A6. J3_Schedule of Items_0001.xlsx
XLSX spreadsheet 20 KB Posted
- Attached to
- Front Country Ranger District HVAC Replacements Federal contract opportunity
- Solicitation number
- 12970223Q0060
- Issued by
- Department of Agriculture Forest Service
About this file
This document provides instructions and a schedule of items for an independent government cost estimate related to the solicitation for Front Country Ranger District HVAC Replacements. The solicitation number is 12970223Q0060 and is being issued by the Department of Agriculture Forest Service. The schedule of items lists nine line items including air conditioners, furnaces, coils, thermostats, miscellaneous parts, crane rental, mobilization, and labor. Offerors are required to provide unit prices and total prices for each line item. The period of performance for any resulting contract is from date of award through December 31, 2023.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| SF30_12970223Q0060_0002.pdf | ||
| SF 30_12970223Q0060_0001.pdf | ||
| J1_Statement of Work_0001.docx | DOCX document | |
| J2_Specifications.pdf | ||
| 12970223Q0060.pdf | ||
| J3_Schedule of Items.xlsx | XLSX spreadsheet | |
| J1_Statement of Work.docx | DOCX document | |
| J4_Davis-Bacon Act WD CA20230017.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Instructions
INSTRUCTIONS: HOW TO USE THIS FORM
| Independent Government Estimate (IGE) |
| No specific format is required for an IGE; however this must be an independent estimate and not a reiteration of a contractor quote. The selected format should generally be in the same level of detail and manner that the Schedule of Items pricing we request from contractors. The estimate should state any underlying assumptions or rationale used in formulating the estimate. Initially the CO will use the IGE to determine the estimated value of the procurement and to identify the appropriate procurement thresholds applicable to the solicitation. Later the IGE is compared to prices received to evaluate an offeror’s understanding of the government requirements and in supporting a price reasonableness determination. |
EXPLANATION OF TABS
| Stand Alone IGE: | Use if the below do not apply to your requirement. |
| Stand Alone IGE w/options: | Use if you have a requirement where you know you have an ongoing/recurring need year after year. |
| IDIQ: | Use if you have a need that is reoccurring or multi-year requirement. |
| Task Order: | Use if you want to issue a order against an existing contract or agreement. |
SOI
SCHEDULE OF ITEMS
San Bernardino National Forest PROJECT TITLE: Front Country Ranger District HVAC Replacements SOLICITATION NO: 12970223Q0060
| Period of Performance | Date of Award through 12/31/2023 | |||||
| SCHEDULE OF ITEMS | ||||||
| ITEM | ||||||
| NUMBER | DESCRIPTION | QTY | Unit of Issue | Unit Price | Total Price | |
| 0001 | Air conditioner | 2 | EA | $0.00 | ||
| 0002 | Roof mounted down flow furnace (Millcreek) | 1 | EA | $0.00 | ||
| 0003 | Up flow furnace (Lytle creek) | 2 | EA | $0.00 | ||
| 0004 | Air conditioner coil | 2 | EA | $0.00 | ||
| 0005 | Thermostat | 3 | EA | $0.00 | ||
| 0006 | Miscellaneous parts | 1 | LS | $0.00 | ||
| 0007 | Crane Rental | 4 | HR | $0.00 | ||
| 0008 | Mobilization | 2 | LS | $0.00 | ||
| 0009 | Labor | 1 | LS | $0.00 | ||
| TOTAL | $ - 0 |
| EA = Each |
| HR = Hour |
| LS = Lump Sum |
File details come from the government source that posted it. Updated .