S01 12FPC321R0016 Amendment 0003.pdf
PDF 1 MB Posted
- Attached to
- Construction of Rawson Hill Dam Rehabilitation Project - Worcester County, Massachusetts
- Solicitation number
- 12FPC321R0016
About this file
This solicitation requests proposals for the construction of the Rawson Hill Dam Rehabilitation Project located in Worcester County, Massachusetts. The major work items include clearing and grubbing, structure removal, seeding, mulching, earthwork, drainage, concrete work, and roller-compacted concrete. Interested contractors must be registered in the System for Award Management and complete annual representations and certifications electronically. A firm fixed price construction contract will be awarded using FAR Part 15 procedures. Bids are due by September 13, 2021 and must include a 20% bid guarantee. Performance and payment bonds of 100% will be required within 10 days of award. The period of performance is 153 calendar days from notice to proceed. The estimated value is between $1 million and $5 million. The NAICS code is 237990 and it is set aside for small business with a size standard of $39.5 million. Questions are due by September 3, 2021 to the listed contracting officer.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
12FPC321R0016
x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
FPAC-HQ-APD-TX
Fort Worth TX 76115-3404 501 W. Felix St., Building 23 Fort Worth Federal Center
FPAC BUS CNTR-ACQUISITION DIV-TX
FPAC-HQ-12FPC3
WASHINGTON DC 20250
1400 INDEPENDENCE AVE SW, RM 6801-S
FPAC BUS CNTR-ACQ DIV-OPS BRANCH-SE
09/09/20210003
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
08/12/2021
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Construction of Rawson Hill Brook Floodwater Retarding Dam -
Dam Rehabilitation Project located in Worcester County, Massachusetts
The purpose of this amendment is to provide answers to questions, issue a revised bid schedule, issue revised Specification 6, and issue revised drawing page 5 of 37.
Remove pages 6 and 7 of 52 (Part I - The Schedule, B-Supplies or Services and Prices) of the original solicitation and replace with the Revised Bid Schedule attached to this amendment. Changes to the bid schedule are in red.
Remove Construction Specification 6 in Attachment 1 Specifications and replace with
Construction Specification 6 Attached to this amendment. Changes to the specification are
Continued ...
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
LAUREEN M. EIPP
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 11
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
12FPC321R0016/0003
in red.
Remove drawing page 5 of 37 in Attachment 2
Drawings and replace with page 5 of 37 attached to this amendment. Boring locations have been added to this drawing.
Questions and Answers
Q1: Please clarify how the proposed planting schedules for shrubs & trees are to be paid for.
A1: The bid table and Construction Specification
No. 6 have been revised to clarify payment for tree and shrub planting.
Q2: Please confirm that all excavated material is to be spread throughout the existing auxiliary spillway and that no imported fill is required to reconstruct the spillway.
A2: The design intent was to balance cut and fill to eliminate the need for off-site borrow or off-site spoil. As indicated on Drawing Sheet 6, the spoil area may be modified to achieve cut-fill balance upon approval of the COR. The contractor is responsible for processing excavated soils as needed and controlling or adjusting soil moisture content as needed to make the soil materials suitable for use in the proposed fill. As detailed in Construction
Specification 23, Article 10.a.1, ¿Additional
Earthfill material is not anticipated to be required; however, if at any time additional
Earthfill material is determined to be required by the COR, the Contractor shall furnish and place suitable Earthfill material at no additional compensation from either an off-site location or borrow source following approval of the source and quality of the material by the
COR.¿
Q3: Please provide boring map that indicates where borings GF-1, GF-1A, GF-2, GF-201, GF-601, GF-602, GF-603 are located.
A3: Drawing Sheet 5 has been revised to show the locations of the borings.
The proposal due date is not extended. All proposals are due no later than September 13, 2021 at 2:00 pm Central Time.
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
Solicitation No. 12FPC321R0016
Updated thru FAC 2021-06 dated July 12, 2021 Page 6 of 52
PART I – THE SCHEDULE
Rawson Hill Brook Floodwater Retarding Dam Worcester County, Massachusetts
B - SUPPLIES OR SERVICES AND PRICES
This solicitation requires proposing on all line items, failure to do so will disqualify the bid.
Item No. Supplies/Services Spec.
No. Qty. Unit Unit Price Amount
1 Clearing & Grubbing 2 1 LS XXXX $
2 Structure Removal 3 1 LS XXXX $
3 Temporary Seeding and Mulching 5 1 LS XXXX $
4 Compost Filter Sock 5 1 LS XXXX $
Construction and Maintenance of Access
Roads
5 1 LS XXXX $
6 Seeding and Mulching 6 2.7* AC $ $
7 Surveys 7 1 LS XXXX $
8 Mobilization and Demobilization 8 1 LS XXXX $
9 Dewatering the Construction Site 11 1 LS XXXX $
10 Diverting Surface Water 11 1 LS XXXX $
11 Sheet Piling 13 3,370* SF $ $
12 Excavation, Unclassified 21 4,650* CY $ $
13 Compacting Structure Backfill 23 1 LS XXXX $
14 Earthfill, Approved, Class A 23 3,600* CY $ $
15 Earthfill, Random Class C 23 1,100* CY $ $
16 Fine Drainfill 24 260* CY $ $
17 Coarse Drainfill 24 280* CY $ $
18 Salvaging and Spreading Topsoil 26 2,400* CY $ $
19 Concrete, Backfill 31 2* CY $ $
20 Concrete, Reinforced 31 35* CY $ $
21 Roller-Compacted Concrete (RCC) 36 2,660* CY $ $
22 Roller-Compacted Concrete Test Section 36 1 LS XXXX $
23 Principal Spillway Conduit, 30” Diameter 41 20* LF $ $
24 Perforated Drain Pipe, 8” Diameter 45 150* LF $ $
Revised Bid Schedule
Solicitation No. 12FPC321R0011
Updated thru FAC 2021-06 dated July 12, 2021 Page 7 of 52
25 Non-Perforated Drain Pipe, 8” Diameter 45 200* LF $ $
26 Loose Rock Riprap 61 20* CY $ $
27 Construction Quality Control 94 1 LS XXXX $
28 Precast Concrete Manholes 401 2 EA $ $
29 Tree and Shrub Planting 6 1 LS XXXX $
TOTAL PRICE PROPOSAL $
COMPANY NAME:__________________________________________________________________
SUBMITTED BY:___________________________________DUNS#___________________________
52.211-18 Variation in Estimated Quantity. (Apr 1984) If the quantity of a unit-priced item in this contract is an estimated quantity and the actual quantity of the unit-priced item varies more than 15 percent above or below the estimated quantity, an equitable adjustment in the contract price shall be made upon demand of either party. The equitable adjustment shall be based upon any increase or decrease in costs due solely to the variation above 115 percent or below 85 percent of the estimated quantity. If the quantity variation is such as to cause an increase in the time necessary for completion, the Contractor may request, in writing, an extension of time, to be received by the Contracting Officer within 10 days from the beginning of the delay, or within such further period as may be granted by the Contracting Officer before the date of final settlement of the contract.
Upon the receipt of a written request for an extension, the Contracting Officer shall ascertain the facts and make an adjustment for extending the completion date as, in the judgement of the Contracting Officer, is justified.(End of clause)
Quantities marked with an * above are estimated quantities and the clause FAR 52.211-18, Variation in Estimated Quantity, applies.
ONE AWARD FOR THE AGGREGATE OF ALL ITEMS WILL BE MADE AS A RESULT OF
THIS SOLICITATION
Revised Bid Schedule
(210-VI-NEH, January 2014) 6–1
Construction Specification 6—Seeding, Sprigging, and Mulching
1. Scope The work consists of preparing the area for treatment; furnishing and placing seed, sprigs, mulch, fertilizer, inoculant, lime, and other soil amendments; and anchoring mulch in designated areas as specified.
The following BioPreferred® product categories are applicable to this specification:
— mulch and compost materials
— erosion control materials
— fertilizers
— agricultural spray adjuvants
2. Material Seed—All seed shall conform to the current rules and regulations of the state where it is being used and shall be from the latest crop available. It shall meet or exceed the standard for purity and germination listed in section 7.
Seed shall be labeled in accordance with the state laws and the U.S. Department of Agriculture rules and regulations under the Federal Seed Act in effect on the date of invitations for bids. Bag tag figures are evidence of purity and germination. No seed will be accepted with a test date of more than 9 months before the delivery date to the site.
Seed that has become wet, moldy, or otherwise damaged in transit or storage will not be accepted. The percent of noxious weed seed allowable shall be as defined in the current State laws relating to agricultural seeds. Each type of seed shall be delivered in separate sealed containers and fully tagged unless exception is granted in writing by the contracting officer.
Fertilizer—Unless otherwise specified, the fertilizer shall be a commercial grade fertilizer. It shall meet the standard for grade and quality specified by State law. Where fertilizer is furnished from bulk storage, the contractor shall furnish a supplier's certification of analysis and weight. When required by the contract, a representative sample of the fertilizer shall be furnished to the contracting officer for chemical analysis.
Inoculants—The inoculant for treating legume seeds shall be a pure culture of nitrogen-fixing bacteria prepared specifically for the species and shall not be used later than the date indicated on the container or as otherwise specified. A mixing medium, as recommended by the manufacturer, shall be used to bond the inoculant to the seed. Two times the amount of the inoculant recommended by the manufacturer shall be used except four times the amount shall be used when seed is applied using a hydraulic seeder. Seed shall be sown within 24 hours of treatment and shall not remain in the hydraulic seeder longer than 4 hours.
Lime and other soil amendments—Lime shall consist of standard ground agriculture limestone, or approved equivalent. Standard ground agriculture limestone is defined as ground limestone meeting current requirements of the State Department of Agriculture. Other soil amendments shall meet quality criteria and application requirements specified in section 7.
Mulch tackifiers—Asphalt emulsion tackifiers shall conform to the requirements of ASTM D 977, Specification for Emulsified Asphalt. The emulsified asphalt may be rapid setting, medium setting, or
(210-VI-NEH, January 2014) 6–2 slow setting. Nonasphaltic tackifiers required because of environmental considerations shall be as specified in section 7.
Straw mulch material—Straw mulch shall consist of wheat, barley, oat or rye straw, hay, grass cut from native grasses, or other plants as specified in section 7. The mulch material shall be air-dry, reasonably light in color, and shall not be musty, moldy, caked, or otherwise of low quality. The use of mulch that contains noxious weeds is not permitted. The contractor shall provide a method satisfactory to the contracting officer for determining weight of mulch furnished.
Other mulch materials—Mulching materials, such as wood cellulose fiber mulch, mulch tackifiers, synthetic fiber mulch, netting, and mesh, are other mulching materials that may be required for specialized locations and conditions. These materials, when specified, must be accompanied by the manufacturer's recommendations for methods of application.
3. Seeding mixtures, sod, sprigs, and dates of planting The application rate per acre for seed mixtures, sprigs, or sod and date of seeding or planting shall be as shown on the plans or as specified in section 7.
4. Seedbed preparation and treatment Areas to be treated shall be dressed to a smooth, firm surface. On sites where equipment can operate on slopes safely, the seedbed shall be adequately loosened (4 to 6 inches deep) and smoothed. Depending on soil and moisture conditions, disking or cultipacking, or both, may be necessary to properly prepare a seedbed. Where equipment cannot operate safely, the seedbed shall be prepared by hand methods by scarifying to provide a roughened soil surface so that broadcast seed will remain in place.
If seeding is to be accomplished immediately following construction operations, seedbed preparation may not be required except on a compacted, polished, or freshly cut soil surface.
Rocks larger than 6 inches in diameter, trash, weeds, and other debris that will interfere with seeding or maintenance operations shall be removed or disposed of as specified in section 7.
Seedbed preparation shall be discontinued when soil moisture conditions are not suitable for the preparation of a satisfactory seedbed as determined by the contracting officer's technical representative
(COTR).
5. Seeding, sprigging, fertilizing, mulching, and stabilizing All seeding or sprigging operations shall be performed in such a manner that the seed or sprigs are applied in the specified quantities uniformly in the designated areas. The method and rate of seed application shall be as specified in section 7. Unless otherwise specified, seeding or sprigging shall be accomplished within 2 days after final grading is completed and approved.
Fertilizer, lime, and other soil amendments shall be applied as specified in section 7. When specified, the fertilizer and soil amendments shall be thoroughly incorporated into the soil immediately following surface application.
The rate, amount, and kind of mulching or mesh shall be as specified in section 7. Mulches shall be applied uniformly to the designated areas. They shall be applied to areas seeded not later than 2 working days after seeding has been performed. Straw mulch material shall be stabilized within 24 hours of application using a mulch crimper or equivalent anchoring tool or by a suitable tackifier. When the mulch crimper or equivalent anchoring tool is used, it shall have straight blades and be the type manufactured expressly for and capable of firmly punching the mulch into the soil. Where the equipment can be safely
(210-VI-NEH, January 2014) 6–3 operated, it shall be operated on the contour. Hand methods shall be used where equipment cannot safely operate to perform the work required.
The tackifier shall be applied uniformly over the mulch material at the specified rate, or it shall be injected into the mulch material as it is being applied. Mesh or netting stabilizing materials shall be applied smoothly, but loosely on the designated areas. The edges of these materials shall be buried or securely anchored using spikes or staples as specified in section 7.
The contractor shall maintain the mesh or netting areas until all work under the contract has been completed and accepted. Maintenance shall consist of the repair of areas damaged by water erosion, wind, fire, or other causes. Such areas shall be repaired to reestablish the intended condition and to the design lines and grades required by the contract. The areas shall be refertilized, reseeded, and remulched before the new application of the mesh or netting.
6. Measurement and payment Method 1—For items of work for which specific unit prices are established in the contract, each area treated is measured as specified in section 7 and the area calculated to the nearest 0.1 acre. Payment for treatment is made at the contract unit price for the designated treatment, which will constitute full compensation for completion of the work.
When specified as an item of work, mesh or netting is measured to the nearest square yard of surface area covered and accepted. Payment is made at the contract unit price and will constitute full compensation for completion of the work.
Method 2—For items of work for which specific lump sum prices are established in the contract, the quantity of work will not be measured for payment. Payment for this item is made at the contract lump sum price for the item and will constitute full compensation for the completion of the work.
Method 3—For items of work for which lump sum prices are established in the contract, payment is made as the work proceeds. Progress payments will be determined as specified in section 7. Payment of the lump sum contract price will constitute full compensation for completion of the work.
All Methods—The following provisions apply to all methods of measurement and payment.
Compensation for any item of work described in the contract, but not listed in the bid schedule is included in the payment for the item of work to which it is made subsidiary. Such items and the item(s) to which they are made subsidiary are identified in section 7.
1/9/2019 5:33 PM
MA – RAWSON HILL DAM 6-4
7. Items of work and construction details
Items of work to be performed in conformance with this specification and the construction details are:
a. Bid Item 6, Seeding and Mulching
(1) This item shall consist of seeding and mulching to establish permanent cover over all disturbed areas within the construction limits shown on the Drawings.
(2) All areas that have been brought to final grade and those disturbed areas that will not be worked within one year’s time shall have permanent stabilization measures immediately applied.
(3) Permanent stabilization of vegetated areas, as referred to in this narrative, involves the stabilization and protection of the soil surface to an extent that will prevent erosion and eliminate offsite sedimentation. Typical permanent stabilization is obtained by placing rock riprap or establishing a vegetative cover across the disturbed area. Establish permanent vegetative cover of disturbed areas in accordance with the following:
(a) Permanent seeding shall be done within one of the following periods:
April 1 - May 31 August 1 - September 10 November 1 - December 15 as a dormant seeding
Seeding rates shall be increased by 50% for dormant seedings. If permanent stabilization activities occur outside of the allowable seeding dates, apply temporary stabilization measures.
(b) Prepare subgrade of areas to be seeded. Bring areas to rough grade and remove stones larger than 6 inches in diameter, organic material, and debris. Spread topsoil (12 inch minimum depth).
(c) The approved lines and grades for permanent seeding, at the time of permanent seeding, shall be maintained during and after the seeding and mulching operation.
Any area that has been damaged or had part or all of the seeding material removed, by any means, shall be repaired before acceptance will be made.
(d) The area to be repaired shall be filled and/or graded as needed to bring it back to original elevation and grade, seedbed prepared, and then it shall be refertilized, limed, seeded, and mulched at the specified rates.
(e) Prepare the soil surface by loosening soil to a depth of 4 to 6 inches by means of suitable agricultural or construction equipment, such as disk harrows, chisel plows, raking, or rippers mounted on construction equipment. Soil shall be left in a roughened condition.
(f) Soil Supplements: The rate of application will be determined by soil test. The Contractor shall submit soil test results prepared by a certified laboratory to the COR one week prior to seeding. Lime shall be added to correct the pH to between
5.5 and 6.0. The maximum amount of lime required will be 4 tons per acre. Apply
1/9/2019 5:33 PM
MA – RAWSON HILL DAM 6-5
a slow-release nitrogen fertilizer with the following minimum amounts of fertilizer applied per acre prior to seeding unless otherwise stipulated by the soil test:
Nitrogen (N) 100 pounds Phosphoric Acid (P2O5) 200 pounds Potash (K2O) 200 pounds
The above application can be met by applying material having an analysis of 10-20- 20 at the rate of 500 pounds per acre.
(g) Incorporate soil supplements into the top 4 to 6 inches of the soil by disking or other suitable means.
(h) Seedbed Preparation: Fertilizer and lime shall be applied prior to seedbed preparation. Equipment seedbed preparation shall be by one of the following methods:
Scarifying across the slope.
Disking across the slope.
Grading and tracking up and down the slope with a crawler tractor.
Areas inaccessible to equipment shall be hand-tilled to a depth of 1-1/2 inches.
(i) Seed: All legume seeds shall be inoculated. Seed may be inoculated in the hydroseeder when this type of equipment is used. All seed shall meet or exceed the following standards for purity, germination, and application rate:
Species Percent Purity
Percent Germination Rate/Acre1
Seeding Depth
Red Fescue (Festuca rubra L.) 95 85 10 lbs 1”
Canada Bluegrass (Poa compressa L.) 95 85 10 lbs 1”
Perennial Ryegrass (Lolium perenne L.) 95 85 10 lbs 1”
Redtop (Agrostis gigantea Roth.)
95 85 1 lbs 1”
1. When seeding is performed between November 1 and December 15, the rates of seed per acre shown above shall be increased by 50 percent.
(j) Sow permanent seed by use of hydroseeding methods, broadcasting, drop seeders or cultipacker seeders. Cover grass seed with soil using suitable equipment for that purpose.
(k) Lightly roll the seedbed area.
(l) Immediately after seeding, provide an anchored straw mulch spread uniformly in a continuous blanket at a rate of 826 pounds per 1,000 square yards (2 tons per acre).
9/8/2021 11:28 AM
MA – RAWSON HILL DAM 6-6
Anchor straw mulch with a non-asphaltic type mulch binder consisting of a free-flowing silicate powder with hydrophilic polymer additives mixed in water applied according to the manufacturer's recommendation. The Contractor shall submit in writing to the COR a request for approval of the selected mulch binding agent. The request by the Contractor shall include sufficient descriptive information (manufacturer's specifications) to allow a determination of acceptability and suitability to be made.
(4) Permanent stabilization of vegetative areas is considered to be a uniform erosion resistant perennial vegetation established to the point where the surface soil is capable of resisting erosion during runoff events and subsurface characteristics are sufficient to resist sliding and other movements. The standard for this vegetative cover will be a uniform coverage or density of 70% across the entire disturbed area.
(5) The COR shall determine if permanent stabilization has been established. The contractor shall be responsible for reseeding and mulching as needed to establish the uniform 70% coverage rate. These activities shall be performed at no additional cost to the government.
(6) Method 1 of Section 6 will apply. Measurements to determine the size of the area seeded shall be horizontal.
b. Bid Item 29, Tree and Shrub Planting
(1) This item shall consist of tree and shrub planting as shown on the Drawings for mitigation of required tree clearing activities.
(2) The areas of BVW mitigation and tree planting shall be as shown on the drawings.
(3) Place topsoil in the tree planting area as shown on the drawings prior to planting of trees.
(4) The COR shall provide final acceptance of all tree planting and the BVW mitigation area.
(5) For items of work for which specific lump prices are established in the contract, payment for
Tree and Shrub Planting is made at the contact lump sum price. Such payment shall constitute full compensation for all materials, labor, equipment, tools, and all other items necessary and incidental to the completion of the work.