127EAX24R0006-0001 Pipeline Recreation Site Improvements.pdf

PDF 92 KB Posted

Attached to
Pipeline Recreation Site Improvements
Solicitation number
127EAX24R0006
Issued by

About this file

This document contains an amendment to a solicitation for Pipeline Recreation Site Improvements. The U.S. Forest Service is soliciting offers for a single award, firm-fixed price contract between $500,000 to $1,000,000 to improve recreation sites along a pipeline in Gila County, Arizona. Through this amendment, the agency provides answers to submitted questions, makes corrections to the SF-1442 form, and extends the closing date to April 15, 2024. Specifically, it clarifies prevailing wage requirements, railing installation methods, the meaning of circles on the site plan, bond requirements, and schedules a pre-bid site visit for March 29th.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

127EAX24R0006

x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

7EAX

ALBUQUERQUE NM 87102-3498

333 BROADWAY BLVD SE

USDA-FS CSA SOUTHWEST 7

GAOA02/26/20240001

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

02/26/2024

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

The purpose of amendment 0001 to solicitation 127EAX24R0006, Pipeline OHV Staging Area is to provide answers to the questions received and make correction to the SF1442.

1. Block # 11 of the SF 1442 is changed to say, The Contractor shall begin performance with 10 calendar days and complete it within 60 calendar days after receiving Notice to

Proceed.

2. Block # 12a of the SF 1442 is changed to state the Contractor must furnish required

Performance and Payments Bonds 10 calendar days after award.

3. Block 13b of the SF 1442 is changed to read an offer guarantee is required.

4. The closing date has been extended to April 15, 2024, at 5:00 PM EST.

Continued ...

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

MICHAEL E. CARICO

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

2 2

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

127EAX24R0006/0001

QUESTIONS AND ANSWERS

1. The Documents for the Prevailing wage requirements, does not list welder, what would the welder fall under?

a. On page # 3 is says the following: Welders

- Receive rate prescribed for craft performing operation to which welding is incidental.

2. For the railing - How do we complete the corners? Would we put an Expansion Break point at each corner? Would we install a Safety

Turndown at each corner?

a. For the railing - install a Safety Turndown at each corner.

3. Do the two green circles on the attached represent the Driveway openings?

a. On the

USDA_FS_MonumentFireCenter_Title1_20240304_Rev01 document, the two green circles represent the

Driveway openings.

4. Is a Bid Bond required?

a. In accordance with FAR 52.228-15, which is included in full text in Section I of the solicitation, both 100% payment and performance bonds are required to be submitted. A 20% bid bond guarantee will be required.

5. There is no mention of a determined date and time of a job site walk, will there be one?

a. The site visit is scheduled for March 29th at 10:00 a.m. The location is as follows: Meet at

Eastern side of the Globe Ranger District, OHV

Pipeline, Globe, AZ 85501. Approximately at the southwest corner of the intersection of SR-70 and

SR-77.

b. Point of Contact: Kossigan Apedjinou, 480-973-0553, kossigan.apedjinou@usda.gov.