for diverting surface water and dewatering the construction site. The plan must be approved before beginning construction. Progress Payment determined by percentage of work.

Note: both sites need to dewater approximately 8’ – 10’ below principal spillway crest for installation of wave berm and plunge basin.

CS 21- EXCAVATION UPSTREAM & DOWN STREAM

Bid Item 8 & 9 – Cedar Creek 16 & 16A Cubic Yards Upstream excavation item shall consist of all excavation required to repair the upstream embankment shown on the drawings including the removal or saturated cut material to form the minimum dimensions shown in the profile and section views within the work limits of the upstream embankment of this repair.

Downstream excavation items shall consist of all excavations required to repair the downstream embankment, plunge basin, and outlet channel.

Note: excavation of the borrow area is subsidiary and will not be paid for material excavation.

CS 21 Excavation Remove 21.10.e.(1) & (2) Subsidiary Item Excavation, Rock Riprap

CS 23 – EARTHFILL

Bid Item 10 – Cedar Creek 16 & 16A Cubic Yards This item shall consist of backfill to repair and construct the upstream and downstream embankments, principal spillway repair, armored plunge basin and earthen outlet channel as shown on the drawings Note: Earthfill is Class A compaction mailto:John.cernero@dallas.gov mailto:Guadalupe.bailey@dallas.gov

An Equal Opportunity Provider and Employer

CS 24 – DRAINFILL

Bid Item 11 – Cedar Creek 16 Cubic Yards This item shall consist of furnishing and installing the fine and coarse drain fill and geotextile required for the sand filter collar, and pipe support subbase bedding material as specified in the construction drawings. Fine and coarse drain fill shall comply with the gradation requirements shown in the drawings.

CS 26 – TOPSOILING

Subsidiary Item –Cedar Creek 16 and 16A - Topsoiling This item shall consist of the salvaging of approved topsoil from required excavations; from the foundation stripping operations; and from the borrow area and placing and spreading it on all earthfill areas and exposed cut slopes as designated on the drawings.

In section 3, Furnishing, Method 1 shall apply and shall be from designated earth surfaces that will be disturbed by construction activities.

In Section 5, Spreading, Method 1 shall apply. After spreading the topsoil on the required surfaces, a minimum amount of compacted effort shall be applied with at least 1 pass of a dozer track.

The depth of topsoil for these areas shall be 6 inches.

Compensation for this item is to be included in Bid Item 1 – Earth Fill.

CS 31 – Concrete Structural Bid Item 12 Cedar Creek 16 – Cubic yard This item shall consist of furnishing and placing all concrete required for construction of the concrete principal spillway repair as shown on the drawings.

Note: the item of work subsidiary to this bid item is Steel Reinforcement as specified in CS 34.

CS 41 – Concrete Pipe, Pressure 42- inch I.D.

Bid item 13 Cedar Creek 16 – LF This item shall consist of furnishing an installing the 42-inch I.D. conduit shown on the drawings.

CS 61 – Rock Riprap Bid Item 14 – Cedar Creek 16 – Tons Bid Item 11 – Cedar Creek 16A - Tons This item shall include furnishing and placing the loose rock riprap required for the wave berm, inlet riser armoring, plunge basin and channel armoring as shown on the drawings.

Cedar Creek 16 has R-150 wave berm & R-300 plunge basin In section 2, Material, second paragraph, the Contractor shall provide written notice of proposed source of rock material at least five working days before delivery.

Rock for use as riprap shall comply with the requirements of Material Specification 523, Rock Type 1.

Rock shall conform to the gradation requirements of ASTM D6092 R-150 & R-300.

In section 7, Measurement and payment, Method 1 shall apply and be computed to the nearest ton by actual weight. Furnished delivery tickets are required showing the weight to the nearest 0.1 ton.

An Equal Opportunity Provider and Employer

92 – FIELD FENCE

Bid Item 5 – Cedar Creek 16A Field Fence & Stub Out Fence This item shall consist of furnishing all materials required and constructing the barbed wire fences as designated on the drawings. Barbed wire shall be 12.5 gauge and have Class III coating.

The approximate location of the fences to be constructed is shown on the construction drawings. The final location of the fences (including corners, gates, pull and brace panels, and special anchorage) shall be as staked by the Engineer.

In Section 10, Measurement and payment, Method 1 shall apply and measured to the nearest foot.

94 – CONTRACTOR QUALITY CONTROL

Bid Item 14 – Cedar Creek 16A – Lump Sum Bid Item 15 – Cedar Creek 16 – Lump Sum In Section 3, Quality Control System, Method 2 shall apply. The system established shall be documented in a written plan developed by the Contractor and approved by the CO. The plan shall be submitted to the CO within 10 calendar days after notice of award. No construction activity that requires inspection shall not proceed until the plan is approved by the CO.

In Section 4, Quality Control Personnel, Method 2 shall apply. This requires the quality control activities to be performed by competent personnel who are separate and apart from line supervision and who report directly to management. Names of quality control personnel and their duties, qualifications, certifications, and authorities are required and shall be submitted to the CO for approval.

In Section 9, Measurement and Payment, Method 2 shall apply and be paid in equal amounts on each monthly estimate.

It is the Contractor’s responsibility to perform tests to prove and ensure that all work performed meets the contract requirements. Any testing done by the Government is for the sole benefit of the Government. All tests must be conducted in accordance with the appropriate ASTM method and with equipment that meets the requirements of the specified ASTM test method.

Daily QC reports are required to be submitted to the Inspector.

Quality control personnel shall also be responsible for maintaining a record of progress with photographs and be submitted with the request for final payment.

95 – Geotextile Subsidiary Item – Cedar Creek 16 & 16A Geotextile This item shall consist of furnishing and placing the geotextile under the new rock riprap plunge basin, channel armoring, and watering ramps including all excavation, fill and backfill required for keying geotextile into the ground as shown on the drawings.

Geotextiles shall be non-woven Class I and meet Material Specification 592.

Compensation for this item is to be included in Rock Riprap and Drainfill

An Equal Opportunity Provider and Employer

Questions asked during site visit

1. Cedar Creek 16A - What do we do with the gate at Sta. 20+65?

a. Replace gate and pipe fence.

2. Cedar Creek 16A - Is the gate at Sta 20+65 a property line?

a. Yes, it is a property line.

3. Cedar Creek 16 & 16A - Will we get paid for the extra width of each lift on the upstream repair due to the width of the 34” plow equipment?

a. We pay to neat-line and grades of the compacted Class A material and not for contractor convenience.

SITE VISIT

A field visit was made to Site 16 & 16A. All locations and works of improvement from the drawings were shown on the ground.

Sam Drummond Civil Engineering Technician – Project Engineer.

Texas State Watershed Construction cc: Shane Ice, State Conservation Engineer, Texas NRCS

Joe Forrest, Watershed Construction Engineer, Texas NRCS Jerry Creasser, Watershed Inspector, Texas NRCS Blake Boyer, Contract Specialist, FPAC

Questions and Anwers
Site Showing Technical Notes - Cedar Creek Site 16-16A
Changes and Corrections
special empHasis items

Cedar Creek 16 & 16A sign in sheet