Sawyers Bar Generator Building Repairs

TECHNICAL SPECIFICATIONS

SAWYERS BAR GENERATOR BUILDING

EMERGENCY REPAIRS

April 25, 2019

(Revision 00)

TABLE OF CONTENTS

Table of Contents

SECTION 01010 - SUMMARY OF WORK

SECTION 01040 - PROJECT COORDINATION

SECTION 01060 - REGULATORY REQUIREMENTS

SECTION 01300 - SHOP DRAWINGS AND SUBMITTALS

SECTION 01430 - CONTRACTOR QUALITY CONTROL

SECTION 01700 - PROJECT CLEAN UP

SECTION 02010 - SITE CONDITIONS

SECTION 02050 - DEMOLITION/DEBRIS REMOVAL

SECTION 05500 - METAL FABRICATIONS

SECTION 06100 - ROUGH CARPENTRY

SECTION 07190 - BUILDING PAPER

SECTION 07200 - BUILDING INSULATION

SECTION 07251 - SELF-ADHERED MEMBRANE FLASHINGS

SECTION 07400 - METAL ROOFING AND SIDING SYSTEM

SECTION 07600 - FLASHING AND SHEET METAL

SECTION 07900 - JOINT SEALERS

SECTION 08111 - STANDARD STEEL DOORS AND FRAMES

SECTION 08710 - DOOR HARDWARE

SECTION 09260 - GYPSUM DRYWALL AND FINISHES

SECTION 09900 - PAINTING

SECTION 15010 - GENERAL MECHANICAL REQUIREMENTS

SECTION 16010 - GENERAL PROVISIONS ELECTRICAL

SECTION 16050 - BASIC ELECTRIC MATERIALS AND METHODS

SECTION 16100 - GENERATORS

SECTION 16510 - LIGHTING FIXTURES

SUMMARY OF WORK 01010

SECTION 01010 - SUMMARY OF WORK

PART 1 - GENERAL

1.1 PROJECT DESCRIPTION

Replace Two Prime Power Diesel Generators (Complete)

• Furnish all labor, materials, tools, transportation and equipment to remove and replace two prime power diesel generators, including but not necessarily limted to:

• Removal, crate-up and transport of two existing 60kW diesel generators from USFS Sawyers

Bar Work Center, Sawyers Bar, CA to USFS Yreka Service Center at 1030 So. Main Street, Yreka, CA 96097, specific delivery location at Yreka site to be determined at a later date.

• Furnish and install two new 60kW prime power diesel generators, including engines, alternators, electrical systems, exhaust systems, cooling systems, fueling systems (connect to existing tank supply lines), and digital controls system and control panel display.

• Digital Control System to include at a minimum: system monitoring and diagnostics, English units on operator display panel, remote access capability, AC protection, engine protection, integrated voltage regulation, alternator and engine data, alpha numeric display with push button access for viewing system status, start up and manual setup & adjustments.

• Repair sheet metal transformor housing outside building that was damaged by fallen tree.

• Compliance with NFPA and NEMA requirements

• Compliance with EPA Stationary Non-Emergency; Tier 4 CARB desirable

• Enclosure not required.

• Provide complete start up services by an Authorized Generator Factory Representative to ensure the generator is installed properly and functioning correctly. Services to include a 30 day follow-up inspection.

Repair Generator Metal Building (see attached 1984 drawings)

• Repair 16’x30’ Generator Metal Building

• Furnish all labor, materials, tools, transportation and equipment to remove and replace damaged building components, and ancillary building systems related to making repairs and providing a complete weather tight, insulated and finished building, inside and out.

• Work includes but is not necessarily limited to, removal and replacement of damaged:

exterior metal siding, structural members (steel girts and 2x4 wood framing), furing, blocking, wall and ceiling R-19 insulation; ½” CDX interior plywood backing, sound deadening panels, doubled up ½” drywall, drywall taping and and joint compund, interior lower wall plywood sheathing, interior lower wall 18GA sheet metal wainscoat; heavy duty insultated/sound attenuating steel doors, frames and lockset; air intake ducting screens and angle frames with fasteners, 2 places (inside and out);

electrical conduit, conductors, and fixtures for replacement lighting; caulking, cleaning walls, and priming and painting interior and exterior walls and ceiling. Repair exterior lighting. See 1984 drawings for generator building layout and wall/ceiling section details and notes.

• In general, tree damage to building is concentrated on the right side of the building, however the entire building repairs entail new lighting, and associated conduit & conductors, cleaning and preparation of walls and ceiling for primer and paint, including exterior sheet metal wall and roof surfaces.

Location of Work The project work items are located at the Sawyers Bar Work Center of the Salmon River Ranger District, Klamath National Forest, 25415 Sawyers Bar Road, Sawyers Bar, CA 96027.

To reach the site from Yreka, CA, head south on Main St and continue on Hwy 3 for approximately 28 miles to Etna, CA. Continue through Etna on Collier Way one-half mile to the stop sign at Main Street/Sawyers Bar Road and turn right. Continue on Sawyers Bar Road approximately 25 miles to Sawyers Bar (15 MPH). The Work center is on the right hand side approximately ½ mile west after entering the community of Sawyers Bar. See Vicinity and Location Maps included with the solicitation

Site Visit

A bidders site visit will be scheduled prior to due date for proposals.

List of Attachments

• Sawyers Bar Vicinity & Site Maps (2 pages)

• Sawyers Bar Generator Building Dwgs – 1984 (3 pages)

• Sawyers Bar Generator Building Photos ( 5 pages)

• Sawyers Bar Generators 1 & 2 Photos (3 pages)

• Sawyers Bar Generators 1 & 2 Load Record Dec 2012 – Feb 2019

Power Outages During Performance Of The Work

It is important to minimize power outage periods during the performance of the work.

Normal operation is to run these generators alternatively on two-week intervals, with basic servicing of one while the other is in operation. This is to be the general operation during removal and replacement of the generators (as well as for the building repairs), such that removal and replacement of one generator is underway while the other is fully operating and powering the site. The Contractor’s technicians and electricians involved with the work shall be thoroughly familiar with prime power generator operations. Procedures for powering up/powering down are in the generator building. The government will not allow prolonged power outages, however from time to time it may be necessary to accomplish the work. In which case, a total of four 8-hour outages will be allowed, separated by no less than 72 hours each, with advance notice of 72 hours to the Government (the COR) and Siskiyou Telephone Co. for each occurrence.

Points of Contact for Outages:

USFS: Kelly Nolan, Facilities Engineer, (530) 841-4431 USFS: Ken Kellogg, Forest Engineer, (530) 841-4536

Siskiyou Telephone Co.: Dan Rimmer, (530) 467-6145

Special Conditions Affecting Work

Contractor shall be responsible for preventing fuel spills on soil during the course of the work and promptly cleaning up any spills in the generator building.

Time For Completion

The project must be complete and ready for acceptance by September 30, 2019. This includes start up and testing and final clean-up of the premises. Factory follow-up inspection to occur 30 days from final acceptance.

Utilities

Contractor shall provide all temporary power, as necessary, for construction of this work. Power, when generators are operating, and water are on site for use by the Contractor. Temporary restrooms for construction workers shall be provided by the Contractor as needed. Contractor shall be responsible for locating and protecting above and below ground utilities in the project areas.

Contractor Use of Premises

• Construction yards and/or storage areas are the responsibility of the Contractor.

• Confine operations at site to areas agreed by the Contracting Officer.

• Do not encumber site with materials or equipment.

• Do not load structure or roadway with weight that will endanger or render unusable any structures or roadways.

• Assume full responsibility for protection and safekeeping of products stored on premises.

• Move any stored products which interfere with operations of Owner.

• Return all surface areas to their original condition upon completion of the work.

PART 2 - PRODUCTS

Not Used.

PART 3 – EXECUTION

Not Used.

**END OF SECTION 01010**

PROJECT COORDINATION 01040

SECTION 01040 - PROJECT COORDINATION

1.1 SCOPE

A. This Section specifies administrative and supervisory requirements necessary for Project coordination including, but not necessarily limited to:

1. Coordination.

2. Contractor's personnel.

3. General installation provisions.

4. Cleaning and protection.

1.2 COORDINATION

A. Coordination: Coordinate construction activities included under various Sections of these

Specifications to assure efficient and orderly installation of each part of the Work.

Coordinate construction operations included under different Sections of the Specifications that are dependent upon each other for proper installation, connection, and operation.

1. Where installation of one part of the Work is dependent on installation of other components, either before or after its own installation, schedule construction activities in the sequence required to obtain the best results.

2. Where availability of space is limited, coordinate installation of different components to assure maximum accessibility for required maintenance, service and repair.

3. Make adequate provisions to accommodate items scheduled for later installation.

B. Conservation: Coordinate construction activities to ensure that operations are carried out with consideration given to conservation of energy, water, and materials.

1.3 SUBMITTALS

A. Coordination Drawings: Prepare and submit coordination Drawings where close and careful coordination is required for installation of products and materials fabricated offsite by separate entities, and where limited space availability necessitates maximum utilization of space for efficient installation of different components.

1. Indicate required installation sequences.

2. Comply with requirements contained in Section "Shop Drawings and Submittals."

PART 2 - PRODUCTS

Not Applicable

PROJECT COORDINATION 01040

PART 3 - EXECUTION

3.1 GENERAL INSTALLATION PROVISIONS

A. Inspection of Conditions: Require the Installer of each major component to inspect both the substrate and conditions under which Work is to be performed. Do not proceed until unsatisfactory conditions have been corrected in an acceptable manner.

B. Manufacturer's Instructions: Comply with manufacturer's installation instructions and recommendations, to the extent that those instructions and recommendations are more explicit or stringent than requirements contained in Contract Documents.

C. Inspect materials or equipment immediately upon delivery and again prior to installation.

Reject damaged and defective items.

D. Provide attachment and connection devices and methods necessary for securing Work.

Secure Work true to line and level. Allow for expansion and building movement.

E. Visual Effects: Provide uniform joint widths in exposed Work. Arrange joints in exposed

Work to obtain the best visual effect. Refer questionable choices to the Contracting Officer for final decision.

F. Recheck measurements and dimensions, before starting each installation.

G. Install each component during weather conditions and Project status that will ensure the best possible results. Isolate each part of the completed construction from incompatible material as necessary to prevent deterioration.

H. Coordinate temporary enclosures with required inspections and tests, to minimize the necessity of uncovering completed construction for that purpose.

I. Mounting Heights: Where mounting heights are not indicated, install individual components at standard mounting heights recognized within the industry for the particular application indicated. Refer questionable mounting height decisions to the Contracting Officer for final decision.

3.2 CLEANING AND PROTECTION

A. During handling and installation, clean and protect construction in progress and adjoining materials in place. Apply protective covering where required to ensure protection from damage or deterioration at Substantial Completion.

B. Clean and maintain completed construction as frequently as necessary through the remainder of the construction period. Adjust and lubricate operable components to ensure operability without damaging effects.

**END OF SECTION 01040**

8 REGULATORY REQUIREMENTS 01060

SECTION 01060 - REGULATORY REQUIREMENTS

A. This section describes the codes and standards which apply to the work in this contract.

Additional codes and standard may be cited in sections to which they apply.

1.2 CODES AND STANDARDS

A. The following codes and standards, current editions, shall apply to the work in this contract:

1. International Building Code (IBC)

2. National Electrical Code (NEC)

3. National Electrical Manufacturers Association (NEMA)

4. Americans with Disabilities Act (ADA), Architectural Barriers Act (ABA).

5. American Institute of Steel Construction (AISC) Latest Edition.

6. American Iron and Steel Institute (AISI) Latest Edition.

7. American Society for Testing and Materials (ASTM) latest edition.

8. Metal Buildings Manufacturers Association (MBMA).

9. Underwriter's Laboratories, (UL)

10. Architectural Aluminum Manufacturers Association (AMMA)

11. Steel Door Institute, Standard 100

12. American Water Works Association (AWWA)

13. National Fire Protection Association (NFPA)

14. California Fire Code (CFC) 2010 Edition

B. Unless otherwise specified in this contract, reference to a specific standard or specification shall mean the latest edition or amendment in effect on the date of the invitation to bid.

1.3 DEFINITIONS

A. Administrative Authority as used in the California Mechanical Code, the California

Plumbing Code and the National Electrical Code will be the Contracting Officer.

B. Building Official as used in the California Fire Code, International Building Code and the National Electrical Code Standards will be the Contracting Officer.

**END OF SECTION 01060**

SHOP DRAWINGS AND SUBMITTALS 01300

9 Sawyers Bar Generator

SECTION 01300 - SHOP DRAWINGS AND SUBMITTALS

1.1 SCOPE:

A. The term submittal means all documents required for determining conformance with the contract as indicated herein. Documents include but are not limited to Shop Drawings, Samples, Catalog Data, Installation Instructions, Certifications and Test Results.

1.2 SUBMITTALS

A. Submittals shall include all pertinent data required to understand the quality of components, dimensional relationships, integration with other materials, assembly techniques, structural aspects, color, finish, texture, and other such characteristics as may be necessary to fully describe the item and its intended use.

B. All submittals shall be transmitted to the Contracting Officer Representative using the

Contract_Transmittal.doc form attached separately to this contract.

PART 2 – PRODUCTS

3.1 SUBMITTALS

A. Submittals and shop drawings shall be submitted in a timely fashion to allow 14 calendar days for review by the Government. "No work shall begin until associated shop drawings and submittals are approved".

3.2 SHOP DRAWINGS

A. Original Submittal: Two copies of all shop drawings shall be submitted for approval as required under 3.01, above, prior to fabrication, installation or order placement to allow for checking and coordination.

B. Resubmittal: When a resubmittal is required, one print so indicating will be returned to the Contractor. After revision of the original, a new reproducible and four copies shall be submitted for approval.

C. Approval: Once approved, documents shall be returned to the Contractor and shall be complied with as noted. Variation from the approved documents shall be likewise submitted and approved before being carried out.

SHOP DRAWINGS AND SUBMITTALS 01300

10 Sawyers Bar Generator

3.3 SAMPLES

A. Samples of each item for which samples are required, unless otherwise specified, shall be furnished for approval. Approval shall be obtained prior to delivery of the material to the project site. These samples shall be representative of the actual material proposed for use in the project and of sufficient size to demonstrate design, color, texture and finish as they will appear in the completed installation.

3.4 CATALOG DATA

A. Submittals: Two copies of catalog data are required for the original submittal and each resubmittal. Catalog data shall be submitted along with shop drawings. One copy will be returned.

B. Data: Each submittal shall have all pertinent data contained therein that is applicable to the item submitted for approval.

3.5 IDENTIFICATION

A. Catalog Data: Each separate catalog brochure or page submitted shall have the identification shown. Catalog of brochures submitted containing multiple items for approval need have only cover identification. In such cases the identification shall include page and catalog item numbers.

B. In the event one or more of the multiple items are not approved in any submittal, the additional copies required will not be requested until all items are approved.

**END OF SECTION 01300**

11 CONTRACTOR QUALITY CONTROL 01430

SECTION 01430 - CONTRACTOR QUALITY CONTROL

1.1 SCOPE: This work of this Section shall consist of the Contractor providing quality control to ensure compliance with the referenced drawings, specifications, and provisions of the contract. The Contractor shall provide all personnel, equipment, tests, and reports necessary to meet the requirements of this specification. See FAR Clause 52.246-12 Inspection of Construction.

1.2 GOVERNMENT TESTING/INSPECTION: The Government may at its option monitor the testing and inspection of the Contractor and may perform additional testing/inspections to verify compliance with the contract documents. In addition to the Contractors everyday inspections the Government will perform the following inspections: foundation, rough framing/shear, rough-in; plumbing, electrical and mechanical and final inspection. Contractor shall coordinate the Government inspections with the work progress and provide a lead time of one week.

PART 2 - PRODUCTS (Not Applicable)

3.1 QUALITY CONTROL SYSTEM:

A. The Contractor shall provide and maintain a quality control system that will ensure that all services, supplies, and construction required under this contract conform to the contract requirements. The Contractor shall perform, or cause to be performed, the sampling, inspection, and testing required to ensure that all supplies, services, and construction conform to the contract requirements.

**END OF SECTION 01430**

12 PROJECT CLEANUP 01700 Sawyers Bar Generator

SECTION 01700 - PROJECT CLEAN UP

1.1 DESCRIPTION

A. This section covers the disposal of excess material from clearing and grubbing, excavation, building construction, cleaning or any other operation in which waste is generated.

1.2 MEASUREMENT AND PAYMENT

A. No separate payment shall be made for work specified in this section. Compensation for this work will be considered included in the payment for the completed project.

3.01 WORKMANSHIP

A. All debris and unused material shall be removed from the site. All debris shall be disposed of off National Forest land in accordance with local regulations. Site shall be restored to as near its original condition as possible.

B. Concrete trucks shall not be washed out in the project area. Burning of material is not allowed.

C. Building shall be swept clean of all debris and dust. Windows and roof shall be cleaned of all dust and marks.

**END OF SECTION 01700**

13 SITE CONDITIONS 02010

SECTION 02010 - SITE CONDITIONS

1.1 INFORMATION ON SITE CONDITIONS

A. Information obtained by the designer regarding site conditions, subsurface information, and existing facilities, and similar data are shown on the Plans.

1.2 CONTRACTOR'S RESPONSIBILITIES

A. The Contractor shall satisfy himself as to the nature and location of the work, the general and local conditions, particularly those bearing upon availability of transportation, disposal, handling and storage of materials, availability of labor, water, electric power, roads, work in sensitive environment and uncertainties of weather, or similar physical conditions at the site, the conformation and conditions of the ground, the character of equipment facilities needed preliminary to and during the prosecution of the work and all other matters which can in any way affect the work or the cost thereof under this contract.

B. The Contractor shall satisfy himself as to the character, quality, and quantity of surface and subsurface materials to be encountered from inspecting the site as well as from information presented by the referenced information and specifications made a part of this contract. Any failure by the Contractor to acquaint himself with all the available information will not relieve him from responsibility for properly estimating the difficulty or cost of successfully performing the work.

1.3 ADDITIONAL INFORMATION

see attachments

**END OF SECTION 02010**

DEMOLITION/DEBRIS REMOVAL 02050

SECTION 02050 - DEMOLITION/DEBRIS REMOVAL

L

1.1 DESCRIPTION

Selective removal and disposal of damaged building components. Removal, Crate-up and transport of Generators to Yreka, CA.

1.2 JOB CONDITIONS

A. Disposition of material:

1. Title to materials:

a. Title to all materials to be removed, except as specified otherwise, is vested in the Contractor upon receipt of notice to proceed. The Owner will not be responsible for the condition or loss of, or damage to, such property after notice to proceed.

b. Generators to be transported to the USFS Yreka Service Center, 1030 So. Main Street, Yreka, CA 96097. Exact location for placement at Service Center will be determined at a later date.

2. Reuse of materials and equipment:

a. Carefully remove and store materials and equipment indicated to be reused or relocated to prevent damage, and reinstall as the work progresses.

B. Cleanup:

1. Debris and rubbish:

a. Contain, remove and transport debris and rubbish in a manner that will prevent spillage to adjacent areas.

2. General:

a. Use all means necessary to protect existing structures designated to remain and, in the event of damage, immediately make all repairs and replacements necessary to the approval of the Engineer at no additional cost to the Owner.

C. UTILITY SERVICES

1. The Contractor shall arrange with the utility provider to shut off utilities when necessary. See restriction on power outages elsewhere in these specifications.

2. At no times shall the Contractor interrupt existing utilities that serve occupied or active facilities, except when authorized in writing to do so by the COR.

3. Perform all operations to avoid breakage, marring, bending or other damage to existing structures or utilities, which are to remain.

4. If damage is done to any adjacent facilities caused by demolition operations, the Contractor shall promptly repair the damage. All costs for repair of damaged facilities shall be at the Contractor’s expense.

PART 2 – PRODUCTS - Not Applicable

DEMOLITION/DEBRIS REMOVAL 02050

3.1 SITE INSPECTION

A. Prior to any clearing removal work, carefully inspect the site and determine the extent of work involved.

B. Report any discrepancy to the Engineer immediately, including any obstructions which are not noted or shown on the plans or described herein. Protect such facilities until further direction is received from the COR. Additional work required due to unforeseen conditions shall be performed as directed by the Contracting Officer and will be paid for as extra work in accordance with the General Conditions. No extra work is authorized without written approval from the Contracting Officer.

3.2 COORDINATION AND SCHEDULING

A. Coordinate work with the COR.

3.3 SAFETY

A. All work shall conform to pertinent OSHA regulations and to other State and local codes and ordinances as applicable.

3.4 REMOVAL OF DEBRIS

A. Remove all debris from the site and leave the site in a neat and orderly condition and legally dispose of off the project site at an approved disposal site.

**END OF SECTION 02050**

METAL FABRICATIONS 05500

SECTION 05500 - METAL FABRICATIONS

A. This section includes the following metal fabrications:

1. Miscellaneous framing and supports.

2. Pipe bollards (if shown).

B. Related Sections: None

A. General: Submit the following in accordance with Conditions of Contract and

Division 1 Specification Sections.

B. Product data for products used in miscellaneous metal fabrications, including paint products and grout.

C. Shop drawings detailing fabrication and erection of overhead door supports and pipe bollards. Include plans, elevations, sections, and details of metal fabrications and their connections. Show anchorage and accessory items. Provide templates for anchors and bolts specified for installation under other sections.

D. Samples representative of materials and finished products as may be requested by Contracting Officer.

E. Welder certificates signed by Contractor certifying that welders comply with requirements specified under "Quality Assurance" article.

1.3 QUALITY ASSURANCE

A. Fabricator Qualifications: Firms experienced in successfully producing metal fabrications similar to that indicated for this Project, with sufficient production capacity to produce required units without causing delay in the Work.

B. Installer Qualifications: Arrange for installation of metal fabrications specified in this section by same firm that fabricated them.

C. Qualify welding processes and welding operators in accordance with AWS D1.1 "Structural Welding Code - Steel," D1.3 "Structural Welding Code - Sheet Steel", and D1.2 "Structural Welding Code - Aluminum."

1. Certify that each welder has satisfactorily passed AWS qualification tests for welding processes involved and, if pertinent, has undergone recertification.

1.4 PROJECT CONDITIONS

A. Field Measurements: Check actual locations of walls and other construction to which metal fabrications must fit, by accurate field measurements before fabrication; show recorded measurements on final shop drawings. Coordinate fabrication schedule with construction progress to avoid delay of Work.

2.1 FERROUS METALS

A. Metal Surfaces, General: For metal fabrications exposed to view upon completion of the Work, provide materials selected for their surface flatness, smoothness, and freedom from surface blemishes. Do not use materials whose exposed surfaces exhibit pitting, seam marks, roller marks, rolled trade names, roughness, and, for steel sheet, variations in flatness exceeding those permitted by reference standards for stretcher-leveled sheet.

B. Steel Plates, Shapes, and Bars: ASTM A 36.

C. Steel Pipe: ASTM A 53; finish, type, and weight class as follows:

1. Galvanized finish for exterior installations and where indicated.

2. Type S, Grade B, standard weight (schedule 40), unless otherwise indicated, or another weight required by structural loads.

D. Brackets, Flanges and Anchors: Cast or formed metal of the same type material and finish as supported rails, unless otherwise indicated.

E. Welding Rods and Bare Electrodes: Select in accordance with AWS specifications for the metal alloy to be welded.

2.2 GROUT AND ANCHORING CEMENT

A. Non-shrink Nonmetallic Grout: Premixed, factory-packaged, non-staining, non-corrosive, nongaseous grout complying with CE CRD-C 621. Provide grout specifically recommended by manufacturer for interior and exterior applications of type specified in this section.

B. Erosion-Resistant Anchoring Cement: Factory-prepackaged, non-shrink, non-staining, hydraulic controlled expansion cement formulation for mixing with water at Project site to create pourable anchoring, patching, and grouting compound.

Provide formulation that is resistant to erosion from water exposure without need for protection by a sealer or waterproof coating and is recommended for exterior use by manufacturer.

2.3 FASTENERS

A. General: Provide zinc-coated fasteners for exterior use or where built into exterior walls. Select fasteners for the type, grade, and class required.

B. Bolts and Nuts: Regular hexagon head type, ASTM A 307, Grade A.

C. Lag Bolts: Square head type, FS FF-B-561.

D. Machine Screws: Cadmium plated steel, FS FF-S-92.

E. Wood Screws: Flat head carbon steel, FS FF-S-111.

F. Plain Washers: Round, carbon steel, FS FF-W-92.

G. Toggle Bolts: Tumble-wing type, FS FF-B-588, type, class, and style as required.

H. Lock Washers: Helical spring type carbon steel, FS FF-W-84.

2.4 PAINT

A. Shop Primer for Ferrous Metal: Manufacturer's or fabricator's standard, fast-curing, lead-free, universal modified alkyd primer selected for good resistance to normal atmospheric corrosion, for compatibility with finish paint systems indicated, and for capability to provide a sound foundation for field-applied topcoats despite prolonged exposure complying with performance requirements of

FS TT-P-645.

B. Galvanizing Repair Paint: High zinc dust content paint for re-galvanizing welds in galvanized steel, with dry film containing not less than 94 percent zinc dust by weight, and complying with DOD-P-21035 or SSPC-Paint-20.

2.5 FABRICATION, GENERAL

A. Form metal fabrications from materials of size, thickness, and shapes indicated but not less than that needed to comply with performance requirements indicated.

Work to dimensions indicated or accepted on shop drawings, using proven details of fabrication and support. Use type of materials indicated or specified for various components of each metal fabrication.

B. Form exposed work true to line and level with accurate angles and surfaces and straight sharp edges.

C. Allow for thermal movement resulting from the following maximum change (range) in ambient temperature in the design, fabrication, and installation of installed metal assemblies to prevent buckling, opening up of joints, and overstressing of welds and fasteners. Base design calculations on actual surface temperatures of metals due to both solar heat gain and nighttime sky heat loss.

1. Temperature Change (Range): 100 deg F (55.5 deg C).

D. Shear and punch metals cleanly and accurately. Remove burrs.

E. Ease exposed edges to a radius of approximately 1/32 inch, unless otherwise indicated. Form bent-metal corners to smallest radius possible without causing grain separation or otherwise impairing work.

F. Remove sharp or rough areas on exposed traffic surfaces.

G. Weld corners and seams continuously to comply with AWS recommendations and the following:

1. Use materials and methods that minimize distortion and develop strength and corrosion resistance of base metals.

2. Obtain fusion without undercut or overlap.

3. Remove welding flux immediately.

4. At exposed connections, finish exposed welds and surfaces smooth and blended so that no roughness shows after finishing and contour of welded surface matches those adjacent.

H. Form exposed connections with hairline joints, flush and smooth, using concealed fasteners wherever possible. Use exposed fasteners of type indicated or, if not indicated, Phillips flat-head (countersunk) screws or bolts. Locate joints where least conspicuous.

I. Provide for anchorage of type indicated; coordinate with supporting structure.

Fabricate and space anchoring devices to provide adequate support for intended use.

J. Shop Assembly: Pre-assemble items in shop to greatest extent possible to minimize field splicing and assembly. Disassemble units only as necessary for shipping and handling limitations. Use connections that maintain structural value of joined pieces. Clearly mark units for reassembly and coordinated installation.

K. Cut, reinforce, drill and tap miscellaneous metal work as indicated to receive finish hardware, screws, and similar items.

L. Fabricate joints that will be exposed to weather in a manner to exclude water, or provide weep holes where water may accumulate.

2.6 ROUGH HARDWARE

A. Furnish bent or otherwise custom fabricated bolts, plates, anchors, hangers, dowels, and other miscellaneous steel and iron shapes as required for framing and supporting woodwork, and for anchoring or securing woodwork to concrete or other structures. Straight bolts and other stock rough hardware items are specified in Division 6 sections.

B. Fabricate items to sizes, shapes, and dimensions required. Furnish malleable-iron washers for heads and nuts which bear on wood structural connections; elsewhere, furnish steel washers.

2.7 MISCELLANEOUS FRAMING AND SUPPORTS

A. General: Provide steel framing and supports for applications indicated or which are not a part of structural steel framework, as required to complete work.

B. Fabricate units to sizes, shapes, and profiles indicated and required to receive adjacent other construction retained by framing and supports. Fabricate from structural steel shapes, plates, and steel bars of welded construction using mitered joints for field connection. Cut, drill, and tap units to receive hardware, hangers, and similar items.

1. Equip units with integrally welded anchors for casting into concrete or building into masonry. Furnish inserts if units must be installed after concrete is placed.

a. Except as otherwise indicated, space anchors 24 inches o.c. and provide minimum anchor units in the form of steel straps 1-1/4 inches wide x 1/4 inch x 8 inches long.

C. Galvanize miscellaneous framing and supports in the following locations:

1. Exterior locations.

2. Interior locations where necessary.

2.8 FINISHES, GENERAL

A. Comply with NAAMM "Metal Finishes Manual" for recommendations relative to application and designations of finishes.

B. Finish metal fabrications after assembly. See Division 9 Section "Painting" for finish.

2.9 STEEL AND IRON FINISHES

A. Preparation for Shop Priming: Prepare uncoated ferrous metal surfaces to comply with minimum requirements indicated below for SSPC surface preparation specifications and environmental exposure conditions of installed metal fabrications:

1. Exteriors (SSPC Zone 1B): SSPC-SP6 "Commercial Blast Cleaning."

B. Apply shop primer to uncoated surfaces of metal fabrications, except those with galvanized finish or to be embedded in concrete, unless otherwise indicated.

Comply with requirements of SSPC-PA1 "Paint Application Specification No. 1" for shop painting.

1. Stripe paint all edges, corners, crevices, bolts, welds, and sharp edges.

3.1 PREPARATION

A. Coordinate and furnish anchorages, setting drawings, diagrams, templates, instructions, and directions for installation of anchorages, including concrete inserts, sleeves, anchor bolts, and miscellaneous items having integral anchors that are to be embedded in concrete construction. Coordinate delivery of such items to project site.

B. Set sleeves in concrete with tops flush with finish surface elevations; protect sleeves from water and concrete entry.

3.2 INSTALLATION, GENERAL

A. Fastening to In-Place Construction: Provide anchorage devices and fasteners where necessary for securing miscellaneous metal fabrications to in-place construction; include threaded fasteners for concrete inserts, toggle bolts, through-bolts, lag bolts, wood screws, and other connectors as required.

B. Cutting, Fitting, and Placement: Perform cutting, drilling, and fitting required for installation of miscellaneous metal fabrications. Set metal fabrication accurately in location, alignment, and elevation; with edges and surfaces level, plumb, true, and free of rack; and measured from established lines and levels.

C. Provide temporary bracing or anchors in formwork for items that are to be built into concrete construction.

D. Fit exposed connections accurately together to form hairline joints. Weld connections that are not to be left as exposed joints, but cannot be shop welded because of shipping size limitations. Do not weld, cut, or abrade the surfaces of exterior units which have been hot-dip galvanized after fabrication, and are intended for bolted or screwed field connections.

E. Field Welding: Comply with AWS Code for procedures of manual shielded metal-arc welding, appearance and quality of welds made, methods used in correcting welding work, and the following:

1. Use materials and methods that minimize distortion and develop strength and corrosion resistance of base metals.

2. Obtain fusion without undercut or overlap.

3. Remove welding flux immediately.

4. At exposed connections, finish exposed welds and surfaces smooth and blended so that no roughness shows after finishing and contour of welded surface matches those adjacent.

F. Secure non-removable units to supporting members by welding where both materials are the same; otherwise, fasten by bolting as indicated above.

3.3 SETTING LOOSE PLATES

A. Clean concrete bearing surfaces of any bond-reducing materials, and roughen to improve bond to surfaces. Clean bottom surface of bearing plates.

B. Set loose leveling and bearing plates on wedges, or other adjustable devices. After the bearing members have been positioned and plumbed, tighten the anchor bolts.

Do not remove wedges or shims, but if protruding, cut off flush with the edge of the bearing plate before packing with grout.

1. Use metallic non-shrink grout in concealed locations where not exposed to moisture; use nonmetallic non-shrink grout in exposed locations, unless otherwise indicated.

2. Pack grout solidly between bearing surfaces and plates to ensure that no voids remain.

3.4 ADJUSTING AND CLEANING

A. Touch-Up Painting: Immediately after erection, clean field welds, bolted connections, and abraded areas of shop paint, and paint exposed areas with same material as used for shop painting to comply with SSPC-PA 1 requirements for touch-up of field painted surfaces.

1. Apply by brush or spray to provide a minimum dry film thickness of 2.0 mils.

B. For galvanized surfaces clean welds, bolted connections and abraded areas and apply galvanizing repair paint to comply with ASTM A 780.

**END OF SECTION 05500**

ROUGH CARPENTRY 06100

SECTION 06100 - ROUGH CARPENTRY

A. The scope of this Section includes the following:

1. Framing with dimension lumber.

2. Framing with engineered wood products.

3. Wood nailers, and blocking.

4. Sheathing.

1.2 DEFINITIONS

A. Rough carpentry includes carpentry work not specified as part of other Sections and generally not exposed, unless otherwise specified.

1.3 SUBMITTALS

A. Include lumber certification as part of Section 01300 submittals

1.4 DELIVERY, STORAGE, AND HANDLING

A. Delivery and Storage: Keep materials under cover and dry. Protect against exposure to weather and contact with damp or wet surfaces. Stack lumber as well as plywood and other panels; provide for air circulation within and around stacks and under temporary coverings including polyethylene and similar materials.

1. For lumber and plywood pressure treated with waterborne chemicals, place spacers between each bundle to provide air circulation.

1.5 QUALITY CONTROL

A. Codes and Standards

1. International Building Code, 2009 Edition.

2. Industry Standards

a. WCLIB Standard Grading Rules No. 16, for Lumber.

b. WWPA Western Lumber Grading Rules.

c. U.S. Bureau of Standards PS-1, for plywood.

d. Redwood Inspection Service Standard Specifications.

B. Quality of products and installation shall conform to codes and standards referenced above, as applicable.

C. Moisture Content: Air-dry untreated lumber, with sticking both horizontally and vertically, for not less than 30 days prior to installation. Kiln-dry treated lumber to 19 percent moisture content.

D. Grade Stamps: All lumber and plywood shall be grade-stamped.

2.1 LUMBER, GENERAL

A. Lumber Standards: Furnish lumber manufactured to comply with PS 20 "American Softwood Lumber Standard" and with applicable grading rules of inspection agencies certified by American Lumber Standards Committee's (ALSC) Board of Review.

B. Inspection Agencies: Inspection agencies and the abbreviations used to reference them with lumber grades and species include the following:

1. RIS - Redwood Inspection Service.

2. WCLIB - West Coast Lumber Inspection Bureau.

3. WWPA - Western Wood Products Association.

C. Grade Stamps: Provide lumber with each piece factory-marked with grade stamp of inspection agency evidencing compliance with grading rule requirements and identifying grading agency, grade, species, moisture content at time of surfacing, and mill.

D. Nominal sizes are indicated, except as shown by detail dimensions. Provide actual sizes as required by PS 20, for moisture content specified for each use.

1. Provide dressed lumber, S4S, unless otherwise indicated.

2. Provide seasoned lumber with 19 percent maximum moisture content at time of dressing and shipment for sizes 2 inches or less in nominal thickness, unless otherwise indicated.

2.2 DIMENSION LUMBER

A. All dimension lumber shall be graded as indicated on the drawings or as otherwise used as standard industry practice.

B. Sill plates in contact with concrete shall be pressure treated Douglas fir - No. 1 for structural walls and construction grade for non-structural walls. Or at non-structural walls, foundation grade redwood may be substituted.

2.3 MISCELLANEOUS LUMBER

A. General: Provide lumber for support or attachment of other construction including cant strips, bucks, nailers, blocking, furring, grounds, stripping, and similar members.

B. Fabricate miscellaneous lumber from dimension lumber of sizes indicated and into shapes shown.

C. Moisture content: 19 percent maximum for lumber items not specified to receive wood preservative treatment.

D. Grade: "Standard" grade light-framing-size lumber of any species or board-size lumber as required. "No. 3 Common" or "Standard" grade boards per WCLIB or WWPA rules or "No. 2 Boards" per SPIB rules.

2.4 CONSTRUCTION PANELS, (PLYWOOD), GENERAL

A. Construction Panel Standards: Comply with PS 1 "U.S. Product Standard for

Construction and Industrial Plywood" for plywood construction panels and, for products not manufactured under PS 1 provisions, with APA PRP-108.

B. Trademark: Furnish construction panels that are each factory-marked with APA trademark evidencing compliance with grade requirements.

2.5 CONCEALED PERFORMANCE-RATED CONSTRUCTION PANELS

A. General: Where construction panels are indicated for the following concealed types of applications, provide APA Performance-Rated Panels complying with requirements designated under each application for grade designation, span rating, exposure durability classification, edge detail (where applicable), and thickness.

B. Trademarks: Factory-mark each construction panel with APA trademark evidencing compliance with grade requirements.

C. Structural Plywood for roof, wall and floor sheathing shall be as indicated on the drawings. Comply with paragraph 2.04 (C) above.

2.6 CONSTRUCTION PANELS FOR BACKING

A. Plywood Backing Panels: For mounting electrical or telephone equipment, provide fire-retardant-treated plywood panels with grade designation, APA C-D PLUGGED EXPOSURE 1, in thickness indicated, or, if not otherwise indicated, not less than 15/32 inch.

2.7 AIR INFILTRATION BARRIER

A. Tyvek Housewrap or approved equal.

2.8 FASTENERS

A. General: Provide fasteners of size and type indicated that comply with requirements specified in this article for material and manufacturer.

1. Where rough carpentry is exposed to weather, in ground contact, or in area of high relative humidity, provide fasteners with a hot-dip zinc coating per ASTM A 153 or of AISI Type 304 stainless steel.

2. Use hot-dipped galvanized or stainless steel fasteners in preservative-treated lumber as specified in the Code and on the drawings.

B. Nails, Wire, Brads, and Staples: FS FF-N-105.

C. Power Driven Fasteners: National Evaluation Report NER-272.

D. Wood Screws: ANSI B18.6.1.

E. Lag Bolts: ANSI B18.2.1.

F. Bolts: Steel bolts complying with ASTM A 307, Grade A, with ASTM A 563 hex nuts and where indicated, flat washers.

2.9 METAL FRAMING ANCHORS

A. General: Provide metal framing anchors of type, size, metal, and finish indicated that comply with requirements specified including the following:

1. Current Evaluation/Research Reports: Provide products for which model code evaluation/research reports exist that are acceptable to authorities having jurisdiction and that evidence compliance of metal framing anchors for application indicated with the building code in effect for this Project.

2. Allowable Design Loads: Provide products for which manufacturer publishes allowable design loads that are determined from empirical data or by rational engineering analysis and that are demonstrated by comprehensive testing performed by a qualified independent testing laboratory.

B. Galvanized Steel Sheet: Steel sheet zinc-coated by hot-dip process on continuous lines prior to fabrication to comply with ASTM A 525 for Coating Designation G60 and with ASTM A 446, Grade A (structural quality); ASTM A 526 (commercial quality); or ASTM A 527 (lock-forming quality); as standard with manufacturer for type of anchor indicated.

1. Use galvanized steel framing anchors for rough carpentry exposed to weather, in ground contact, or in area of high relative humidity, and where indicated.

2.10 MISCELLANEOUS MATERIALS

A. Water Repellent Preservative: NWWDA-tested and -accepted formulation containing 3-iodo-2-propynyl butyl carbonate (IPBC) as its active ingredient.

2.11 PRESERVATIVE WOOD TREATMENT BY PRESSURE PROCESS

A. General: Where lumber or plywood is indicated as preservative-treated wood or is specified herein to be treated, comply with applicable requirements of AWPA Standards C2 (Lumber) and C9 (Plywood). Mark each treated item with the AWPB Quality Mark Requirements.

B. Pressure-treat above-ground items with water-borne preservatives to a minimum retention of 0.25 pcf. For interior uses, after treatment, kiln-dry lumber and plywood to a maximum moisture content, respectively, of 19 percent and 15 percent. Treat indicated items and the following:

1. Wood cants, nailers, curbs, equipment support bases, blocking, stripping, and similar members in connection with roofing, flashing, vapor barriers, and waterproofing.

2. Wood sills, sleepers, blocking, furring, stripping, and similar concealed members in contact with masonry or concrete.

C. Complete fabrication of treated items prior to treatment, where possible. If cut after treatment, coat cut surfaces to comply with AWPA M4. Inspect each piece of lumber or plywood after drying and discard damaged or defective pieces.

3.1 INSTALLATION AND WORKMANSHIP, GENERAL

A. Members shall be accurately cut to required dimensions and shall be firmly secured with metal connectors true to the lines, levels, and dimensions indicated, all in accordance with the UBC.

B. Where there is a significant variation in moisture content between individual members, shrinkage shall be allowed for and final connections shall not be made until moisture content of adjacent members has been stabilized. Allow no construction over framing members until final connections and/or adjustments have been made to achieve maximum strength at connections and minimum future movement from shrinkage or expansion.

C. Discard units of material with defects that impair quality of rough carpentry construction and that are too small to use in fabricating rough carpentry with minimum joints or optimum joint arrangement.

D. Fit rough carpentry to other construction; scribe and cope as required for accurate fit. Correlate location of furring, nailers, blocking, grounds, and similar supports to allow attachment of other construction.

E. Securely attach rough carpentry work to substrate by anchoring and fastening as indicated.

F. Bore bolt holes true to line and of 1/16 inch greater diameter than bolts. Drive bolts into place with a tight fit and provide with plates or washers as indicated on the Drawings. Turn up and make tight all nuts, bolts, and lag screws at time of installation and again just before enclosed with other fixed materials, or at the completion of the work, to ensure that shrinkage has been overcome and the fastenings are tight.

G. No lubricant of any kind shall be used on any fastener depending on friction for holding.

H. Screws shall not be driven by hammering.

I. Countersink nail heads on exposed carpentry work and fill holes.

J. Use common wire nails, unless otherwise indicated. Use finishing nails for finish work. Select fasteners of size that will not penetrate members where opposite side will be exposed to view or will receive finish materials. Make tight connections between members. Install fasteners without splitting of wood; predrill as required.

K. Members (other than all heart Redwood) which are in contact with concrete exposed to weather, shall be treated a distance of 2'-0" along their length from point of contact with two flowing coats of 5% Pentachlorophenol (or copper napthenate solution, if not to be stained).

L. Coordinate installation of open web trusses, glue laminated beams, plate connected wood trusses.

M. Tolerances:

1. Framing Members: 1/4 inch maximum from true position.

2. Surface Flatness of Floor: 1/4 inch in 10 feet maximum.

3.2 WOOD GROUNDS, NAILERS, BLOCKING, AND SLEEPERS

A. Provide and install wood grounds, nailers, blocking, and sleepers where shown and where required for screening or attachment of other work. Form to shapes as shown and cut as required for true line and level of work to be attached.

Coordinate location with other work involved.

B. Attach to substrates as required to support applied loading. Countersink bolts and nuts flush with surfaces, unless otherwise indicated. Where possible, anchor to formwork before concrete placement.

3.3 WOOD FRAMING, GENERAL

A. Framing Standard: Comply with National Forest Products Association (N.F.P.A.)

"Manual for House Framing," unless otherwise indicated.

B. Install framing members of size and spacing indicated. Coordinate with other framing and to other trades prior to actual construction.

C. Anchor and nail as shown, and to comply with the following:

1. National Evaluation Report No. NER-272 for pneumatic or mechanical driven staples, P-Nails, and allied fasteners.

2. Published requirements of manufacturer of metal framing anchors.

3. "Recommended Nailing Schedule" of referenced framing standard and with

N.F.P.A. "National Design Specifications for Wood Construction."

D. Do not splice structural members between supports.

E. Provide solid blocking at all joist or truss supports (2x framing depth), unless otherwise noted.