AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE
0002 07/22/2021
6. ISSUED BY CODE FPAC-HQ-12FPC3
FPAC BUS CNTR-ACQ DIV-OPS BRANCH-SE
1400 INDEPENDENCE AVE SW, RM 6801-S
WASHINGTON DC 20250
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
1. CONTRACT ID CODE
4. REQUISITION/PURCHASE REQ. NO.
7. ADMINISTERED BY (If other than Item 6)
USDA-NRCS NEW YORK STATE
441 s. SALINA STREET
SUITE 354
ROOM 520
SYRACUSE NY 13202
9A. AMENDMENT OF SOLICITATION NO.
12FPC321B0013
X
9B. DATED (SEE ITEM 11)
06/24/2021
I
PAGE OF PAGES
1 I 2
5. PROJECT NO. (If applicable)
CODE INRCS-NY-122C31
OFFICE
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
IXI The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers IZl is extended. Dis not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
ORDER NO. IN ITEM 10A.
E. IMPORTANT:
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Contractor Dis not Dis required to sign this document and return ______ _ copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
EWP Streambank Stabilization - 4 Sites - City of Hattiesburg, Forrest County, Mississippi
This amendment serves to provide responses to questions and requests for information that have been received.
In addition, the slope protection materials to be installed on the Gordon's Creek@ Mccleod Street Site have been changed from grouted rock riprap to articulated blocks; and the Hi-Fi Cruisin site has been removed from the project.
The following documents are attached and incorporated into this amendment:
Continued ...
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 1 0A, as heretofore changed, remains unchanged and in full force and effect .
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED
(Signature of person authorized to sign)
Previous edition unusable
LAUREEN M. EIPP
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
16C. DATE SIGNED
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Solicitation No. 12FPC321B0013
Updated thru FAC 2021-05 dated March 10, 2021 Page 4 of 47
PART I – THE SCHEDULE
EWP Construction – City of Hattiesburg, Forrest County, Mississippi (Five (5) Sites - Hi-Fi Cruisin, Campbell Loop #3, Oceola McCarty Park, McClead @ Gordon Creek, and Forrest to McClead Sites)
B - SUPPLIES OR SERVICES AND PRICES
This solicitation requires bidding on all line items, failure to do so will disqualify the bid.
Item No.
Supplies/Services Spec.
Quantity Unit Unit Price Amount
Protective Cover
LS
XXXXXX
Mobilization and Demobilization
LS
XXXXXX
Earthfill, Class C (offsite)
100 *
CY
Rock Riprap
7,930 *
TN
Geotextile
1,040 *
SY
Concrete Grout
1,080 *
CY
Articulated Mat
See Notes of Plans
2,440*
SY
TOTAL BID: $____________________________
SUBMITTED BY:___________________________________DUNS#____________________
52.211-18 Variation in Estimated Quantity. (Apr 1984) If the quantity of a unit-priced item in this contract is an estimated quantity and the actual quantity of the unit-priced item varies more than 15 percent above or below the estimated quantity, an equitable adjustment in the contract price shall be made upon demand of either party. The equitable adjustment shall be based upon any increase or decrease in costs due solely to the variation above 115 percent or below 85 percent of the estimated quantity. If the quantity variation is such as to cause an increase in the time necessary for completion, the Contractor may request, in writing, an extension of time, to be received by the Contracting Officer within 10 days from the beginning of the delay, or within such further period as may be granted by the Contracting Officer before the date of final settlement of the contract.
Upon the receipt of a written request for an extension, the Contracting Officer shall ascertain the facts and make an adjustment for extending the completion date as, in the judgement of the Contracting Officer, is justified.(End of clause)
Updated thru FAC 2021-05 dated March 10, 2021 Page 5 of 47
Quantities marked with an * above are estimated quantities and the clause FAR 52.211-18, 52.211-18 Variation in Estimated Quantity, applies.
ONE AWARD FOR THE AGGREGATE OF ALL ITEMS WILL BE MADE AS A RESULT OF THIS
SOLICITATION
Updated thru FAC 2021-05 dated March 10, 2021 Page 6 of 47
C - DESCRIPTION/SPECIFICATIONS
The work consists of installing bank stabilization measures on designated slopes with concrete lined ditches. The major items of work include clearing and grubbing, pollution control, protective cover, removal of water, excavation, earthfill, diversions, loose rock riprap, concrete grout for rock riprap, and channel excavation.
This is an Emergency Watershed Protection streambank stabilization project on four sites located within the City of Hattiesburg, Forrest County, Mississippi. The sites are named:
• Hi-Fi Cruisin
• Campbell Loop #3
• Oceola McCarty Park
• McClead @ Gordon Creek
• Forrest to McClead
AGAR 452.211-72 Statement of Work/Specifications. (Feb 1998) The Contractor shall furnish the necessary personnel, material, equipment, services and facilities (except as otherwise specified), to perform the Statement of Work/Specifications referenced in Section J.
(End of clause)
AGAR 452.211-73 Attachments to Statement of Work/Specifications. (Feb 1988) The attachments to the Statement of Work/Specifications listed in Section J are hereby made part of this solicitation and any resultant contract.
(End of clause)
EWP Streambank Stabilization City of Hattiesburg, Forrest County, Mississippi
Solicitation: 12FPC321B0013
Pre-Bid Questions & RFI’s:
1. RIPRAP Suppliers: Spec Section 61 para 8 references the list of approved RIPRAP suppliers that is attached to the specifications. The list is dated April of 2000.
a. Is a more recent RIPRAP supplier list available or are there other approved quarries that are closer to the project site? The nearest supplier listed on the document is in Tuscumbia, AL.
To obtain current local suppliers, it's recommended you use your preferred online search engine.
b. Will the USDA accept material from a quarry that is a state approved quarry?
Yes. We will accept any quarry that can provide certification of meeting our material specifications.
2. Grouted Rock RIPRAP: The section detail that is shown on the contract drawings states that the “grouted rock riprap shall be grouted to within 6” of the surface”.
a. Is the surface considered the top of the riverbank? Please clarify.
The note is referring to rock surface.
3. Campbell Loop Road Site 3 (Sheet 8): This drawing provides quantities for RIPRAP and Protective Cover.
a. If the stone dike is to be installed per the detail please provide the length, start / stop, of the required dike construction.
Item is addressed in plan notes on Sheet 8.
b. Will construction be one continuous dike, or will it be broken up into sections based on the washout locations?
Item is addressed in plan notes on Sheet 8.
c. Will excavation, clearing and grubbing or bank sloping be required at this location?
Work required on this site is identified on plans and Construction Spec 2.
d. Will offsite fill material be required?
Work required on this site is identified on plans
e. Is there an estimated quantity for protective cover for this site?
No.
f. Is there a specific access point for construction at this location?
No.
4. Forrest Street to McCleod Site (Sheet 9): The comments under the section detail on this drawing states to “Shape and Backfill all Side slopes”. Based on the section detail itself it looks like excavation is required to achieve the required slope.
a. Is it intended that the excavated material is to be used to achieve the required slope?
Item is addressed in construction spec 21.
b. The detail also depicts the grouted RIPRAP stopping at some point below the top of the bank. Is there a dimension for how far below the top of bank that the riprap should stop?
Item is addressed in plan notes on Sheet 9.
c. Is there a centerline or baseline that will be provided in order to determine the width of the construction?
Item is addressed in plan notes on Sheet 9.
d. Please provide the length, start / stop, of the riverbank reinforcement.
Item is addressed in plan notes on Sheet 9.
e. Will construction be continuous, or will it be broken up into sections based on the washout locations?
Item is addressed in plan notes on Sheet 9.
f. Does the existing chain link fence along the side of the bank require removal and reinstall, or will it need to be disposed of?
Item is addressed in construction spec 3.
g. Please provide grout detail for the RIPRAP to be installed.
Item is addressed on sheet 5 of plans.
5. On 4 of the 5 sites there is either RCP or A2000 pipe entering the construction area. Is the pipe to remain in place, be removed and replaced, or removed completely?
Plans will identify any handling of pipes.
6. Hi-Fi Crusin Site (Sheet 4): One the north end of the site there is a washout on both the
East and West sides of the river. More specifically, on the West side, it appears to have a large drainpipe that has been collapsed by broken concrete due erosion under the existing concrete slab.
a. Please provide clarification on what will be done with the drain pipe and broken concrete. Also, is contractor responsible for backfilling under the existing concrete slab?
Site is removed in modified design plans.
b. Is there a specific access point for construction at this location?
Site is removed in modified design plans.
7. Gordon’s Creek Site (Sheet 2):
a. Is there a specific access point for construction at this location?
8. Oseola McCarty City Park Site (Sheet 6):
a. Will the large Magnolia & Oak tree remain in place along the stream bank or will the need to be removed and backfilled?
Item is addressed in construction spec 2.
9. For all sites where it may apply:
a. Can excess excavated material be spread onsite, or will it need to be hauled off?
Item is addressed in construction spec 21.
10. General:
a. Are there any survey requirements? Pre or post construction or progress surveys?
No post construction or progress surveys are required.
b. What are the as-built drawing requirements?
As-built drawings aren't required.
c. Are there any specific storm water pollution prevention requirements for the 5 sites?
Item is addressed in construction spec 5.
11. Forrest Street Site (sheet 9): The drawing states *Shape and Backfill all side slopes and protect with grouted Rock Rip Rap*.
a. Will Rip Rap need to be placed all the way across the creek as well, or will Rip Rap only be required on the banks?
Rock will be placed across the creek as identified in the cross section on sheet 9.
b. If Rip Rap is to be placed across the creek bottom as well, will Geotextile and Concrete grout be required in the creek bottom? From the detail on plan sheet 9; it appears to only show Rip Rap.
• Grout will be placed across the creek bottom as stated in the description of work on sheet 9 - "protect with grouted riprap."
• Geotextile will be placed under all riprap as shown in the detailed typical cross sections on pages 3, 5, and 7.
c. Are the Geotextile and Concrete Grout quantities accurate for this site?
All quantities are estimated based on site conditions at the time of evaluation. Actual quantities may vary.
12. Campbell Loop Road Site (Sheet 8): It is called out to install a peak stone dike to correct the 5 wash outs depicted on the plan sheet.
a. The detail provided shows the stone Dike to be at a height of 6’, topped surface at 3’; but does not provide an overall with. Please provide more detail.
The average height of the dike is 6'. Since the existing ground varies, the overall width will vary depending on the ground elevation at any given point. This is covered in the notes on Sheet 8 "Alignment, limits and placement of peak stone dike shall be directed in the field by the COR."
b. This location is heavily covered with large trees within the work zone that are to be cleared. Will the Stone Dike begin at the top of the bank top, or the toe of the water?
The dike will begin near the toe of the slope. This is covered in the notes on Sheet 8 "Alignment, limits and placement of peak stone dike shall be directed in the field by the
COR."
c. Please provide an estimated Quantity that is to be cleared prior to placing the Stone Dike.
Quantity of clearing is covered under construction specification 2.7.a.1.
d. How many access points are available at this site, and where are they located?
Access points are at the discretion of the contractor within the work limits identified on sheet 8.
e. Can the trees be mulched and left below the ground surface?
We currently do not have permission to bury debris on the properties.
13. “In the specs, page 61-4 #8, it states that the rock riprap shall be delivered to the site and stored in a rock box. Can you clarify this for me? Stephens Construction would like to dump and then place the material as it's dumped. Would that be a problem?”
61-4 #8 States “Rock riprap shall be delivered to the site at the rate it is placed or shall be stored in a rock box.”
14. What if I have a rock supplier that is not on the listed provided Being on the list has nothing to do with a supplier’s eligibility. Any supplier who provides certification that their rock meets our quality/gradation standards is acceptable.
1,040 1,080
7,930
Articulated Mat 2,440
GORDON"S CREEK AT MCCLEOD ST.
EMERGENCY WATERSHED PROTECTION
HATTIESBURG, MISSISSIPPI
FORREST COUNTY 2 of 7
PLAN VIEW
Geotextile 3,000 SY
Rock Riprap 360 TN
Norman.Patterson Line
Norman.Patterson Line
Norman.Patterson Line
GORDON"S CREEK AT MCCLEOD ST.
EMERGENCY WATERSHED PROTECTION
HATTIESBURG, MISSISSIPPI
FORREST COUNTY 3 of 7
SECTIONS
1 inch = 5 feet
GRAPHIC SCALE
( IN FEET )
07/15/2021
ESTIMATED QUANTITIES
E•covotion, Common Earthfill. Class C Geotextile Protective Cover Rock Riprop Concrete Grout
Notes:
1,560 CY
400 CY
1.540 SY
0.3 Acres
1,370 Tons
230 CY
Tie rockand grout into existingrockprolectionunder bridge as directed by the COR. Final alignment and placement of rock and grout shall be determined in the field by the COR.
Wont Limits shall be 100 feet downstream of Sta.
13+83, 50 feet upstream of Sta. 10+00, the channel centerline, and 100 feel left of station line excluding estoblished porkslructures.
GPS COORDINATES
N31" 19' 46.09"
W89" 18' 01.91"
DSR# 5294-301
RE\IISIONS
File No.
Drawing No.
Sheet4 of 7
! 2• 8ffl[· / og
Geotextile LJ 4'
ROCK RIPRAP KEY DETAIL
NOT TO SCALE
GRADATION NO. 2
STONE CUMULATIVE
WEIGHT PERCENT LIGHTER
POUNDS BY WEIGHT
200 100
80 50 - 85 40 15 - 50
10 0 - 15
Note:
�J?
O �fev� n �h�� ckco���!t t�r n;�II i��: a than 5% by weight.
f------19.5'-----+--4'
13'
4'
Geotextile
SECTION
Sta. 10+04 to Sto. 3+ 79
Grouted Rock Riprap shall be grouted to within 6" of surface
FIie No.
Drawing No.
RE\1SIONS
Sheot 5 of 7
SLOPE OF NA Wl REPOSE
///\\V//\\\
EXJSTING GROUND
STRUC. AZ. LINE
Parking Lot
400' of Severe Erosion Along Ditch.
Along ditch.
l Parking Lot
GPS COORDINATES
N 31.34908 W-89.35040
ROCK RIP RAP 1200 TON
CONCRETE GROUT OCY.
PROTECTIVE I LS.
GEOTEXTILE O SY.
EARTHFIU OCY
DSR#
28-4-18-5283-363
Notes:
Alignment, limits and placement of peak stone dike shall be directed in the field by the COR.
Work Limits shall be 100 LF upstream and downstream of rock placement limits and 75 ft left and right of peak stone dike centerline excluding buildings.
Protective cover estimate approximately 0.3 acres.
STONE CUMULATIVE
WEIGHT PERCENT LIGHTER
POUNDS BY WEIGHT
200 100
80 50 - 85
40 15 - 50
10 - 1
RE\IISIONS
I al i i l .2'
Ji ,1s 6 i=
File No.
Sheet6 of 7 r--r-------------�©
V,'-,j -o
------+�-----+---g
McLead
St i-1----------------------
!:'i
..ari ' f1>1 HoltoScole
Shape and Backfill all sideslopes, And protect with grouted Rock Rip Rap.
300' of Severe Erosion Along Ditch.
ROCK RIP RAP
CONCRETE GROUT
PROTECTIVE COVER
GEOTEXTILE
EARTHFILL
5000 TON
850 CY.
0.5 ACRE
5500 SY
100 CY
Notes:
Alignment, limits and placement of rock riprap bank stabilization will be as directed in the field by the C0R.
Work Limits shall be 100 LF upstream and downstream of rock placement limits and 75 ft left and right of centerline excluding buildings.
GRADATION NO. 2
STONE
WEIGHT
POUNDS
CUMULATIVE
PERCENT LIGHTER
BY WEIGHT
50 - 85
15 - 50
- 1
Note: �ea �?ev�n �h�1r�o��T!t t�?t n�� II �i�: 0 than Sr. by weight.
GPS COORDINATES
N 31.32719. W-89.29471
DSR#28-04-20-5294-303
RE\1SIONS
</2 .. I " II ,i a: ]i
! 1
FIie No.
Sheot 7 of 7
| 52.211-12 -- Liquidated Damages – Construction. (Sept 2000) |
| (a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $482.00 for each calendar day of delay until the work is completed or accepted. |
| 52.211-13 -- Time Extensions. (Sept 2000) |
| 52.204-8 Annual Representations and Certifications (Mar 2020) |
| (a) Definitions. As used in this provision— |