1282B123R0026_A0001_Final.pdf
PDF 170 KB Posted
- Attached to
- Mill Creek Summit Rock Crushing Federal contract opportunity
- Solicitation number
- 1282B123R0026
- Issued by
- Department of Agriculture Forest Service
About this file
This amendment to a federal solicitation extends the proposal due date to May 11, 2023 at 1:00pm ET for a rock crushing project located on the Boise National Forest in Idaho. The contractor shall furnish all labor, materials, equipment, tools, transportation, and supplies needed to perform rock crushing and develop a surface aggregate course from the Mill Creek Summit Pit. A site visit will be held on April 20, 2023 at 10:00am MT. The solicitation is issued by the USDA Forest Service and seeks these services to support aggregate production from the specified national forest lands.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment 1_Revised_Mill Creek_FSSS_20230519.pdf | ||
| 1282B123R0026_A0005.pdf | ||
| 1282B123R0026.pdf | ||
| Attachment 07_Revised_sheet2_MillCreek.pdf | ||
| A0003_QA_20230505.pdf | ||
| 1282B123R0026_A0003.pdf | ||
| A0003_Prebid Site Visit Sign In.pdf | ||
| 1282B123R0026_A0002.pdf | ||
| Attachment 3_Valley County WD.pdf | ||
| 1282B123R0026_Final.pdf | ||
| Attachment 5_PPQ.docx | DOCX document | |
| Attachment 6_SOI.doc.pdf | ||
| Attachment 2_Plans_Mill Creek Crushing_Combined.pdf | ||
| Attachment 1_Mill Creek_FSSS.pdf | ||
| Attachment 4_GEM County WD.pdf |
Show all 15
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
1282B123R0026 x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
82B1
WASHINGTON DC 20250-0001
1400 INDEPENDENCE AVE SW MS-1138
SPOC INTERMOUNTAIN
USDA FOREST SERVICE
IIJA03/30/20230001
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
03/27/2023
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
POC: Lucas Dahlman Email: lucas.dahlman@usda.gov
The purpose of this Amendment is to:
1. Extend Proposal Due Date from April 26th, 2023 to May 11th, 2023 at 100pm ET
2. Add Site Visit date of April 20th, 2023 at 1000 MT
3. Answer questions asked to date
4. See Summary of Changes for Full Details
Continued ...
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
JEFFREY R. BLACK
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 3
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
1282B123R0026/0001
Period of Performance: 06/15/2023 to 10/01/2023
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
SUMMARY OF CHANGES
The purpose of this Amendment is to:
1. Extend the proposal due date from April 26th, 2023 at 100pm ET to May 11th, 2023 at
1:00pm ET.
2. A Site Visit date has been established. Based on the current conditions, the Site Visit will be on April 26th, 2023, at 10:00 MT. All interested parties are to provide contact information of those attending to the Contracting Specialist, Lucas Dahlman at lucas.dahlman@usda.gov prior to this date. Location of Site visit is at the Mill Creek
Summit Pit which is noted in the project documents and maps.
3. Answer question(s) asked to date:
Question: Does this site require blasting to get the aggregates freed up to process or is it able to dig out of the bank freely?
Answer: The government has not performed a formal geotechnical investigation of the Mill Creek Pit. Excavation of the material used to generate and process the aggregate is unclassified. The Contractor shall utilize any reasonable means and/or methods to generate the material needed for processing.
Question: Is there any length restrictions or weight restrictions on this road.
Answer: The primary access route to the Mill Creek Summit Pit is via the 618
Road. All but the last mile of the 618 Road is under the jurisdiction of Gem
County. Gem County indicated there’s no length or weight restrictions on this road. However, the 618 Road contains various curves, cattleguards, etc. and the
Contractors should make their own determination of accessibility to the Mill
Creek Summit Pit via the 618 Road.
4. All other terms and conditions remain unchanged.
mailto:lucas.dahlman@usda.gov
| 1282B123R0026 |
| SUMMARY OF CHANGES |
File details come from the government source that posted it. Updated .