United States Department of Agriculture Agricultural Research Service
STATEMENT OF WORK
BUILDING 413 SEWER LINE REPLACEMENT
SOUTHWEST WATERSHED RESEARCH CENTER
TUCSON, AZ
Date: May 26, 2022 (Rev 1-2023)
STATEMENT OF WORK
1.0 CONTRACT PROJECT:
0. Project Number: TBD
0. Project Title: BUILDING 413 Sewer line replacement.
| 0. Project Location: | Southwest Watershed Research Center | |
| 2000 E. Allen Road, Tucson AZ |
2.0 PROJECT CONTACT PERSONS:
a. CONTRACTING OFFICER (CO):
Email: Tel. No.:
b. CONTRACTING SPECIALIST (CS):
Email: Tel. No.:
c. LOCATION MONITOR (LM):
Roger Clemo
USDA-ARS-PWA
2000 E. Allen Road, Tucson AZ 85719 Email: roger.clemo@usda.gov Tel. No.: 520-330-1896
d. ADMINISTRATIVE OFFICER (AO):
Laura Elmore
USDA-ARS-PWA
2000 E. Allen Road, Tucson AZ 85719 Email: laura.elmore@usda.gov Tel. No.: 520-647-9160
e. CONTRACTING OFFICERS REPRESENTATIVE (COR):
Email: Tel. No.:
f. AREA SAFETY AND HEALTH MANAGER
Email: phil.smith@usda.gov Tel. No.: 979-260-9449
g. ENGINEERING PROJECT MANAGER (EPM) Email: Tel. No.:
3.0 PROJECT
DESCRIPTION:
Provide all services necessary to replace existing sewer lines in men’s and women’s restrooms, including converting one toilet area in each to a shower, removing existing equipment, installing new equipment, electrical, flooring, walls, counter, and sink. Existing flooring will need to be abated (ACT-Environmental Survey report attached) Sewer line needs to be replaced from the fixtures to the trunk line, determine if main trunk line is compromised and need to be replaced before covering.
4.0 PROJECT REQUIREMENTS:
1. Provide standard commercial warranties on equipment and one year on workmanship.
1. Contractor shall provide and maintain all necessary guards, lights, barricades, etc., to protect persons, property, and materials in and around the site.
1. The Contractor’s work shall adhere to the criteria stated within these project requirements, drawings, and specifications. All construction shall comply with applicable federal, state, and local code requirements as well as current industry standards, (i.e., IBC, NEC, NSPC, NFPA, EPA, ASTM, GSA, AASHTO, etc.) and health and safety codes, in effect at the time of contract award.
1. No Architectural or Engineered drawings are needed.
4.1 Background & Site Description:
Building 413 is an occupied by the Southwest Watershed Research Center (SWRC). This group does research on underground watersheds.
4.2 Bid Schedule:
Provide all labor, equipment, and materials to perform this Statement of Work and Schedule of Items
4.3 Description of Work:
a. Demolition
i. Abatement of both restroom floor.
ii. Remove sinks, cabinets, toilets (4 total), and Urinal (1 total)
iii. Remove partitions, walls as needed, concrete flooring, and old cast iron sewer lines to include venting pipes.
iv. Prevent damage to existing utilities and construction that are not scheduled for demolition. If damage occurs, make repairs to the satisfaction of the Contracting Officer and at no cost to the Government.
v. All demolished materials and equipment must be removed from government property and disposed in accordance with applicable laws and regulations.
vi. Save existing doors and hardware to be reinstalled.
b. New installations
i. Install new Sewer line to an acceptable cut in the existing line to be used.
1. Replace all lighting with new updated LED lighting.
Install single lavatories in both men’s and women’s restrooms. Use standard commercial material, cabinet, top, sink, and faucet.
2. Install new venting lines.
3. Install sewer clean outs as needed. PVC rough plumbing is acceptable for replacement to underground line.
4. New rough plumbing to be installed into new rough UG plumbing at existing drinking fountain location.
5. Move two floor pipes to be used as floor drains for the two showers.
ii. Sewer line needs to be replaced from the fixtures to the trunk line, determine if main trunk line is compromised and need to be replaced before covering.
iii. Repair structure of walls, sheet rock, prep, and paint walls. Any existing walls that are untouched will need to be textured and painted the same as the replacement walls.
iv. Flooring to be tiled with a non-slip surface, floor prep (Leveling), Rubber baseboard install.
v. Install all toilets (3 total) and urinal (1 total), One toilet in each bathroom will be set up for ADA compliance. New Urinal needs to be wall mounted (ADA compliance) and have an automatic flush valve installed on it. Partition replacements can either be steel or plastic, whichever is cheaper.
vi. Install two showers with all hardware and set up for ADA compliance.
vii. Showers are to be located on the East Wall of both bathrooms; Women's bathroom will be ADA compliance with one toilet placed in the same area of the shower so that it will be ADA compliance also, one additional toilet that will be standard (Two toilets and one shower). Men's bathroom will have a standard shower. One (1 ea) toilet that will be ADA compliant and one (1 ea) urinal.
viii. Replace all existing automatic flush valves with new automatic hardware.
ix. Soap, Toilet paper, and paper towel dispensers will be supplied by owner.
x. Repair any damage done to existing walls or hard lid during the remodel/repair project.
4.4 Government Furnished Equipment\Services
1. Government will furnish a reasonable amount of electricity and water.
5.0 GENERAL REQUIREMENTS:
5.1 Permits: Where governing regulations and imposed codes and standards require notices, permits, licenses, inspections, tests, and similar items or actions to lawfully proceed with the required work, the Contractor shall obtain items and take those actions in accordance with the regulations of the governing authority. The costs of such permits, licenses, inspections, etc., are the obligation of the Contractor.
5.2 Existing Installations / Demolition: Contractor shall modify existing installations as needed to accommodate the new installation. Contractor shall coordinate modification of existing installations with Government. All disturbances of existing systems shall be thoroughly coordinated with the Government to prevent disturbances that might jeopardize on-going operations and research. Government reserves the right to retain any equipment / materials removed as part of the scope of work. Contractor shall coordinate any equipment / materials to be retained with Government prior to starting demolition operations. Contractor shall legally dispose all any materials removed that will not be retained.
5.3 Installation: It shall be the responsibility of the Contractor to complete work in accordance with Federal, State, and Local Code Standards. Additional procedures and materials may be required than is indicated herein. If any item specified herein conflicts with the applicable codes and recommendations, the Contractor shall bring it to the attention of the Contracting Officer Representative for immediate resolution.
5.4 Submittals: Provide manufacturer’s descriptive literature/shop drawings for all materials to the Location Monitor for review. The descriptive literature shall be annotated/ highlighted to show its conformance with contract requirements. Submittals are required for new materials and will be stamped and/or signed by the general contractor prior to submission to the Government. Contractor is responsible for any costs incurred for equipment ordered without prior approval.
5.5 Quality Control: The work performed under this contract shall be subject to continuous audit by the Location Monitor. Quality control is the exclusive responsibility of the Contractor.
5.6 Protection of Work and Property/Safety Requirements:
1. Contractor shall furnish a Site-Specific Safety Plan (SSSP) or Accident Prevention Plan (APP) ten days after contract award. SSSP / APP shall be approved by the Government before construction work commences.
1. The Contractor shall protect the work, the site, and all existing property and structures within the limits of the construction activities or that may be affected thereby until acceptance of the work. Any damage to property shall be repaired at the Contractor’s expense, to pre-damaged condition to the satisfaction of the Location Monitor.
1. Safety and health matters, as they relate to the work, are the exclusive responsibility of the Contractor. The Contractor shall furnish, erect, and maintain barricades, warning lights, signs, guards, or take other precautions as may be required by law or local authorities of the protection and security.
1. Contractor is responsible for verifying location of any underground utility and is responsible for any damaged caused to such utilities.
5.7 Temporary Facilities:
1. Temporary utilities (water and electricity) may be furnished to the Contractor by the Government, if so requested. The Contractor shall maintain and protect all such utilities during the course of construction and shall repair or replace any items damaged through its own negligence.
1. Should the Contractor require any power or utility shutdowns during construction, the Contractor shall obtain approval for such shutdown from the Location Monitor seven (7) working days prior to the need.
5.8 Materials and Equipment:
1. The material and equipment to be furnished under these contract documents shall be the standard products of manufacturers regularly engaged in the production of such materials and equipment and shall be the manufacturer’s latest standard design.
1. All materials and equipment to be incorporated in the work shall be handled and stored by the manufacturer, fabricator, supplies and Contractor before during and after shipment in a manner to prevent any injury, theft, or damage of any kind to the materials and equipment. All materials and equipment furnished by the Contractor shall be subject to inspection and approval by the CO/Location Monitor.
1. Government will not furnish any labor or equipment to unload or move materials or supplies.
5.9 Cleanup: The construction site shall be always kept clean and free of debris. Restore areas disturbed as nearly as possible to the original appearance and condition. Upon completion of the project, and prior to final inspection, the Contractor shall remove from the premises all unused material, trash, and debris resulting from the work to the satisfaction of the Location Monitor.
5.10 Warranty:
1. Submit data concerning the standard one-year warranty for workmanship, including the warranty periods (dates), and warranty contacts with names, addresses and telephone numbers.
1. Equipment/Product Warranties: Obtain and furnish to the Contracting Officer all written standard commercial warranties for equipment. The warranty period shall begin on the same date as project acceptance and shall continue for the full/product warranty period. The warranties shall be fully executed and delivered to the Contracting Officer prior to final acceptance of the facility.
5.11 Final Payment/Contract Closeout: The following documents are REQUIRED PRIOR TO FINAL PAYMENT (other documents may also be required):
1. General contractor’s minimum one (1) year warranty on work.
1. Manufacturers commercial warranty on equipment
1. Operation and Maintenance Data
1. Release of liens.
1. Contractor signed release of claims.
1. Final Invoice
6.0 PROJECT SCHEDULE: The Contract time for this project is 90 calendar days from Notice to Proceed.
7.0 Figures
· Area to be done marked in highlighted yellow.
Figure. BLDG 413 (Yellow Area) image2.png image1.png