This is an amendment to a solicitation for the reconstruction of 10 miles of Black Mountain Road. The work includes reconditioning nearly 10 miles of the road, placing 4 inches of aggregate on 4.9 miles, repairing soft spots with geo-fabric and aggregate, clearing and grubbing portions, cleaning a cattle guard, replacing a cattle guard, installing signs and a gate, and applying magnesium chloride to 0.4 miles. Aggregate will be supplied from the Copper Creek Pit and will need crushing. The amendment incorporates clauses on telecommunications and video surveillance, updates a clause date, includes questions and answers from site visits, and removes requirements for a dedicated quality control manager while maintaining quality control responsibilities. All offerors must acknowledge this amendment by signing and submitting with proposals. The period of performance is from August 2020 to November 2021.

View the file

Other files for this federal contract opportunity

Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

12853820R0006 x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

SHERIDAN WY 82801

2013 EASTSIDE 2ND STREET

BIGHORN NATIONAL FOREST

07/15/20200003

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

07/15/2020

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Black Mountain Road Reconstruction

Amendment 0003 is issued to Incorporate Far Clauses 52.204-24 and update FAR 52.204-25 with the AUG 2020 date

1. 52.204-24 Representation Regarding Certain Telecommunications and Video Surveillance

Services or Equipment. (Must answer the two questions in the clause)

2. 52.204-25 Prohibition on Contracting for Certain Telecommunications and Video

Surveillance Services or Equipment.(FROM AUG 2019 TO AUG 2002)

Continued ...

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

SUE A. LACROIX

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

2 2

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

12853820R0006/0003

It is strongly encouraged that all contactors review the clauses, understand their responsibility in complying with the clauses and proving the representations.

Amendment 0003 also incorporates;

3. The Questions & Answers from site visits held on August 8th and 13th, as well as any questions received via emails. (refer to separate attached document in FBO)

4. FP14-619 Cattlegurard Wing Layout

Exhibit-(refer to separate attached document in

FBO)

5. Copper Creek Pit Exhibit-(refer to separate attached document in FBO)

Amendment 0003 also removes;

6. Quality Control Manager (QCM)-Section

153.02(a)of FP-14SSBlackMountain on page 17 of the specifications - However, this does not alleviate the contractor's responsibility for quality control, it just means the contractor does not have to have an individual person onsite at all times whos job is specifically Quality

Control

7. Section 153.02(b) Testers- remains in the specifications

All Offerors SHALL acknowledge this amendment by signing and submitting with Proposal Response.

All other terms and conditions of the solicitation remain the same

Period of Performance: 08/24/2020 to 11/30/2021