Solicitation 127EAX22R0003 Amendment 1.pdf

PDF 3 MB Posted

Attached to
Amendment 1 Edited Section M and Included additional Pictures
Solicitation number
127EAX22R0003
Issued by

About this file

This federal solicitation seeks proposals for construction services to replace three restroom facilities located across three sites within the Coronado National Forest in Arizona. The scope of work involves demolishing existing restroom buildings and site features; installing new vault toilet buildings ranging from two-hole to six-hole configurations; constructing concrete slabs, walks, and a stairway; relocating site utilities and amenities; and providing all necessary labor, materials, and equipment. Proposals are due by January 7, 2022. The award will be a fixed-price contract determined by lowest price technically acceptable criteria. The contractor must complete all work within 360 calendar days of the notice to proceed.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION, OFFER,

AND AWARD

2. TYPE OF SOLICITATION

6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.

PAGE OF PAGES

7. ISSUED BY CODE 8. ADDRESS OFFER TO

SOLICITATION

(Construction, Alteration, or Repair)

1. SOLICITATION NO. 3. DATE ISSUED

IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.

9.

INFORMATION

a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."

CALL:

FOR

SEALED BID (IFB)

NEGOTIATED (RFP)

1051785

USDA-FS CSA SOUTHWEST 7

333 BROADWAY BLVD SE

ALBUQUERQUE NM 87102-3498

7EAX

DANIEL FRANCO 520-388-8312

127EAX22R0003

x 12/07/2021

127EAX22R0003

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)

GAOA- Facilities-Replace three restrooms Coronado National Forest.

MAGNITUDE OF PROJECT: Between $250,000 and $500,000. This solicitation is a 100 percent Total Small Business Set-Aside.

NAICS: 238220 $16.5 Million is size standard for small business. PSC: J085

Davis-Bacon Wages apply. Payment and Performance Bonds will be required after award.

Offerors are required to have active vendor record for the DUNS number above in the

System for Award Management (SAM) https://www.sam.gov.

Site visits will be conducted on:

12/15/2021 at 11:00 AM on-site at Rose Canyon Lake immediately following Bear Canyon

Overlook and 12/16/2021 at 11:30 AM on-site at Camp Rucker.

Site visit is not mandatory, but it is highly encouraged to ensure contractors have an opportunity to view the actual site and ask questions. No questions will be answered on site. All questions shall be submitted in writing, via email, to the

Contracting Specialist Daniel Franco at: daniel.franco@usda.gov

Continued ...

11. The Contractor shall begin performance

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and is not required.is, b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

d. Offers providing less than

12b. CALENDAR DAYSYES NO

(If "YES", indicate within how many calendar days after award in Item 12b.)

10 360 calendar days and complete it within ________________ ________________ calendar days after receiving

01/07/2022

NSN 7540-01-155-3212

x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________

STANDARD FORM 1442 (Rev. 4-85)

Prescribed by GSA

FAR(48 CFR) 53.236-1(d)

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than item 14.)

CODE FACILITY CODE

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGEMENT OF AMENDMENTS

OFFER (Must be fully completed by offeror)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this document and return (Contractor is not required to sign this document.)

Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.

No further contractual document is necessary.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE

BY

2PAGE OF

USDA-FS CSA SOUTHWEST 7

333 BROADWAY BLVD SE

ALBUQUERQUE NM 87102-3498

7EAX

WARREN ABBOTT

28. NEGOTIATED AGREEMENT 29. AWARD

Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, copies to issuing office.)

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

STANDARD FORM 1442 (REV. 4-85) BACK

Continued...

ITEM NO.

(A)

SUPPLIES/SERVICES

(B)

QUANTITY

(C)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

NAME OF OFFEROR OR CONTRACTOR

3 3

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

127EAX22R0003

All questions must be submitted no later than

December 24, 2021. All Proposals will be submitted no later than January 07, 2021.

Delivery: 360 Days After Award

Delivery Location Code: 8196

SANTA CATALINA RANGER DISTRICT

5700 N SABINO CANYON ROAD

TUCSON AZ 85715 US

0001 Coronado -GAOA- Camp Rucker Bathrooms

Product/Service Code: J085

Product/Service Description: MAINT/REPAIR/REBUILD

OF EQUIPMENT- TOILETRIES

0002 Coronado -GAOA- Rose Canyon Lake Bathrooms

Product/Service Code: J085

Product/Service Description: MAINT/REPAIR/REBUILD

OF EQUIPMENT- TOILETRIES

0003 Coronado -GAOA- Bear Canyon Overlook Bathrooms

Product/Service Code: J085

Product/Service Description: MAINT/REPAIR/REBUILD

OF EQUIPMENT- TOILETRIES

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

1. Introduction.

USDA Forest Service has a requirement for the replacement of three bathrooms in the Coronado National Forest.

2. Type of Award. As a result of this solicitation, Government anticipates The Government Anticipates awarding a Firm Fixed‐Price Construction Contract using RFQ Lowest Price Technically Acceptable

(LPTA).

This is a 100% Small Business Set Aside to NAICS code 238910 Septic system contractors. PSC code J085 Maint/Repair/Rebuild of Equipment‐ Toiletries.

In order to be eligible for award of a Federal contract, potential vendors need to already be registered in the System for Award Management (SAM) at https://www.sam.gov . DUNS and business email are required to enroll in SAM.

3. Basis for Award. Technical Capability shall be submitted in the form of a statement or document that demonstrates the contractor’s capability to perform the work to meet or exceed the requirements of this solicitation. To meet the Technical Capability Requirements, offers shall address the following factors:

Factor a ‐ Tools, equipment, training, and general business practices should be developed in the statement or document to satisfy an evaluation panel that you the contractor has a level of technical capability that meets or exceeds the requirements to perform this work:

Factors b ‐Provide evidence of Registrar of Contractors listing, industry licensing and any appropriate and germane training which supports your technical capability for this type of work.

Factors c – Past Performance. Provide a minimum of three government contracts similar in nature and value.

Failure to provide adequate information for Technically Capability may result in the offer being removed from the competitive range.

Competitive offers will establish price reasonableness. Therefore, when contracting on a firm‐fixed‐price basis, comparison of the proposed prices will satisfy the requirement to perform a price analysis (cost analysis need not be performed). Contracting Officer intends to award without discussions, offerors shall provide their best prices up front. Pricing will serve as a final determining factor for award under

LPTA.

4. How to submit your offer. Submit RFQ pages 1 through 8 as your business proposal. In a separate document, also submit a technical proposal as outlined in the Basis for Award (above). Offers shall be submitted to the Contracting Officer on or before Janyary 07, 2021 1700 (local time). All Questions shall be submitted on or before December 24, 2021 by 5:00PM, (EST), to ensure all questions are answered by the Contracting Officer Representative Gerry Pedrego.

Offers shall be sent only to the Contracting Specialist Daniel Franco.

Offers shall be sent by email and should contain the Solicitation Number 127EAX22R0003 in the subject line for the email. Email: daniel.franco@usda.gov

5. Formal Site Visit: Site visits will be conducted on:

12/15/2021 at 11:00 AM on‐site at Rose Canyon Lake immediately following Bear Canyon Overlook and 12/16/2021 at 11:30 AM on‐site at Camp Rucker.

Site visit is not mandatory, but it is highly encouraged to ensure contractors have an opportunity to view the actual site and ask questions. No questions will be answered on site. All questions shall be submitted in writing, via email, to the Contracting Specialist Daniel Franco at: daniel.franco@usda.gov All questions must be submitted no later than December 24 2021. All Proposals will be submitted no later than January 07, 2021.

Technical Point‐Of‐Contact

Contracting Officer’s Representative COR:

Gerry Pedrego Civil Engineer Forest Service Coronado National Forest gerardo.pedrego@usda.gov

PART I – THE SCHEDULE

SECTION B – SUPPLIES OR SERVICES AND PRICES/COSTS

B1 – SCHEDULE OF BASE ITEMS

Pay Item Description

Method of Measurement

Est.

Quantity

Pay Unit

Unit Price Total

1 Mobilization LSQ 1 LS

2 Staking LSQ 1 LS

3 Demolition and Clearing LSQ 1 LS

4 CXT Restroom Building (2-hole) AQ 1 EA

5 Bear-proof trash bins AQ 2 EA

Total

6 Mobilization LSQ 1 LS

7 Staking LSQ 1 LS

8 Demolition (composting toilet building) LSQ 1 LS

Imported Fill (placed) - to fill area where composting toilet building basement removed AQ 300 TON

10 Riprap (dark, angular, 6-9", hand placed) AQ 75 TON

11 CXT Vault Restroom Buildings (3-hole) LSQ 2 LS

12 Relocate existing trash bins AQ 2 EA

13 Aggregate Base (2" under all concrete slabs) AQ 125 TON

14 Concrete Slabs, reinforced, 4" thick AQ 50 SY

Total

15 Mobilization LSQ 1 LS

16 Staking LSQ 1 LS

17 Demolition and Clearing LSQ 1 LS

18 Imported Fill (placed) AQ 75 TON

19 Finish Grading (incl. accessible walkway) LSQ 1 LS

20 CXT Restroom Building (2-hole) LSQ 1 LS

21 Aggregate Base (2" under all concrete slabs) AQ 30 TON

22 Concrete Slabs and Walks, reinforced, 4" thick AQ 30 SY

23 Concrete Stairway with metal handrail LSQ 1 LS

24 Relocate existing trash bins AQ 2 EA

25 Relocate hydrant and provide drain pit LSQ 1 LS

Total

Grand Total

Coronado National Forest Restroom Replacement Schedule of Items

Camp Rucker

Rose Canyon Lake

Bear Canyon Overlook

T:\Proj14\85001302\schedule of terms.xls

Pay Item Description

Method of Measurement

Est.

Quantity

Pay Unit

Unit Price Total

26 Demolition (camp store building) LSQ 1 LS

27 2 compacted AB picnic table pads (each 20'x20'x4") AQ 15 Ton

28 Concrete Picnic Tables AQ 2 EA

Designated Method of Measurement: AQ - actual quantities; LSQ - lump sum quantities

NOTE: Required work shown on the drawings and described in the specifications and not listed on this schedule of Items shall be considered incidental to other pay items.

Optional Bid Items - Rose Canyon Lake

T:\Proj14\85001302\schedule of terms.xls

SECTION C – STATEMENT OF WORK/DESCRIPTIONS

C.1 – GENERAL DESCRIPTION OF WORK

Furnish all material, equipment, transportation, labor and supervision necessary to complete all work, according to the Drawings and Specifications.

Scope of work includes:

1. Demolition of existing restroom buildings, slabs, concrete stairs, railings, and other items associated with buildings.

2. Installation and compaction of fill material, riprap, and aggregate, and site grading.

3. Installation of vault restroom buildings, including 2‐hole buildings at Bear Canyon Overlook and Camp Rucker and a

6‐hole building at Rose Canyon Lake. This work includes providing bedding material and establishment of FFE.

4. Construction of concrete walks and slabs, and a concrete stairway with railing.

5. Installation of trash bins and picnic tables.

6. Relocation of water hydrant and drain pit, and trash bins.

No changes to the specifications, terms, or conditions of this Request for Proposal (RFP) shall be made without the prior approval of the Contracting Officer in writing.

The Government intends to award a contract based on Lowest Price Technically Acceptable (LPTA). The offeror that demonstrates that they have technical skill required and lowest price. In order to remain in the competitive range, Offerors (Contractors) shall submit the Return Package with the requirements in Section M, Evaluation Factors.

Reference Section J for Exhibits:

Exhibit 1 – U.S. Department of Labor, Wage Determination Exhibit 2 – Bio‐preferred Requirements

Magnitude of project ‐ Between $250,000 and $500,000.

C.2 – LOCATION OF PROJECT

The proposed project is located at Camp Rucker, Rose Canyon Lake, and Bear Canyon Overlook within the Coronado

National Forest.

C.3 – SPECIFIC SCOPE OF WORK

3.1 – General

C3.1 See attachment “CNF Restroom Replacement Specifications”

Period of Performance All work and final cleanup should be completed within 360 calendar days from issuance of Notice‐To‐Proceed.

Formal Site Visit: Site visits will be conducted on:

12/15/2021 at 11:00 AM on‐site at Rose Canyon Lake immediately following Bear Canyon Overlook and 12/16/2021 at 11:30 AM on‐site at Camp Rucker.

Site visit is not mandatory, but it is highly encouraged to ensure contractors have an opportunity to view the actual site and ask questions. No questions will be answered on site. All questions shall be submitted in writing, via email, to the Contracting Specialist Daniel Franco at: daniel.franco@usda.gov All questions must be submitted no later than December 21, 2021. All Proposals will be submitted no later than December 29, 2021.

Technical Point‐Of‐Contact

Contracting Officer’s Representative COR:

Gerry Pedrego Civil Engineer Forest Service Coronado National Forest gerardo.pedrego@usda.gov

SECTION D – PACKAGING AND MARKING

D1—GENERAL INFORMATION:

See Section J for Exhibits that are incorporated as part of the statement of work:

Reference Section J for Exhibits:

Exhibit 1 – U.S. Department of Labor, Wage Determination Exhibit 2 – Bio‐preferred Requirements

SECTION E ‐ Inspection and Acceptance

52.246‐12 Inspection of Construction (Aug 1996)

(a) Definition. Work includes, but is not limited to, materials, workmanship, and manufacture and fabrication of components.

(b) The Contractor shall maintain an adequate inspection system and perform such inspections as will ensure that the work performed under the contract conforms to contract requirements. The Contractor shall maintain complete inspection records and make them available to the Government. All work shall be conducted under the general direction of the Contracting Officer and is subject to Government inspection and test at all places and at all reasonable times before acceptance to ensure strict compliance with the terms of the contract.

(c) Government inspections and tests are for the sole benefit of the Government and do not—

(1) Relieve the Contractor of responsibility for providing adequate quality control measures;

(2) Relieve the Contractor of responsibility for damage to or loss of the material before acceptance;

(3) Constitute or imply acceptance; or

(4) Affect the continuing rights of the Government after acceptance of the completed work under paragraph (i) of this section.

(d) The presence or absence of a Government inspector does not relieve the Contractor from any contract requirement, nor is the inspector authorized to change any term or condition of the specification without the Contracting Officer’s written authorization.

(e) The Contractor shall promptly furnish, at no increase in contract price, all facilities, labor, and material reasonably needed for performing such safe and convenient inspections and tests as may be required by the Contracting Officer. The Government may charge to the Contractor any additional cost of inspection or test when work is not ready at the time specified by the Contractor for inspection or test, or when prior rejection makes re‐inspection or retest necessary. The Government shall perform all inspections and tests in a manner that will not unnecessarily delay the work. Special, full size, and performance tests shall be performed as described in the contract.

(f) The Contractor shall, without charge, replace or correct work found by the Government not to conform to contract requirements, unless in the public interest the Government consents to accept the work with an appropriate adjustment in contract price. The Contractor shall promptly segregate and remove rejected material from the premises.

(g) If the Contractor does not promptly replace or correct rejected work, the Government may—

(1) By contract or otherwise, replace or correct the work and charge the cost to the Contractor; or

(2) Terminate for default the Contractor’s right to proceed.

(h) If, before acceptance of the entire work, the Government decides to examine already completed work by removing it or tearing it out, the Contractor, on request, shall promptly furnish all necessary facilities, labor, and material. If the work is found to be defective or nonconforming in any material respect due to the fault of the Contractor or its subcontractors, the Contractor shall defray the expenses of the examination and of satisfactory reconstruction. However, if the work is found to meet contract requirements, the Contracting Officer shall make an equitable adjustment for the additional services involved in the examination and reconstruction, including, if completion of the work was thereby delayed, an extension of time.

(i) Unless otherwise specified in the contract, the Government shall accept, as promptly as practicable after completion and inspection, all work required by the contract or that portion of the work the Contracting Officer determines can be accepted separately. Acceptance shall be final and conclusive except for latent defects, fraud, gross mistakes amounting to fraud, or the Government’s rights under any warranty or guarantee.

(End of clause)

52.246‐13 Inspection—Dismantling, Demolition, or Removal of Improvements (Aug 1996)

(a) Unless otherwise designated by the specifications, all workmanship performed under the contract is subject to Government inspection at all times and places where dismantling or demolition work is being performed. The Contractor shall furnish promptly, and at no increase in contract price, all reasonable facilities, labor, and materials necessary for safe and convenient inspection by the Government. The Government shall perform inspections in a manner that will not unduly delay the work.

(b) The Contractor is responsible for damage to property caused by defective workmanship. The Contractor shall promptly segregate and remove from the premises any unsatisfactory facilities, materials, and equipment used in contract performance, and promptly replaces them with satisfactory items. If the Contractor fails to proceed at once in a workmanlike manner with performance of the work or with the correction of defective workmanship, the Government may—

(1) By contract or otherwise, replace the facilities, materials, and equipment or correct the workmanship and charge the cost to the Contractor; and

(2) Terminate for default the Contractor’s right to proceed. The Contractor and any surety shall be liable, to the extent specified in the contract for any damage or cost of repair or replacement. (End of clause) 52.246‐21 Warranty of Construction (MAR 1994)

(a) In addition to any other warranties in this contract, the Contractor warrants, except as provided in paragraph (i) of this clause, that work performed under this contract conforms to the contract requirements and is free of any defect in equipment, material, or design furnished, or workmanship performed by the Contractor or any subcontractor or supplier at any tier.

(b) This warranty shall continue for a period of 1 year from the date of final acceptance of the work. If the Government takes possession of any part of the work before final acceptance, this warranty shall continue for a period of 1 year from the date the Government takes possession.

(c) The Contractor shall remedy at the Contractor’s expense any failure to conform, or any defect. In addition, the Contractor shall remedy at the Contractor’s expense any damage to Government‐owned or controlled real or personal property, when that damage is the result of—

(1) The Contractor’s failure to conform to contract requirements; or

(2) Any defect of equipment, material, workmanship, or design furnished.

(d) The Contractor shall restore any work damaged in fulfilling the terms and conditions of this clause. The Contractor’s warranty with respect to work repaired or replaced will run for 1 year from the date of repair or replacement.

(e) The Contracting Officer shall notify the Contractor, in writing, within a reasonable time after the discovery of any failure, defect, or damage.

(f) If the Contractor fails to remedy any failure, defect, or damage within a reasonable time after receipt of notice, the Government shall have the right to replace, repair, or otherwise remedy the failure, defect, or damage at the Contractor’s expense.

(g) With respect to all warranties, express or implied, from subcontractors, manufacturers, or suppliers for work performed and materials furnished under this contract, the Contractor shall—

(1) Obtain all warranties that would be given in normal commercial practice;

(2) Require all warranties to be executed, in writing, for the benefit of the Government, if directed by the Contracting Officer;

and

(3) Enforce all warranties for the benefit of the Government, if directed by the Contracting Officer.

(h) In the event the Contractor’s warranty under paragraph (b) of this clause has expired, the Government may bring suit at its expense to enforce a subcontractor’s, manufacturers, or supplier’s warranty.

(i) Unless a defect is caused by the negligence of the Contractor or subcontractor or supplier at any tier, the Contractor shall not be liable for the repair of any defects of material or design furnished by the Government nor for the repair of any damage that results from any defect in Government‐furnished material or design.

(j) This warranty shall not limit the Government’s rights under the Inspection and Acceptance clause of this contract with respect to latent defects, gross mistakes, or fraud.

(End of clause)

SECTION F – DELIVERIES OR PERFORMANCE

FAR 52.211‐10 Commencement, Prosecution, and Completion of Work (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives notice‐to‐proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 360 calendar days from issuance of notice‐to‐proceed. The time stated for completion shall include final cleanup of the premises.

AGAR 452.236‐75 MAXIMUM WORK WEEK – CONSTRUCTION SCHEDULE (NOV 1996)

Within 10 calendar days after receipt of a written request from the Contracting Officer, the Contractor must submit the following information in writing for approval:

(a) A schedule as required by FAR 52.236‐15, Schedules for Construction Contracts, and

The maximum workweek shall be: Perform construction during normal waking hours from 6:00am to 6:00pm up to seven days per week. Any change in the work schedule shall be approved in writing by the Contracting Officer prior to commencement. (Note: Building is unoccupied most of the time, and when occupied it is with USFS or USFS‐sponsored individuals—under our control).

SECTION G – CONTRACT ADMINISTRATIVE DATA

Government Furnished Items: N/A

SECTION H – Special Contract Requirements

N/A

PART II ‐ SECTION I ‐ CONTRACT CLAUSES AND PROVISIONS

52.252-2 Clauses Incorporated by Reference (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

Federal Acquisition Regulation (FAR) Clauses: https://www.acquisition.gov/browse/index/far (FAR clauses begin with 52) Department of Agriculture Acquisition Regulation (AGAR) Clauses:

https://www.acquisition.gov/agar (AGAR clauses begin with 452) Deviations to clauses may be viewed at:

https://www.dm.usda.gov/procurement/policy/FARClassDeviations.htm

52.202-1 Definitions (JUN 2020) 52.203-3 Gratuities (APR 1984) 52.203-5 Covenant against Contingent Fees (MAY 2014) 52.203-6 Restrictions on Subcontractor Sales to the Government (JUN 2020) 52.203-7 Anti-Kickback Procedures (JUN 2020) 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity (MAY

2014) 52.203-10 Price or Fee Adjustment for Illegal or Improper Activity (MAY 2014) 52.203-12 Limitation on Payments to Influence Certain Federal Transactions (JUN 2020) 52.203-17 Contractor Employee Whistleblower Rights & Requirements to Inform Employees of

Whistleblower Rights (JUN 2020) 52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements

(JAN 2017)

52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper (MAY 2011) 52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards (JUN 2020) 52.204-13 System for Award Management Maintenance (OCT 2018) 52.204-14 Service Contract Reporting Requirements (OCT 2016) 52.204-18 Commercial and Government Entity Code Maintenance (AUG 2020) 52.204-19 Incorporation by Reference of Representations and Certifications (DEC 2014) 52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab and Other Covered Entities (JUL 2018) 52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance

Services or Equipment (AUG 2020) 52.209-6 Protecting the Government's Interest when Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (JUN 2020) 52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (NOV 2015) 52.215-2 Audit and Records -- Negotiation (JUN 2020) 52.215-8 Order of Precedence—Uniform Contract Format (OCT 1997) 52.219-6 Notice of Total Small Business Set-Aside (NOV 2020) 52.219-8 Utilization of Small Business Concerns (OCT 2018) 52.219-14 Limitations on Subcontracting (SEP 2021)

[Contracting Officer check as appropriate.] ☐ By the end of the base term of the contract and then by the end of each subsequent option period; or ☐ By the end of the performance period for each order issued under the contract.

52.219-27 Notice of Service-Disabled Veteran-Owned Small Business Set-Aside (SEP 2021) 52.219-28 Post Award Small Business Program Rerepresentation (SEP 2021) 52.219-29 Notice of Set-Aside for, or Sole-Source Award to, Economically Disadvantaged Women-

Owned Small Business Concerns (SEP 2021) 52.219-30 Notice of Set-Aside for, or Sole-Source Award to, Women-Owned Small Business

Concerns Eligible Under the Women-Owned Small Business Program (SEP 2021)

52.222-3 Convict Labor (JUN 2003) 52.222-4 Contract Work Hours and Safety Standards -- Overtime Compensation (MAY 2018) 52.222-6 Construction Wage Rate Requirement (AUG 2018) 52.222-7 Withholding of Funds (MAY 2014) 52.222-8 Payrolls and Basic Records (JUL 2021) 52.222-9 Apprentices and Trainees (JUL 2005) 52.222-10 Compliance with Copeland Act Requirements (FEB 1988)

52.222-11 Subcontracts (Labor Standards) (MAY 2014) 52.222-12 Contract Termination - Debarment (MAY 2014) 52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations (MAY

2014) 52.222-14 Disputes Concerning Labor Standards (FEB 1988) 52.222-15 Certification of Eligibility (MAY 2014) 52.222-21 Prohibition of Segregated Facilities (APR 2015) 52.222-26 Equal Opportunity (APR 2016) 52.222-27 Affirmative Action Compliance Requirements for Construction (APR 2015) 52.222-35 Equal Opportunity for Veterans (JUN 2020) 52.222-36 Equal Opportunity for Workers with Disabilities (JUN 2020) 52.222-37 Employment Reports on Veterans (JUN 2020) 52.222-40 Notification of Employee Rights Under National Labor Relations Act (DEC 2010) 52.222-50 Combating Trafficking in Persons (OCT 2020) 52.222-54 Employment Eligibility Verification (OCT 2015) 52.222-55 Minimum Wages under Executive Order 13658 (NOV 2020) 52.222-62 Paid Sick Leave under Executive Order 13706 (JAN 2017) 52.223-2 Affirmative Procurement of Biobased Products under Service and Construction Contracts

(SEP 2013)

52.223-3 Hazardous Material Identification and Material Safety Data Alt 1 (FEB 2021) 52.223-5 Pollution Prevention and Right-to-Know Information (MAY 2011) 52.223-6 Drug-Free Workplace (MAY 2001) 52.223-17 Affirmative Procurement of EPA-designated Items in Service and Construction Contracts

(AUG 2018)

52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving (JUN 2020) 52.225-13 Restrictions on Certain Foreign Purchases (FEB 2021) 52.226-1 Utilization of Indian Organizations and Indian-Owned Economic Enterprises (JUN 2000) 52.227-1 Authorization and Consent (JUN 2020) 52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement (JUN 2020) 52.227-4 Patent Indemnity -- Construction Contracts (DEC 2007) 52.228-2 Additional Bond Security (OCT 1997) 52.228-5 Insurance – Work on a Government Installation (JAN 1997) 52.228-12 Prospective Subcontractor Requests for Bonds (MAY 2014) 52.228-14 Irrevocable Letter of Credit (NOV 2014) 52.229-3 Federal, State, and Local Taxes (FEB 2013) 52.229-4 Federal, State, and Local Taxes (State and Local Adjustments) (FEB 2013) 52.232-5 Payments under Fixed-Price Construction Contracts (MAY 2014) 52.232-17 Interest (MAY 2014) 52.232-23 Assignment of Claims (MAY 2014) 52.232-27 Prompt Payment for Construction Contracts (JAN 2017) 52.232-33 Payment by Electronic Funds Transfer – System for Award Management (OCT 2018) 52.232-39 Unenforceability of Unauthorized Obligations (JUN 2013) 52.233-1 Disputes (MAY 2014) Alt 1 (DEC 1991) 52.233-3 Protest after Award (AUG 1996) 52.233-4 Applicable Law for Breach of Contract Claim (OCT 2004) 52.236-2 Differing Site Conditions (APR 1984) 52.236-3 Site Investigation and Conditions Affecting the Work (APR 1984) 52.236-5 Material and Workmanship (APR 1984) 52.236-6 Superintendence by the Contractor (APR 1984) 52.236-7 Permits and Responsibilities (NOV 1991)

52.236-8 Other Contracts (APR 1984) 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements

(APR 1984)

52.236-10 Operations and Storage Areas (APR 1984) 52.236-11 Use and Possession Prior to Completion (APR 1984) 52.236-12 Cleaning Up (APR 1984) 52.236-13 Accident Prevention (NOV 1991)

Alternate I (NOV 1991) 52.236-14 Availability and Use of Utility Services (APR 1984) 52.236-15 Schedules for Construction Contracts (APR 1984) 52.236-16 Quantity Surveys (APR 1984)

Alternate 1 (APR 1984) 52.236-17 Layout of Work (APR 1984) 52.236-21 Specifications and Drawings for Construction (FEB 1997)

Alternate I (APR 1984) Alternate II (APR 1984)

52.242-13 Bankruptcy (JUL 1995) 52.243-4 Changes (JUN 2007) 52.244-2 Subcontracts (JUN 2020) 52.244-6 Subcontracts for Commercial Items (JUL 2021) (DEVIATION APR 2020) 52.245-1 Government Property (SEP 2021) - Alt 1 (APR 2012) 52.245-9 Use and Charges (APR 2012) 52.248-3 Value Engineering – Construction (OCT 2020) 52.249-2 Termination for Convenience of the Government (Fixed-Price) (APR 2012) Alternate I

(SEP 1996)

52.249-3 Termination for Convenience of the Government (Dismantling, Demolition, or Removal of Improvements) (APR 2012) 52.249-10 Default (Fixed-Price Construction) (APR 1984)

Alternate I (APR 1984) 52.253-1 Computer Generated Forms (JAN 1991) 452.232-70 Reimbursement for Bond Premiums – Fixed-Price Construction Contracts (NOV 1996) 452.236-71 Prohibition against the Use of Lead-Paint (NOV 1996) 452.236-72 Use of Premises (NOV 1996) 452.236-74 Control of Erosion, Sedimentation and Pollution (NOV 1996) 452.236-76 Samples and Certificates (FEB 1988) 452.236-77 Emergency Response (NOV 1996) 52.219-13 Notice of Set Aside of Orders (MAR 2020)

(a) The Contracting Officer may set aside orders for the small business concerns identified in 19.000(a)(3).

(b) The Contracting Officer will give notice of the order or orders, if any, to be set aside for small business concerns identified in 19.000(a)(3) and the applicable small business program. This notice, and its restrictions, will apply only to the specific orders that have been set aside for any of the small business concerns identified in 19.000(a)(3).

52.223-9 Estimate of Percentage of Recovered Material Content for EPA-Designated Items (May

2008)

(a) Definitions. As used in this clause—

“Postconsumer material” means a material or finished product that has served its intended use and has been discarded for disposal or recovery, having completed its life as a consumer item. Postconsumer material is a part of the broader category of “recovered material.”

“Recovered material” means waste materials and by-products recovered or diverted from solid waste, but the term does not include those materials and by-products generated from, and commonly reused within, an original manufacturing process.

(b) The Contractor, on completion of this contract, shall—

(1) Estimate the percentage of the total recovered material content for EPA-designated item(s) delivered and/or used in contract performance, including, if applicable, the percentage of post-consumer material content; and

(2) Submit this estimate to _____________________ [Contracting Officer complete in accordance with agency procedures].

52.223-99 Ensuring Adequate COVID-19 Safety Protocols for Federal Contractors (OCT 2021)

(DEVIATION)

(a) Definition. As used in this clause - United States or its outlying areas means—

(1) The fifty States;

(2) The District of Columbia;

(3) The commonwealths of Puerto Rico and the Northern Mariana Islands;

(4) The territories of American Samoa, Guam, and the United States Virgin Islands; and

(5) The minor outlying islands of Baker Island, Howland Island, Jarvis Island, Johnston Atoll, Kingman Reef, Midway Islands, Navassa Island, Palmyra Atoll, and Wake Atoll.

(b) Authority. This clause implements Executive Order 14042, Ensuring Adequate COVID Safety Protocols for Federal Contractors, dated September 9, 2021 (published in the Federal Register on September 14, 2021, 86 FR 50985).

(c) Compliance. The Contractor shall comply with all guidance, including guidance conveyed through Frequently Asked Questions, as amended during the performance of this contract, for contractor or subcontractor workplace locations published by the Safer Federal Workforce Task Force (Task Force Guidance) at https:/www.saferfederalworkforce.gov/contractors/.

(d) Subcontracts. The Contractor shall include the substance of this clause, including this paragraph (d), in subcontracts at any tier that exceed the simplified acquisition threshold, as defined in Federal Acquisition Regulation 2.101 on the date of subcontract award, and are for services, including construction, performed in whole or in part within the United States or its outlying areas.

52.228-1 Bid Guarantee (SEP 1996)

(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.

(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds –

(1) To unsuccessful bidders as soon as practicable after the opening of bids, and (2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.

(c) The amount of the bid guarantee shall be ______ percent of the bid price or $________, whichever is less.

(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.

(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.

52.228-11 Individual Surety - Pledge of Assets (FEB 2021) (DEVIATION APR 2020)

(a) The Contractor shall obtain from each person acting as an individual surety on a performance bond or a payment bond -

(1)A pledge of assets that meets the eligibility, valuation, and security requirements described in the Federal Acquisition Regulation (FAR) 28.203-1; and

(2) Standard Form 28, Affidavit of Individual Surety, [except that the words “being duly sworn, depose and say” on the Standard Form 28 are replaced with the word “affirm” and the Standard Form 28 is not required to be sworn and notarized in block 12].

(b)The Contracting Officer may release a portion of the security interest on the individual surety's assets based upon substantial performance of the Contractor's obligations under its performance bond. The security interest in support of a performance bond shall be maintained—

(1) Contracts for the construction, alteration, or repair of any public building or public work of the Federal Government exceeding $150,000 (40 U.S.C. 3131). Until completion of any warranty period, or for 1 year following final payment, whichever is later.

(2) Contracts subject to alternative payment protection (see FAR 28.102-1(b)(1)). For the full contract performance period plus 1 year.

(3) Other contracts not subject to the requirements of paragraph (b)(1) of this clause. Until completion of any warranty period, or for 90 days following final payment, whichever is later.

(c)A surety's assets pledged in support of a payment bond may be released to a subcontractor or supplier upon Government receipt of a Federal district court judgment, or a sworn statement by the subcontractor or supplier that the claim is correct along with a notarized authorization of the release by the surety stating that it approves of such release. The security interest on the individual surety's assets in support of a payment bond shall be maintained—

(1) Contracts for the construction, alteration, or repair of any public building or public work of the Federal Government exceeding $150,000 which require performance and payment bonds (40 U.S.C. 3131). For 1 year following final payment, or until resolution of all pending claims filed against the payment bond during the 1-year period following final payment, whichever is later.

(2) Contracts subject to alternative payment protection (see FAR 28.102-1(b)(1)). For the full contract performance period plus 1 year.

(3) Other contracts not subject to the requirements of paragraph (c)(1) of this clause. For 90 days following final payment.

(d)The Contracting Officer may allow the Contractor to substitute an individual surety, for a performance or payment bond, after contract award. The Contractor shall comply with the requirements of paragraph (a) of this clause within the timeframe established by the Contracting Officer.

52.228-15 Performance and Payment Bonds -- Construction (JUN 2020) (DEVIATION APR 2020)

(a)Definitions. As used in this clause -- “Original contract price” means the award price of the contract; or, for requirements contracts, the price payable for the estimated total quantity; or, for indefinite-quantity contracts, the price payable for the specified minimum quantity. Original contract price does not include the price of any options, except those options exercised at the time of contract award.

(b) Amount of required bonds. Unless the resulting contract price is valued at or below the threshold specified in Federal Acquisition Regulation 28.102-1(a) on the date of award of this contract, the successful offeror shall furnish performance and payment bonds to the Contracting Officer as follows:

(1) Performance Bonds (Standard Form 25, EXCEPT THAT A SEAL IS NOT REQUIRED).

The penal amount of performance bonds at the time of contract award shall be 100 percent of the original contract price.

(2) Payment Bonds (Standard Form 25-A, EXCEPT THAT A SEAL IS NOT REQUIRED).

The penal amount of payment bonds at the time of contract award shall be 100 percent of the original contract price.

(3) Additional bond protection.

(i) The Government may require additional performance and payment bond protection if the contract price is increased. The increase in protection generally will equal 100 percent of the increase in contract price.

(ii) The Government may secure the additional protection by directing the Contractor to increase the penal amount of the existing bond or to obtain an additional bond.

(c) Furnishing executed bonds. The Contractor shall furnish all executed bonds, including any necessary reinsurance agreements, to the Contracting Officer, within the time period specified in the Bid Guarantee provision of the solicitation, or otherwise specified by the Contracting Officer, but in any event, before starting work.

(d) Surety or other security for bonds. The bonds shall be in the form of firm commitment, supported by corporate sureties whose names appear on the list contained in Treasury Department Circular 570, individual sureties, or by other acceptable security such as postal money order, certified check, cashier’s check, irrevocable letter of credit, or, in accordance with Treasury Department regulations, certain bonds or notes of the United States. Treasury Circular 570 is published in the Federal Register or may be obtained from the:

U.S. Department of Treasury Financial Management Service Surety Bond Branch 3700 East West Highway, Room 6F01 Hyattsville, MD 20782 Or via the internet at http://www.fms.treas.gov/c570/.

(e) Notice of subcontractor waiver of protection (40 U.S.C. 3133(c)). Any waiver of the right to sue on the payment bond is void unless it is in writing, signed by the person whose right is waived, and executed after such person has first furnished labor or material for use in the performance of the contract.

52.228-17 Individual Surety – Pledge of Assets (Bid Guarantee) (FEB 2021)

(a)Offerors shall obtain from each person acting as an individual surety on a bid guarantee—

(1) A pledge of assets that meets the eligibility, valuation, and security requirements described in the Federal Acquisition Regulation (FAR) 28.203-1; and

(2) Standard Form 28, Affidavit of Individual Surety.

(b)The Offeror shall include with its offer the information required at paragraph (a) of this provision within the timeframe specified in the provision at FAR 52.228-1, Bid Guarantee, or as otherwise established by the Contracting Officer.

(c)The Contracting Officer may release the security interest on the individual surety's assets in support of a bid guarantee based upon evidence that the offer supported by the individual surety will not result in contract award.

52.232-40 Providing Accelerated Payments to Small Business Subcontractors (DEC 2013)

(DEVIATION APR 2020)

(a)[(1) In accordance with 31 U.S.C. 3903 and 10 U.S.C. 2307, upon receipt of accelerated payments from the Government, the Contractor shall make accelerated payments to its small business subcontractors under this contract [in accordance with the accelerated payment date established], to the maximum extent practicable and prior to when such payment is otherwise required under the applicable contract or subcontract, [with a goal of 15 days] after receipt of a proper invoice and all other required documentation from the small business subcontractor [if a specific payment date is not established by contract.

(2) The Contractor agrees to make such payments to its small business subcontractors without any further consideration from or fees charged to the subcontractor].

(b) The acceleration of payments under this clause does not provide any new rights under the Prompt Payment Act.

(c) Include the substance of this clause, including this paragraph (c), in all subcontracts with small business concerns, including subcontracts with small business concerns for the acquisition of commercial items.

52.237-4 Payment by Government to Contractor (APR 1984)

(a) In ______ [insert “full” if Alternate I is used; otherwise insert “partial”] consideration of the performance of the work called for in the Schedule, the Government will pay to the Contractor ______________ [fill in amount].

(b)The Government shall make progress payments monthly as the work proceeds, or at more frequent intervals as determined by the Contracting Officer, on estimates approved by the Contracting Officer. Except as provided in paragraph (c) of this clause, in making progress payments the Contracting Officer shall retain 10 percent of the estimated payment until final completion and acceptance of the contract work. However, if the Contracting Officer finds that satisfactory progress was achieved during any period for which a progress payment is to be made, the Contracting Officer may authorize such payment in full, without retaining a percentage. Also, on completion and acceptance of each unit or division for which the price is stated separately, the Contracting Officer may authorize full payment for that unit or division without retaining a percentage.

(c)When the work is substantially completed, the Contracting Officer shall retain an amount considered adequate for the protection of the Government and, at the Contracting Officer’s discretion, may release all or a portion of any excess amount.

(d)In further consideration of performance, the Contractor shall receive title to all property to be dismantled or demolished that is not specifically designated as being retained by the Government. The title shall vest in the Contractor immediately upon the Government’s issuing the notice of award, or if a performance bond is to be furnished after award, upon the Government’s issuance of a notice to proceed with the work. The Government shall not be responsible for the condition of, or any loss or damage to, the property. If the Contractor does not wish to remove from the site any of the property acquired, the Contracting Officer may, upon written request, grant the Contractor permission to leave the property on the premises. As a condition to the granting of this permission, the Contractor agrees to waive any right, title, claim, or interest in and to the property.

(e)Upon completion and acceptance of all work and receipt of a properly executed voucher, the Government shall make final payment of the amount due the Contractor under this contract. If requested, the Contractor shall release all claims against the Government arising under this contract, other than any claims the Contractor specifically excepts, in stated amounts, from operation of this release.

Alternate I (Apr1984). If the contracting officer determines that the Government shall retain all material resulting from the dismantling or demolition work, delete paragraph (d) from the basic clause and renumber the remaining paragraphs.

52.237-5 Payment by Contractor to Government (APR 1984)

(a)The Contractor shall receive title to all property to be dismantled, demolished, or removed under this contract and not specifically designated in the Schedule as being retained by the Government. The title shall vest in the Contractor immediately upon the Government’s issuing the notice of award, or if a performance bond is to be furnished, upon the Government’s issuing a notice to proceed with the work.

The Government shall not be responsible for the condition of, or any loss or damage to, the property.

(b)The Contractor shall promptly remove from the site all property acquired by the Contractor. The Government shall not permit storage of property on the site beyond the completion date. If the Contractor does not wish to remove from the site any of the property acquired, the Contracting Officer may, upon written request, grant the Contractor permission to leave the property on the premises. As a condition of the granting of the permission, the Contractor agrees to waive any right, title, claim, or interest in and to the property.

(c)The Contractor shall perform the work called for under this contract and within ________ days of receipt of notice of award, unless otherwise provided in the Schedule and before proceeding with the work, shall pay _________ [fill in amount]. Checks shall be made payable to the office designated in the contract and shall be forwarded to the Contracting Officer.

52.252-6 Authorized Deviations in Clauses (NOV 2020)

(a) The use in this solicitation or…

This is the start of the file's text. The full file is on GovTribe.