J.2_Description_of_Pay_Items.pdf
PDF 113 KB Posted
- Attached to
- Medicine Bow/Routt National Forests and Thunder Basin National Grassland - Road Maintenance IDIQ
- Solicitation number
- 1282D719R0007
About this file
J.2 Description of Pay Items
View the file
Other files
| File | Type | Posted |
|---|---|---|
| J.7_Bid_Bond_SF24.pdf | ||
| J.3_2019_MBRTB_RD_MAINT_IDIQ_FSSS-14.pdf | ||
| J.5_Performance_Bond_SF25-16a.pdf | ||
| J.6_Payment_Bond_SF25A-16a.pdf | ||
| MBRTB_RD_IDIQ_SOW.pdf | ||
| J.8_Experience_Questionnaire.doc | DOC document | |
| J.1_MBRTB_Schedlue_B_Items.docx | DOCX document | |
| J.4_Vicinity-Map.pdf | ||
| SF1442_1282D719R0007.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DESCRIPTION OF PAY ITEMS (with base bid assumptions)
15101 Mobilization Mobilization will be negotiated and paid for on a per task order basis. The following locations shall be used for mobilization distance determinations: Steamboat Springs, CO; Laramie, WY; Cheyenne, WY;
Gillette, WY; Casper, WY; Rawlins, WY. The city closest to and most accessible to the project site will be used in determining unit prices. For base bid estimating purposes only, assume 2 pieces of equipment and 2 equipment operators and necessary incidental equipment and materials mobilized 70 miles from a location above to the project site.
Mobilization shall be paid one time per job. Mobilization will not be paid for the return trip to the base of operations, or for re-mobilization to the same project (e.g. equipment taken back to the base of operations for the weekend), unless agreed to in advance by the Contracting Officer.
Mobilization covers the movement of personnel, equipment, supplies, and incidentals to the project area.
Requirements and provisions shall follow FP-14 Section 151 and applicable Forest Service Supplemental Specifications (FSSS).
Bonding is a percentage unit price and shall be used for any Task Order between $30,000 and $150,000 at the discretion of the CO. This Pay Item is calculated by adding all mobilization Pay Item costs with all work Pay Item costs, then multiplying it by the percentage unit price.
15219 Establish Clearing Limits Consists of measurement of the required vegetation clearing distance from the edge of the roadway and marking the distance by hanging flags that delineate the area to be cleared. Clearing Limits may vary depending on road location factors such as ground slope, road width and presence of ditches. See drawing “Field Guide for 212 Staking”.
15702 Soil Erosion and Sediment Control Assume base bid is for linear feet of silt fence. Soil Erosion Control structures shall be installed according to FP-14 Section 157 and the drawings.
15802 Watering for Dust Control Includes supplying a water truck and driver/operator for dust control and/or use for dust palliative operations. Assume that a water source within 10 miles of each Task Order location will be available to Contractor for drafting water (no royalty fee). Base bid unit price is for 1 day of truck and operator.
Assume 2,000 gallon truck for base bid.
20302 Removal of Existing Culverts, Disposal Method A Includes the excavation, removal and legal disposal of culverts designated for removal. Assume 18” x 40’ CMP with 4’ of cover on inlet side for base bid. Dispose of culverts in accordance with FP-14 Section 203.05(a). Reinstallation of new culverts shall be paid for under Pay Item 60201.
20403 Roadway Excavation and Embankment, Compaction Placement Method 3 Includes excavation, placement, and compaction of common rippable earthen materials for roadway construction. Compact excavation and embankment material in accordance with FSSS Section 204.11(c).
Assume cut and fill quantities will balance for base bid. Assume a haul distance not to exceed 1 mile from the work location. Distances exceeding this will be negotiated separately.
20425C Drainage Excavation, Type Rolling Dip - Construct Includes construction of rolling dips as shown on the drawings. Assume 12’ wide road with side slope of 20% for base bid.
20425R Drainage Excavation, Type Rolling Dip - Reconstruct Includes reconstruction of existing rolling dips, cleaning of outlet ditch, removal of material from the bottom of the dip and re-shaping as necessary to drain water from the road as shown on the drawings.
Assume 12’ wide road with side slope of 20% for base bid.
21101 Roadway Obliteration, Method 1 Includes roadway obliteration in accordance with FSSS Section 211.01(a). Culvert removal shall be paid for under Pay Item 20302. Assume 12’ wide road with side slope of 40% for base bid.
21102 Roadway Obliteration, Method 2 Includes roadway obliteration in accordance with FSSS Section 211.01(b). Culvert removal shall be paid for under Pay Item 20302. Assume 12’ wide road with side slope of 40% for base bid.
21201 Linear Grading Includes reconstruction of existing roads: tree clearing, installation of new ditches, curve widening, minor re-alignments of the road, and re-finishing the road surface. Rolling dips shall be paid for separately.
Assume 12’ wide road with side slope of 20%, and an inside ditch for base bid. For base bid, assume 5-7 hours per mile for tree clearing with an excavator, 2 chain saws, and a pick-up truck (w/ operators).
23050 Roadside Brushing Includes cutting and removal of trees and brush within the clearing limits of the road 4 feet from the edge of the road. See Roadside Brushing Limits Drawing and FSSS Section 230. Assume base bid is for a mechanical masticator.
25102 Placed Riprap, Class 1 Includes furnishing, hauling, and placing Class 1 riprap in accordance with FP-14 Sections 251 and 705.02). For base bid, assume a haul distance not to exceed 70 miles one-way from the nearest acceptable commercial source to the project site. Distances exceeding this amount will be negotiated separately as needed.
30104 Aggregate Course, Grading E, Compaction Method A Includes hauling, placing, spreading, and compacting aggregate (FSSS Table 703-2 Grading E, or approved equal) from a commercial source. Compaction shall be in accordance with FSSS Section 301.05(a). For base bid, assume a haul distance not to exceed 70 miles one-way from the nearest acceptable commercial source to the project site. Distances exceeding this amount will be negotiated separately as needed.
30315 Roadway Reconditioning Includes re-working/maintaining existing roads and drainage structures in accordance with FSSS Section 303: reconditioning ditches, shoulders, roadbeds, parking areas, turnouts, approach road intersections, cattleguards, and aggregate surfaces.
31202 Dust Palliative Application, Type Magnesium Chloride, Method 1 Includes materials and application. Application rates shall be 0.33 gal/SY in accordance with FP-14 Section 312.04(a). Work required to prepare the roadbed shall be paid for under Pay Item 30315. Water trucks needed for dust palliative application shall be paid for under Pay Item 15802.
31402 Stockpiled Aggregate Includes furnishing material from a commercial source, and placing material in a stockpile for future use by the Government. For base bid, assume 40 mile haul one way, piling with a front-end loader, and aggregate Grading E (or approved equal, see FSSS Section 703). Distances exceeding this amount will be negotiated separately as needed.
60201 Culverts and Drains, Compaction Method 3 Includes the installation of new CMP culverts. Assume 18” x 40’ CMP with 4’ of cover on inlet side for base bid. Removal of old culvert(s) shall be covered under Pay Item 20302. Backfill compaction shall comply with FSSS Section 209.10(c).
65001 Furnish and Install Road Closure Device, Type 1, Size 16 feet Furnish and install road closure device, type 1, width 16 feet (see drawings). Install road closure devices in accordance with FSSS Section 650
65003 Install Road Closure Barrier, Type Earthen Mound Install earthen mound road closure barrier using on site materials (see drawings). Install road closure devices in accordance with FSSS Section 650
Traffic control for all Pay Items shall be considered incidental to other Pay Items.
The Contractor is required to call 811 to obtain a utility line locate before any ground disturbance on any task order. The Forest Service will try to provide as much information about any utilities known but it is the Contractor’s responsibility to locate all utility lines.
| DESCRIPTION OF PAY ITEMS (with base bid assumptions) |
| 15101 Mobilization |
| 15219 Establish Clearing Limits |
| 15702 Soil Erosion and Sediment Control |
| 15802 Watering for Dust Control |
| 20302 Removal of Existing Culverts, Disposal Method A |
| 20403 Roadway Excavation and Embankment, Compaction Placement Method 3 |
| 20425C Drainage Excavation, Type Rolling Dip - Construct |
| 20425R Drainage Excavation, Type Rolling Dip - Reconstruct |
| 21101 Roadway Obliteration, Method 1 |
| 21102 Roadway Obliteration, Method 2 |
| 21201 Linear Grading |
| 23050 Roadside Brushing |
| 25102 Placed Riprap, Class 1 |
| 30104 Aggregate Course, Grading E, Compaction Method A |
| 30315 Roadway Reconditioning |
| 31202 Dust Palliative Application, Type Magnesium Chloride, Method 1 |
| 31402 Stockpiled Aggregate |
| 60201 Culverts and Drains, Compaction Method 3 |
| 65001 Furnish and Install Road Closure Device, Type 1, Size 16 feet |
| 65003 Install Road Closure Barrier, Type Earthen Mound |