This is a Statement of Work for Building 13 window repair and replacement at the U.S. Department of Agriculture's Honeybee Breeding, Genetics & Physiology Research facility located at 1157 Ben Hur Road, Baton Rouge, Louisiana. The contractor shall furnish all labor, materials, equipment, and supplies to remove and replace existing windows in Building 13 (Barn) with energy-efficient windows matching the style and appearance of windows previously installed in Buildings 11 and 22. The scope includes replacement of eight 3-foot by 3-foot windows and one 2-foot by 2-foot window on the south elevation, plus two 5-foot by 3-foot windows and four 3-foot by 3-foot windows on the north elevation. All windows must be installed plumb, level, weather-tight, and in accordance with manufacturer recommendations. The project completion deadline is 90 days from the notice to proceed, with work hours scheduled Monday through Friday from 7:00 AM to 5:00 PM, excluding federal holidays.

The contractor is responsible for obtaining all permits, licenses, and inspections at their own expense; verifying all dimensions and site conditions prior to work commencement; submitting detailed material specifications and samples for approval; maintaining a clean work area with daily debris removal; providing a Site-Specific Safety Plan within 14 days of contract award; and coordinating a final site inspection with the Contracting Officer's Representative upon completion. All work must comply with local, state, and federal codes; ARS Facilities and Design Standards (P&P 242.1); and Federal Specifications and Standards. The contractor shall utilize bio-based products to the maximum extent possible and make best efforts to recycle construction debris. The contractor must provide a superintendent to oversee the project, submit daily work reports to the Contracting Officer's Representative, and repair or replace any property damaged during construction activities at their own cost. The proposal must include detailed cost breakdown in MS Excel format and work description in MS Word format.

View the file

Other files

File Type Posted
127EAX26Q0104 QA3.docx DOCX document
127EAX26Q0104 QA2.docx DOCX document
127EAX26Q0104 QA1.docx DOCX document
127EAX26Q0104.pdf PDF
Attachment 2 - Wage Determination.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work

B13 Window Repair Replacement Honeybee Breeding, Genetics & Physiology Research 1157 Ben Hur Rd Baton Rouge LA 70820

Prepared by:

Everett Wilson 30JUN26

STATEMENT OF WORK:

Contractor shall furnish all labor, materials, and supplies to perform the following work for U. S. Department of Agriculture, Agricultural Research Service, Honeybee Breeding, Genetics & Physiology Research, 1157 Ben Hur Rd, Baton Rouge LA 70820.

All work shall be completed in accordance with all local, state, and federal codes and regulations. All work should meet the manufacturer’s requirements for all equipment used in the project. All work shall also meet the requirements of the ARS Facilities and Design Standards (P&P 242.1). The P&P 242.1 document can be found at: http://www.afm.ars.usda.gov/ppweb/PDF/242-01M.pdf. All work shall be accomplished in a professional manner and in accordance with good workmanship and acceptable practice.

Contractor is responsible for inspecting the site and for determining the exact dimensions and requirements of the project with input from site personnel prior to submitting proposal and detailed cost breakdown.

Contractor shall obtain at own expense all permits, licenses, and inspections required by all local, state, and federal authorities. Contractor shall submit written specifications for all materials and supplies to be used and included in the bid.

Contractor’s working hours shall be scheduled to coincide with the normal working hours (8am-5pm) at the site. Should it be necessary to schedule working hours other than normal working hours, contractor shall arrange for access to the work area with the Contracting Officer’s Representative (COR) at the site at least three days prior to the need.

Contractor shall notify and schedule utility outages at least 24 hours in advance.

During work, contractor shall maintain a safe work area around the site of repair and clearly mark danger areas with cones and safety tape. All unused and demolition materials shall be removed from the site by the contractor and shall not be placed in the owner’s disposal areas.

The contractor will be responsible for replacing at their cost any property damaged at the site during the construction process.

PROJECT REQUIREMENTS:

1) Provide all labor, equipment, and materials required to:

A. B13 Window Repair

Contractor will remove and replace existing windows in Building 13 (Barn) with energy-efficient windows matching the style and appearance of those previously installed in Buildings 11 and 22. Work includes replacement of (8) 3-foot by 3-foot windows and (1) 2-foot by 2-foot window on the south elevation, as well as (2) 5-foot by 3-foot windows and (4) 3-foot by 3-foot windows on the north elevation. New windows will be installed plumb, level, weather-tight, and in accordance with manufacturer recommendations.

INSPECTIONS AND COMPLETION:

1. Upon completion of the project, contractor shall coordinate a site inspection of the work with the COR and/or other owner representatives.

2. Contractor shall remove all excess materials, debris, and equipment from the site.

Utilization of Bio-Based Products:

As required by the Farm Security and Rural Investment Act of 2002 and the Energy Policy Act of 2005 (7 U.S.C. 8102(c) (3)), the Offeror certifies, by signing this offer, that bio-based products (within categories of products listed by the United States Department of Agriculture in 7 CFR part 3201, subpart B) to be used or delivered in the performance of the contract, other than bio-based products that are not purchased by the Offeror as a direct result of this contract, will comply with the applicable specifications or other contractual requirements.

The contractor shall utilize products and material based from bio-based materials as applicable, (e.g. bio-based greases; bio-based hydraulic fluids, bio-based absorbents), to the maximum extent possible without jeopardizing the intended end use of detracting from the overall quality delivered to the end user. All supplies and materials shall be of a type and quality that conform to the applicable Federal Specifications and Standards. All supplies and materials to be used in the performance of work described herein are subject to the approval of the Contracting Officer Representative (COR). Products can be found at:

https://www.biopreferred.gov

Recycling.

Contractor shall make best effort to recycle any construction debris created during the contract.

Safety: The contractor will submit a Site Safety Specific Plan/Accident Prevention Plan in industry recognizable format to the Contracting Officer within 14 days of contract award. Contractor shall furnish a Site-Specific Safety Plan (SSSP) and the Government shall review the SSSP prior to the beginning any construction activities. SSSP shall be in typically accepted industry format.

Detailed Bid: Provide all materials, labor, and equipment to fully and successfully complete the Statement of Work described in this document. Proposal cost detail shall be in MS Excel and the work description shall be in MS Word. Failure to submit a properly documented and detailed proposal and bid will be considered grounds for no consideration.

CONTRACTOR RESPONSIBILITY:

The project has a base bid to be performed per the following specifications:

1. Contractor will verify all dimensions and quantities of materials and existing site conditions prior to beginning work.

2. Contractor shall keep work area clean on a daily basis and take measures to control debris while work is being performed.

3. Contractor is required to manage the project and consult with the Government prior to beginning all work phases. And, to work in a manner that minimizes the impact of the work on Government operations, research, and functions.

4. Contractor will provide daily reports of work performed to the COR.

5. Contractor shall remove and dispose of all construction related materials from all work areas on a daily basis and remove these waste materials from the site on a weekly basis.

6. All work must be performed in such a manner as to not adversely affect daily operations of the facility, its workers, and the onsite facility operations.

7. Contractor must have a superintendent responsible for overseeing this project.

8. Contactor will provide their restroom facility.

Material / Submittals:

The material for the entire work shall be as specified above. Submittals on all materials used on this project shall be submitted to the Research Leader and Engineering Project Manager as noted in this document as well as the yet to be assigned Contracting Officer for the Project. The documents detailing the material covered by the submittals will be provided electronically. Any physical sample required for site approval will be delivered to the site to the Research Leader for consideration and approval. All documentation regarding those samples will also be submitted electronically to the Lab Personnel Representative, COR and EPM.

Installation Procedure:

Contractor will verify all dimensions and site conditions prior to beginning work. Contractor will schedule the work between working hours as listed below. Contractor is required to provide labor, specified material, equipment, and other tools required to perform the job fully and completely. No Government equipment will be available for use by the contractor. The contractor shall be responsible for always protecting their work and ensuring the safety of his crew and ARS employees. Upon completion of the project, the contractor shall remove from the premises all accumulated materials and rubbish caused by the project. Premises shall be left in a clean, orderly, and acceptable condition.

Damage to Property:

Any damage to the Government buildings, utilities, etc. caused as the result of the contractor’s activities shall be repaired or replaced to the satisfaction of the Government.

Inspection and Acceptance:

A government representative shall inspect and approve the work performed on this project. The Contractor shall schedule inspection a minimum of 10 days in advance, in writing, to the Contracting Officer.

Project Schedule:

The completion of this project shall not exceed 90 days from date of notice to proceed with the repair of the roof of the main building and then the garage taking priority. A request for time extension must be submitted to the Contracting Specialist in writing. Each request must include specific and detailed reasons in support of the schedule alteration.

Work Hours:

Contractor work hours shall be Monday through Friday, seven (7) A.M. to five (5) P.M. with the exception of Government holidays or at the discretion of the site with written approval obtained a minimum of 24 hours in advance.