AMENDMENT 1 Questions and Answers.pdf

PDF 21 KB Posted

Attached to
Stewart Well Drilling Federal contract opportunity
Solicitation number
127EAX24R0023
Issued by
Department of Agriculture Forest Service

About this file

This document is an AMENDMENT 1 - Questions and Answers related to a federal contract opportunity for well drilling services. The key details are:

The contract opportunity is for the USDA Forest Service, Gila National Forest, Silver City Ranger District to furnish labor and equipment to construct a non-potable water well approximately 150 to 300 feet deep. The government estimate is based on an 8" steel pipe casing, however the contractor should determine the appropriate casing size based on the soil type upon drilling. Contractors are allowed to quote on a 300-foot well depth, which will provide the full cost if the well ends up being 300 feet.

View the file

Other files for this federal contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT 1 – Questions and Answers

1) As far as the size casing, is there a certain size? Is there also a certain material?

A: Our government estimate is based on the casing size of 8” steel pipe, however this should be determined by the contractor upon drilling and depending on soil type.

2) They mentioned the well would be anywhere from 150 to 300ft. Would it be acceptable to quote on 300ft?

A: Yes, a quote on 300ft is acceptable. That will give the government a full cost if the well ends up being 300ft.