A-8 QA Version 2 - 082620.docx

DOCX document 13 KB Posted

Attached to
McCloud River Loop Recreation Site Access Maintenance Federal contract opportunity
Solicitation number
129AC720Q0088
Issued by
Department of Agriculture Forest Service

View the file

Other files for this federal contract opportunity

Other files attached to McCloud River Loop Recreation Site Access Maintenance, newest first.
File Type Posted
A-8 QA Version 4 - 090120.docx DOCX document
A-8 QA Version 3 - 082720.docx DOCX document
A-8. Drainage Ditch Points.pdf PDF
A-8 Site Plan - Revised.pdf PDF
A-8 QA Version 1 082520.docx DOCX document
A-7.2 Sign Example.pdf PDF
A-7 129AC720Q0088.pdf PDF
A-7 Experience Questionnaire.pdf PDF
A-7.1 Site Plan.pdf PDF
A-7.3 WD 2015-5677, Rev 13 06.13.2020.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Rec Loop Maintenance (129AC720Q0088) Questions and Answers Document

Subsequent versions of this document will contain questions from all previous versions.

Version 2: 08/26/2020

Q1 – What is the desired height of the fire ring? According to the supplier is comes in different heights.

A1 – The desired fire ring dimensions are 56” wide X 11-3/8” (suggested supplier: Pilot Rock, Model FS-56)

Q2 – Where does the ditch run exactly?

A2 – Attached is a map of what the engineers had planned. The ditch would be roughly 100’ with 1-2 cross drains. The ditch feature will be clearly mark onsite before the start of work.

Q3 – What exact roof style would you want on the kiosk? The supplier shows different styles/colors A3 – Kiosk shed roof style: green with metal shingle (suggested supplier: RockArt, Model 03-440)

Q4 – The site plan does not seem to show all the locations where boulders are or need to be placed.

Q4 – A revised site plan showing the missing areas where boulders need to be placed and where existing boulders are currently (highlighted in yellow). This does not change the overall contract needs of roughly 150 boulders to be installed.

Version 1: 08/25/2020

Q1 – What is the set aside for the requirement? The solicitation says Unrestricted Women-Owned Small Business.

A1 – The set aside in Block 10 of the solicitation should reflect Set Aside 100% for Small Business. This requirement IS NOT being solicited on an unrestricted business.

Q2 – Are bonds required?

A2 – Bonds are not required as this is not considered a construction project