Site Showing Questions and Answers.docx
DOCX document 16 KB Posted
- Attached to
- Charlotte Moore WRE - Clark County, Illinois Federal contract opportunity
- Solicitation number
- 12FPC320Q0049
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| S01. 12FPC320Q0049 Charlotte Moore, IL Solicitation.pdf | ||
| S01. Atch 1. Bid Schedule, Specifications, Drawings.pdf | ||
| WRE Alternate Access Roads.pdf | ||
| S01. 12FPC320Q0049 Charlotte Moore, IL Solicitation.pdf | ||
| RFI Form.pdf | ||
| S01. Atch 2. WD# IL20200002 Rev. 06.19.2020.pdf | ||
| S01. 12FPC320Q0049 Charlotte Moore, IL Solicitation.pdf | ||
| S01. Atch 1. Bid Schedule, Specifications, Drawings.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Charlotte Moore MRE Site Showing Questions:
Presentation and Site Visit Questions
1) Noted conflict between Solicitation document and Bid Schedule.
a) Determined a quantity error on bid item 3. An updated sheet will be added to the solicitation
2) Is there a performance bond or a bid bond?
a) This project has a performance bond; no bid bond.
3) Can brush be hauled off site?
a) Tree and Brush grub material can be removed from site for disposal. The removal will be at expense of contractor Removed trees may not be resold. Otherwise the cleared material will have to compile clearing and grubbing specification.
4) What is the current state of the haul road?
a) Haul road will require grubbing/clearing. Trees and brush will require removal along haul road to allow equipment to access swale and ditch plug site. Additionally, there will be a alternative haul road allowed. An attached map will be provided on solicitation. Although all routes will require clearing and grubbing.
5) What is required grubbing depth at pond site?
a) Per project Bid Schedule, Construction Specification 2 – Clearing and Grubbing, paragraph 7, 3., a., “The grub material… shall be grubbed to a minimum depth of 6”.”
b) The grubbed vegetative material will be placed in habitat mound
6) Is there a specified construction timing/phase for the ditch plug?
a) Timing of ditch plug construction is determined by contractor; not specified in plans. It will be the contractor’s responsibility to anticipate weather events and ensure moisture and compaction requirements will be met per specifications
7) Is there a type of fill from the pond site that is not wanted for plug construction?
a) Per project Bid Schedule, Construction Specification 21 – Excavation, paragraph 10, 2., b., “The plug material shall be free of sod, roots, frozen soil, stones over 4” and other vegetative material.” No restriction for soil type is specified for plug construction.
8) Where can a brush pile be located near existing wetland pool area on east side of haul road, inside of tree line entrance?
a) Brush pile not to be located within wetland area. Contractor can establish brush pile within tree line.
9) Can additional fill from pool excavation be placed on haul road if road conditions deteriorate?
a) Fill for haul road construction can be used but must get prior approval from engineering ahead of placement. Any fill from above current condition will be required to be removed at end of construction at contractor’s expense. It is not required to add fill material, and an alternative haul road map will be provided
10) Is the proposed haul road the “best/shortest” option to access the swale and plug site?
a) Based on current conditions, the proposed haul road is the “best/shortest” option to access the swale and plug site. If conditions change during construction, an alternate haul road map will be provided and approved by engineer. See attached map for details.
11) What are the limitations (physical) of the haul road construction?
a) Contractor will clear and grub the haul road to meet job requirements. Haul road width can be twice the width of construction equipment and shall be leveled prior to completion of project. Responsibility of contractor to keep the haul road graded so government inspector can access site for inspection activities.
12) During clearing and grubbing operations, what items are not acceptable for fill material?
a) Per, Construction Specification 21 – Excavation, paragraph 10, 2., b., “The plug material shall be free of sod, roots, frozen soil, stones over 4” and other vegetative material.
13) What is the flow direction of the river in relation to site?
a) Flooding of the site varies, we encourage contractor to monitor local river hydrographs. The estimated river stage that floods the site is a 13’-14’ river
14) What is the layout for the ditch plug?
a) Profile for ditch plug confirmed on sheet six of ten of project site plans.
15) Does the plug site need to be grubbed?
a) Confirmed that the plug site will require grubbing and clearing. Per Bid Item #3 – Excavation, Common – Ditch Plug Spoil Placement – 2,546cy, paragraph 2., a., “Footprint of ditch plug shall be grubbed according to specification, clearing and grubbing prior to placement of any material.”
16) Where do trees from plug site go?
a) Trees removed from the plug site can be piled on site to the east of the existing ditch. Trees cannot be burnt without proper permitting and approval. Root wads removed from plug site will be hauled to habitat mound. If root wad filled with dirt and larger in size than specified brush piles. The root wad can be sawed of the tree trunk and trunk can go in brush pile and root wad in the habitat mound.
17) If trees and brush are grinded on site by contractor, what can they do with the remaining debris?
a) Debris from grinding of trees and brush on site can be left on site but cannot be incorporated into plug fill material and cannot be so think on seeding areas the prevents new seed growth.
18) After ditch plug site is cleared, what can contractor do with small (two-inch diameter and less) root material?
a) Per project Bid Schedule, Construction Specification 21 – Excavation, paragraph 10, 2., b., “The plug material shall be free of sod, roots, frozen soil, stones over 4” and other vegetative material.
19) What will be the rock check structure?
a) Rock check profile confirmed on sheet ten of ten in project site plans. Rock check construction details listed in Bid Item #5 – Rock Riprap.
20) How critical is seeding (implication of seeding impact on project timeline based on site condition)?
a) Seeding shall be in accordance with Construction Specification 6.