RFQ-12970222Q4006
Project: Donovan Tank, Bull Tank & Government Tank-Stock Tank Cleaning Question and Answers Question 1:
Can you please clarify if the contractor has to haul off the sediment or if the sediment can be removed from the ponds and spread across the adjacent areas? Also, is the contractor required to perform any environmental remediation, ie seeding?
Answer: The soil is not removed. It is usually used to build up and reenforce the banks of the stock tanks. No remediation needed.