Questions and Answers Arising from site showing held 9/9/2020, 9 am at the KSPMC

Q. What are the specific requirements for the risers?

A. The risers are to be offset from the main pipeline 48”. The 48” offset may be either pvc or steel pipe, 4” minimum diameter. The elbow and upright portion of the riser must be 4” steel, the steel pipe must extend a minimum of 12” above the ground surface and be terminated with a 4” irrigation type stub valve. Each riser is to have a concrete thrust block.

Q Is the electrical power available at the well location 3 phase?

A. The electrical power available at the well location is 3 phase. Evergy is the power company, the meter number is 40314658 and the service address is 3800 s. 20th St, Manhattan, KS 66052. Please contact Evergy if more information about the electrical power is needed.

Q. At riser # 8, where the pipeline is to cross the driveway, is this to be an open cut in the driveway or is boring under the driveway required?

A. An open cut through the driveway is acceptable. The clearing of the trees necessary to cross the driveway will be done by the PMC staff utilizing PMC equipment.

Q. Is water at approximately 250 GPM available for the well drilling operation?

A. Water from well number 1 will be available for use during the drilling of the new well.

Q. When does the completed project have to be operational?

A. The completed project has to be operational before 4/15/2021.