- Trail Clearing for the Dolores Ranger District
- Solicitation number
- 1282CS19Q0019
About this file
01_Addendum - Q&A
View the file
Other files
| File | Type | Posted |
|---|---|---|
| STD_911-01_Clearing_Limits.pdf | ||
| RFQ_1282CS19Q0019.pdf | ||
| 1.0.docx | DOCX document | |
| Wage_Determination.pdf | ||
| 1.3.docx | DOCX document | |
| STD_912_5_Rolling_Grade_Dip.pdf | ||
| 1.1_1.2.docx | DOCX document | |
| Overview_Map.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Addendum Questions & Answers Question:
Are there any recommendations or resources for camping opportunities, if a crew needs to camp for this project?
Answer:
Research can be done locally with the USDA Forest Service https://www.fs.usda.gov/sanjuan/ https://www.fs.usda.gov/recmain/sanjuan/recreation
Question(s):
Are there historical numbers of logs needing to be removed, as part of this project?
Answer(s):
For table 1.1 4-6 Down Trees per mile is what we expect based on past years records For table 1.2 we estimate 4-8 down trees per mile however we do not have accurate past year data for these trails.
We estimate that brushing should be no more than 25% of the work but do not have a volume estimate.
Question:
What is considered a Fire Plan or what kind of Fire Plan is acceptable?
Answer:
Vendors should submit a Fire Plan conducive to the Scope of Work to meet the requirement(s) outlined.