About this file
This is a Schedule of Items (SOI) for the Capulin Roads Reconstruction project on the Santa Fe National Forest in New Mexico. The SOI outlines the specific work items and quantities for reconstructing approximately 15 miles of National Forest System Roads damaged by the Hermits Peak/Calf Canyon Fire. The project is restricted to Region 3 Forest Engineering & Roads Maintenance (FERM) Blanket Purchase Agreement contractors, and the updated solicitation (127EAX26Q0077) has a quote deadline of September 15, 2026, at 12:00 noon Mountain Time.
The base work items include mobilization, clearing and grubbing, sediment trap removal and turnout construction (76 turnouts), untreated aggregate surface courses (5,800 tons) and subbase courses (8,884 tons), road reconditioning over 15 miles, stockpiled aggregates (400 tons), and cattleguard removal and installation with gates and markers (2 units). All work items are paid by contract quantity using unit prices to be provided by bidders. The cost estimates are derived from market research and previous contract awards. This is a USDA Forest Service project utilizing the existing FERM BPA contract vehicle, which streamlines the procurement process for pre-qualified road maintenance and forestry engineering contractors in the region.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Schedule of Items | |||||
| Company: | Project Title: | Capulin Roads Reconstruction | |||
| Date: | Representative: | ||||
| BASE Items | |||||
| Item No. | Description | Unit | Quantity | Unit Cost | Amount |
| 151(01) | Mobilization | LS | ALL | ||
| 201(01) | Clearing and Grubbing, Disposal Method (b) Scattering | LS | ALL | ||
| 204(01) | Clean and or Remove Sediment Traps, FSSS 204 Compaction Method (d) | EA | 22 | ||
| 204(02) | Construct Turnouts, FSSS 204 Compaction Method (d) | EA | 76 | ||
| 301(01) | Untreated Aggregate Courses, R3-G FS Surface Course (SPS 703), FSSS 301 Compaction C, includes watering, 14' wide min. | TON | 5800 | ||
| 301(02) | Untreated Aggregate Courses, Grading Designation Subbase A (FP-24), Compacted, 14' min, FSSS 204 Compaction Method (d), w/ initial Road Reconditioning, includes watering | TONS | 8884.0 | ||
| 303(01) | Road Reconditioning, FSSS 204 Compaction Method (d), includes watering | MILE | 15 | ||
| 314(01) | Stockpiled Aggregates, R3-G Surface Course, FSSS 301, within project boundary | TON | 400 | ||
| 619(01) | Cattleguard, Removal & Install 14' Government Furnished CG w/ wings and wing posts, and 14' Side Gates (include CONTRACTOR FURNISHED Type II Object Markers in estimate) | EA | 2 | ||
| BASE TOTAL | |||||
| Notes: Estimates derived from market research and previous contract awards. All work items to be paid by Contract Quantity. |