Question - Response Final.pdf
PDF 57 KB Posted
- Solicitation number
- 12905B24Q0147
About this file
This document appears to be a set of questions and responses related to a federal contract opportunity for driveway construction and parking lot work at a USDA facility in Hilo, Hawaii.
The key details are: The solicitation number is 12905B24Q0147, with a construction project value between $25,000 and $100,000. The scope includes constructing a driveway and parking pad, with specific requirements for the base, pavement type, and edge finish. Contractors are responsible for providing their own staging area and equipment. All questions were due by August 6, 2024, and proposals were due by August 13, 2024. Performance and payment bonds will be required if the awarded contract exceeds certain dollar thresholds. The contracting agency is the USDA Agricultural Research Service, Pacific West Area.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Question/Response – Revision 9-12-2024 Driveway Construction to Insectary
Hilo HI
QUESTIONS ARE CLOSED. NO FURTHER QUESTIONS WILL BE ENTERTAINED.
Q - Could not find a paving schedule on the SOW documents describing the requirements for material type and requirements needed to build up and create a subgrade before paving asphalt parking pad slab. Please advise.
R – Compacted ¾” base course with fines.
CORRECTION TO RESPONSE:
Recommend a compacted 1 and 1/2 inch structured fill with tines for the base. The contractor is responsible to determine the quantity.
The type of pavement mix is AC County Mix #4.
Q - Please confirm the finish of the edges of the driveway.
R - Tapered edges
Q - Please confirm the finish of the parking pad.
R - Standard finish for commercial parking pad
Q - There will be a reveal that can erode once we cut down our rough grade on high spots on the driveway. Can you please confirm what this retaining finish will be?
R - Compacted and tapered
Q - Please confirm contractor will be allowed a staging area for equipment, roll offs and material.
R – Yes, the contractor shall be responsible for any equipment, supplies, vehicles stored on site.
The Government is not liable for theft or loss of contractor stored items.