SPECIFICATIONS

FOR

Telegraph Fire BAER Gates

00000-1

SPECIFICATION INDEX

FOR

Telegraph Fire BAER Gates

DIVISION 1 - GENERAL REQUIREMENTS

01101 – Abbreviations 4 pages 01102 – Definitions 4 pages 01103 – Measurement and Payment 2 pages 01300 – Submittals 2 pages

01410 – Quality Control and Quantity Measurement 4 pages 01601 – Mobilization 2 pages

01740 – Cleaning 1 pages

DIVISION 2 - SITE WORK

02071 – Removal of Structures and Obstructions 2 pages 02110 – Clearing and Grubbing 2 pages

02224 – Excavation, Embankment, and Backfill 3 pages 02840 – Road Closure Devices 2 pages 02841 – Signs 2 pages

DIVISION 3 - CONCRETE

03301 – Cast in Place Concrete 6 pages

03345 – Concrete Finishing 2 pages

DIVISION 5 - METALS

05100 – Structural Metal 2 pages

05500 –Metal Fabrication 2 pages

DIVISION 9 - FINISHING

09900 – Painting 2 pages

END OF SPECIFICATION INDEX

01101 - 1

DIVISION 1 GENERAL

ABBREVIATIONS - 01101

Organizations & Standards

Whenever in these specifications, or in other contract documents, the following terms, or pronouns in place of them, are used, the intent and meaning shall be interpreted as follows. Reference to a specific standard of specification shall mean the latest edition or amendment in effect on date of invitation to bid.

AASHTO--American Association of State Highway and Transportation Officials

ACI--American Concrete Institute

AISC--American Institute of Steel Construction

AISI--American Iron and Steel Institute

ANSI--American National Standards Institute

API--American Petroleum Institute

ASME--American Society of Mechanical Engineers

ASTM--American Society for Testing and Material

ATCC--American Type Culture Collection

AWS--American Welding Society

AWWA--American Water Works Association

CFR--Code of Federal Regulations

CRSI--Concrete Reinforcing Steel Institute

CS--Commercial Standard issued by U.S. Department of Commerce

DEMA--Diesel Engine Manufacturers Association

FAR--Federal Acquisition Regulation

FED SPEC. or FS-- Federal Specifications

FSS--Federal Specifications and Standards

01101 - 2

GSA--General Services Administration

MIL--Military Specifications

MSHA--Mine Safety and Health Administration

MUTCD--Manual on Uniform Traffic Control Devices

NBFU--National Board of Fire Underwriters

NBS--National Bureau of Standards

NEMA--National Electrical Manufacturers Association

NESC--National Electrical Safety Code

NFPA--(Fire)--National Fire Protection Association

NFPA--(Forest)--National Forest Products Association

NWMA--National Woodwork Manufacturers Association

OSHA--Occupational Safety and Health Administration

PCA--Portland Cement Association

PCI--Prestressed Concrete Institute

PS--Product Standard issued by the U.S. Department of Commerce

PTI--Post-Tensioning Institute

SAE--Society of Automotive Engineers

SF--Standard Form

SSPC--Steel Structures Painting Council

UL--Underwriter's Laboratories, Inc.

USASI--United States of America Standards Institute

01101 - 3

Pay Items & Pay Units

ABBREVIATIONS

Aluminum . . . . . . . . . . . . . . . . . . . . AL.

Asphalt . . . . . . . . . . . . . . . . . . . . ASP.

Barbed Wire . . . . . . . . . . . . . . . . . . B.W.

Bituminous Coated Corrugated Steel Pipe . . . . B.C.C.S.P. OR B.C.C.S. PIPE

Bituminous Surface Treatment BST Cement . . . . . . . . . . . . . . . . . . . . . CEMT.

Cement Treated . . . . . . . . . . . . . . . . . CEMT.-T.

Cement Treated Base . . . . . . . . . . . . . . CTB Clearing & Grubbing . . . . . . . . . . . . . . CLEAR & GRUB Compaction . . . . . . . . . . . . . . . . . . . CMPCT.

Concrete . . . . . . . . . . . . . . . . . . . . CONC.

Corrugated Metal Pipe . . . . . . . . . . . . . CMP Corrugated Steel Pipe . . . . . . . . . . . . . C.S.P.

Corrugated Steel Pipe Arch . . . . . . . . . . . C.S.P. ARCH Cubic Yard . . . . . . . . . . . . . . . . . . . C.Y.

Cubic Yard Mile . . . . . . . . . . . . . . . . C.Y.MI.

Diameter . . . . . . . . . . . . . . . . . . . . DIA.

Each . . . . . . . . . . . . . . . . . . . . . . EA.

Emulsified . . . . . . . . . . . . . . . . . . . EMLSFD.

Erosion and Pollution Control . . . . . . . . . E&P CONTROL Fabricated . . . . . . . . . . . . . . . . . . . FABR.

Finish Floor Elevation . . . . . . . . . . . . . F.F.E.

Foundation . . . . . . . . . . . . . . . . . . . FOUND.

Furnished . . . . . . . . . . . . . . . . . . . FURN.

Gallon . . . . . . . . . . . . . . . . . . . . . GAL.

Grade . . . . . . . . . . . . . . . . . . . . . GR.

Height . . . . . . . . . . . . . . . . . . . . . HT.

High Strength . . . . . . . . . . . . . . . . . H. STRENGTH Horizontal . . . . . . . . . . . . . . . . . . . HOR.

Hour . . . . . . . . . . . . . . . . . . . . . . HR.

Linear Foot . . . . . . . . . . . . . . . . . . L.F.

Liquid . . . . . . . . . . . . . . . . . . . . . LIQ.

Loading . . . . . . . . . . . . . . . . . . . . LD.

Lump Sum . . . . . . . . . . . . . . . . . . . . L.S.

Material . . . . . . . . . . . . . . . . . . . . MAT'L Maximum . . . . . . . . . . . . . . . . . . . . MAX.

Method . . . . . . . . . . . . . . . . . . . . . M.

Mile . . . . . . . . . . . . . . . . . . . . . . MI.

Minimum . . . . . . . . . . . . . . . . . . . . MIN.

One Thousand Feet Board Measure . . . . . . . . MFBM One Thousand Gallons . . . . . . . . . . . . . . M.GALS.

One Thousand Gallons Mile . . . . . . . . . . . M.GALS.MI.

01101 - 4

One Thousand Square Feet . . . . . . . . . . . . M.S.F.

Polyvinylchloride . . . . . . . . . . . . . . . PVC Pounds . . . . . . . . . . . . . . . . . . . . . LBS.

Reflectorized . . . . . . . . . . . . . . . . . REFLECT.

Section . . . . . . . . . . . . . . . . . . . . SEC.

Square Foot . . . . . . . . . . . . . . . . . . S.F.

Square Yard . . . . . . . . . . . . . . . . . . S.Y.

Station . . . . . . . . . . . . . . . . . . . . STA.

Station Yard . . . . . . . . . . . . . . . . . . STA. YD.

Strand . . . . . . . . . . . . . . . . . . . . . S.

Structural . . . . . . . . . . . . . . . . . . . STRUCT.

Structural Steel . . . . . . . . . . . . . . . . S. STEEL Stump . . . . . . . . . . . . . . . . . . . . . STMP Target Value . . . . . . . . . . . . . . . . . . TV Thickness . . . . . . . . . . . . . . . . . . . TH.

Ton Mile . . . . . . . . . . . . . . . . . . . . T.M.

Tops and Limbs . . . . . . . . . . . . . . . . . T&L Utilization of Timber . . . . . . . . . . . . . UOT Vertical . . . . . . . . . . . . . . . . . . . . VERT.

Welded Wire Fabric . . . . . . . . . . . . . . . W.W.F.

White . . . . . . . . . . . . . . . . . . . . . WH.

Width . . . . . . . . . . . . . . . . . . . . . W.

With . . . . . . . . . . . . . . . . . . . . . . W/ Without . . . . . . . . . . . . . . . . . . . . W/O Woven wire . . . . . . . . . . . . . . . . . . . W.W.

Yellow . . . . . . . . . . . . . . . . . . . . . YE.

END OF SPECIFICATION 01101

01102 - 1

DIVISION 1 - GENERAL

DEFINITIONS - 01102

Wherever in these specifications, or in other contract documents, the following terms, or pronouns in place of them, are used, the intent and meaning shall be interpreted as follows:

Adjustment in Contract Price. "Adjustment in contract price" shall mean "equitable adjustment" as used in the Federal Acquisition Regulations.

Arch Pipe. A culvert section, usually formed of bolted structural plates, that is an arc of a circle (usually one-half or less); that is, a bottomless culvert.

Base Course. The layer or layers of specified or selected material of designed thickness placed on a subbase or subgrade to support a surface course.

Bearings. The portion of a beam, girder, or truss that transmits the bridge superstructure load to the substructure.

Berm. Curb or dike constructed to control runoff water or traffic flow.

Change. "Change" means "Change Order" as used in the Federal Acquisition Regulations.

Clearing Limits. The limits of clearing as designated on the ground or on the drawings.

Conduit. A natural or artificial channel for carrying fluids, as water pipes, canals, and aqueducts.

Construction Slash. All vegetative material not meeting utilization standards, such as tops and limbs, timber, brush, and grubbed stumps associated with construction or reconstruction of a facility.

Contracting Officer (CO). The person with the authority to enter into, administer, and/or terminate contracts and make related determinations and findings.

Contractor. The individual, partnership, joint venture, or corporation undertaking the execution of the work under the terms of the contract and acting directly or through their agent, employees, or subcontractors.

Controlled Felling. Directing the placement of trees in felling by wedges, jacks, cable tension, or distribution of holding wood or any combinations of these which will ensure that trees are dropped into previously cleared areas, or clear of any objects that are to remain.

01102 - 2

Culvert. A conduit or passageway under a road, trail, or other obstruction. A culvert differs from a bridge in that it is usually constructed entirely below the elevation of the traveled way.

Cushion Material. Native or imported material generally placed over rocky sections of unsurfaced roads to provide a usable and maintainable traveled way.

Defect. A failure to meet a requirement with respect to a single quality characteristic.

Drawings. The documents, including plan and profile sheets, cross sections, diagrams, layouts, schematics, descriptive literature, illustrations, schedules, performance and test data, and similar materials showing details for construction of a facility.

Embankment. A structure of soil, aggregate, or rock material placed on the prepared ground surface and constructed to subgrade.

Engineer. The Contracting Officer's Representative (COR) responsible for onsite administration of the contract.

Equipment. All machinery and equipment, together with the necessary supplies for upkeep and maintenance, as well as tools and apparatus necessary for the proper construction and acceptable completion of the work.

Excess Excavation. Material from the excavation in excess of that needed for construction of designed roadways and facilities.

Forest Service. The United States of America, acting through the Forest Service, U.S.

Department of Agriculture.

Gauge. The term "gauge" when used in connection with the measurement of plates will mean the U.S. Standard Gauge, except when reference is made to the measurement of metal sheets used in the manufacture of corrugated metal, pipe, metal plate culverts and arches, and metal cribbing, then the term means the "gauge" or "thickness" specified in AASHTO M 36, M 167, M 196, and M 219, as applicable. When the term "gauge" refers to the measurement of wire, it will mean the wire gauge specified in AASHTO M 32.

Government Land. National Forest System lands, and other lands controlled or administered by the Forest Service or by other Federal agencies.

Inspector. The Government-authorized representative designated in writing by the CO or COR responsible for detailed inspection.

Job-Mix Formula. The percentage of each material in a mixture intended for a particular use.

01102 - 3

Laboratory. A testing laboratory of the Government or any other testing laboratory approved by the Contracting Officer.

Materials. Any substance specified for use in the construction of the project and its appurtenances.

Maximum Density. The highest density that can be obtained under stated conditions.

Measurement. Determining and expressing the quantities of work or materials.

Multi-Beam Girder. A precast, prestressed concrete member where the concrete deck is precast as an integral part of the member.

Neat Line. A line defining the proposed or specified limits of an excavation or structure.

Nominal Dimensions or Weights. The numerical values shown on the drawings or in the specifications as measurements of material to be used in the construction.

Nominal Maximum Particle Size. The largest sieve size listed in the applicable specification upon which any material is permitted to be retained.

Overbreak. Material beyond the neat line of an excavation that is removed in the process of excavation, usually by blasting.

Pavement Structure. Subbase, base, or surface course, or combination thereof, placed on a subgrade to support the traffic load and distribute it to the roadbed.

Pipe. A culvert that is circular (round) in cross-section.

Pipe-Arch. A pipe that has been factory-deformed from a circular shape such that the width (or span) is larger than the vertical dimension (or rise).

Profile Grade. The trace of a vertical plane, as shown on the drawings, intersecting the top surface at the centerline of the proposed facility construction.

Random Sampling. Sampling at times or locations determined in advance by the use of a table of random numbers.

Reasonably Close Conformity. Unless working tolerances are specified, all work performed and materials furnished shall be in reasonably close conformity with lines, grades, cross sections, dimensions, and material requirements shown on the drawings, indicated in the specifications, or designated on the ground. "Reasonably close conformity" is compliance with reasonable and customary manufacturing and construction tolerances.

01102 - 4

Roadway. The portion of the road within the limits of excavation and embankment, including slope rounding.

Schedule of Items. A schedule in the contract that contains a listing and description of construction items, quantities, units of measure, methods of measurement, unit price, and amount.

Second Samples. A sample taken when the initial sample indicates that the material is defective.

Sidewalk. The portion of the roadway constructed primarily for pedestrian use.

Specifications. A description of the technical requirements for a material, product, or service that includes criteria for determination whether these requirements are met.

Standard Specifications. Specifications approved for general application and repetitive use.

Subbase. The layers of specified or selected material of designed thickness placed on a subgrade to support a base course.

Subgrade. The layers of roadbed that bring it up to the top surface, upon which subbase, base, or surface course is constructed. For roads without base course or surface course, that portion of roadbed prepared as the finished wearing surface.

Tackifier. Binder for vegetative mulch.

Target Value. The percentage of each material in a mixture intended for a particular use from which allowable variations are measured.

Unit of Measurement. The unit and fractions of units shown in the Schedule of Items.

Unsuitable Material. The material excavated during roadway construction that is not usable in embankment and must be disposed of or that can be used only in certain locations or for limited purposes.

END OF SPECIFICATION 01102

01103 - 1

MEASUREMENT AND PAYMENT - 01103

PART 1 - GENERAL

1.1 – Requirements

Measurement and payment for contract work will be made only for and under those pay items included in the SCHEDULE OF ITEMS. All other work and materials will be considered incidental to and included in the payment of the pay items in the

SCHEDULE OF ITEMS.

1.2 – Payment

One of the following methods of measurement for determining final payment is DESIGNATED on the SCHEDULE OF ITEMS for each pay item.

(a) Designed Quantities (DQ): These quantities denote the final number of units to be paid for under the terms of the contract. They are based upon the original design data available prior to advertising the project. Original design data include the preliminary survey information, design assumptions, calculations, drawings, and the presentation in the contract. Changes in the number of units of the originally contemplated work will not be made unless authorized under one or more of the following conditions:

(1) As a result of changes authorized by the Contracting Officer in the originally contemplated work. Minor changes to adjust balance points, etc., will not be considered changes in quantities.

(2) As a result of the Contracting Officer determining that errors exist in the original design data used to determine designed quantities, that cause a pay item to change by 15 percent.

(3) As a result of the Contractor submitting to the Contracting Officer a written request showing evidence of errors in the original design data used to determine design quantities that cause a pay item total to change by 15 percent or more. The evidence must be verifiable and consist of calculations, drawings, or other data that show how the designed quantity is believed to be in error.

Final payment will be made for the designed quantities at the unit price shown in the SCHEDULE OF ITEMS, subject to the Variation in Quantities Provision.

(b) Actual Quantities (AQ): These quantities are determined from measurements of completed work.

01103 - 2

(c) Lump Sum Quantities (LSQ): These quantities denote one complete unit of work as required by or described in the contract, including necessary materials, equipment, and labor to complete the job. They will not be measured.

1.3 - Units of Measurement:

Payment will be by units defined and determined according to U.S. Standard measure.

END OF SPECIFICATION 01103

01300 - 1

SUBMITTALS - 01300

1.1 - Requirements

It will be the Contractor's responsibility to submit all items with such promptness as to cause no delay in the work. Approvals must be obtained before starting work which involves the item. Contractor shall allow ten days for processing of submittals by the Government.

Submittals may also be referred to as shop drawings.

1.2 - Manufacturer's Literature and Shop Drawings

Submit two (2) copies to the Engineer for approval on the items required herein.

Submittal specifications are to be submitted in the following format:

A. The specifications and salient qualities of the item specified in the contract.

B. The specifications and salient qualities of the submittal item.

C. A listing of the differences and a comparison between the two, including but not limited to the structural qualities, operational qualities, any modifications necessary to accomplish installation of unit, and guarantee and warranty.

D. A cost comparison between the specified and submitted item(s) with the cost reduction benefit to the government or adequate justification for a cost increase to the government.

E. Shop drawings of submitted item(s) including layout diagrams.

If there are any modifications necessary to facilitate installation, a set of drawings showing installation of specified item and a set showing how the submittal item will be installed.

If the specified item is to be handicapped accessible the submittal item needs to show handicapped access on submitted drawings, not just state it is available as handicapped accessible.

01300 - 2

Submittals will be waived if contractor furnishes exact item used for design when manufacturer's model, size, etc. are shown in the contract.

Submittals are required per the following sections:

1. 01410 – Quality Control and Quantity Measurement Contractor's Representative Designation Quality Control Plan Project Schedule Certificates-of-Compliance Quantity Measurements

2. 02840 – Road Closure Devices Shop Drawings Product Data Paint Samples

3. 02841 – Signage

4. 03301 – Cast-in-Place Concrete Mix Design Admixtures

5. 09900 – Painting Paint Sample

END OF SPECIFICATION 01300

01410 - 1

QUALITY CONTROL AND QUANTITY MEASUREMENT - 01410

1.1 - Description

This work shall consist of providing quality control in conformance with the Inspection of Construction provisions of this contract to ensure compliance with the drawings, specifications, and provisions of the contract, and measuring the quantities of completed work in conformance with the provisions of the applicable specification. The Contractor shall provide all personnel, equipment, tests, and reports necessary to meet the requirements of this specification.

1.2 - Related Work Specified Elsewhere

General Provisions FAR 52.236-5, Material and Workmanship General Provisions FAR 52.236-6, Superintendence by the Contractor General Provisions FAR 52.246-12, Inspection of Construction

1.3 - Submittals

Submittals under this section shall be furnished to the Engineer. Submittals include, but are not limited to the following:

Contractor's Representative Designation Project Schedule Quality Control Plan As Built Drawings Certificates-of-Compliance Quantity Measurements Test Results

PART 2 - PRODUCTS

None

PART 3 - EXECUTION

3.1 - Contractor's Representative

Submit a letter to the Contracting Officer stating the name of the on-the-job superintendent or representative for the Contractor and the duties and authorities of the representative during work under this contract.

01410 - 2

3.2 - Project Schedule

Submit a project schedule stating information such as proposed dates of completion of various elements of construction.

3.3 - Quality Control Plan

The Quality Control Plan shall consist of the following:

(1) Authorities and responsibilities of inspection and testing personnel.

(2) Experience and qualifications of inspection and testing personnel to be assigned and name and location of any (for hire) testing facility to be used.

The Contractor's proposed quality control plan for all items requiring quality control shall be submitted to the CO for review prior to the Contractor commencing work. Within 10 days of receipt of the plan, the CO shall notify the Contractor whether the plan adequately covers quality control requirements. Construction work shall not be performed prior to Contractor's receipt of written approval of the proposed plan. The Contractor shall submit to the CO, in writing, any proposed changes in the approved quality control plan. Proposed changes shall not be put into effect until approved in writing by the CO.

All work shall comply with local applicable codes and codes referenced in individual sections of the technical specifications.

3.4 - Sampling, Testing, Inspection, and Measurement of Quantities

The Contractor shall provide and maintain appropriate measuring and testing devices, equipment, and supplies to accomplish the required measurement, testing, and inspection in a timely manner. Tests, measurements, and certifications shall be made as required by the drawings and specifications. The Contractor shall take samples and perform inspections and tests necessary to achieve the quality of construction required by the contract and make required measurements of work under this contract performed onsite or offsite. Sampling and testing frequency for specific items shall be specified in the related section.

The Contractor shall maintain current records of all inspections and tests performed. The following information will be acceptable to the Government:

PROJECT NAME:________________________

CONTRACT No._____________________

Pay Item No. Test Date Location Standard Results Test By (Initials)

01410 - 3

The Contractor shall engage inspection and testing agencies which are prequalified as complying with the recommendations of "Independent Laboratory Qualification" by the American Council of Independent Laboratories, and which specialize in the types of inspections and tests to be preformed.

The Contractor shall protect construction exposed by or for quality control service activities and protect repaired construction. Upon completion of inspection and testing repair damaged construction and restore substrates and finishes to eliminate deficiencies.

The Contractor is responsible for repair and protection of inspected work, whether inspection is performed by the Contractor or by the Government.

The Contractor shall certify in writing that all inspections and tests were performed in accordance with specifications.

3.5 - As-Built Drawings

The Contractor shall maintain a set of the contract drawings depicting as-built conditions.

These drawings shall be maintained in a current condition and shall be available for review. All variations from contract drawings shall be indicated in red on the drawings.

Upon completion of the contract work, as-built drawings shall be submitted by the Contractor.

3.6 - Certificates and Measurements

Certification:

The Contractor shall furnish certificates executed by the manufacturer, supplier, or vendor, stipulating that all offsite produced materials incorporated into the work meet the applicable requirements SHOWN ON THE DRAWINGS or stated in the specifications.

Incidental purchases needed to remedy minor shortages of material shall be certified by the Contractor.

Measurements:

The Contractor shall make all measurements for computation of quantities for all work items except those specified for payment by Designed Quantity (DQ). The Contractor shall compute the quantities for periodic progress payments; the Engineer will compute the quantities for the final payment based on measurements taken by the Contractor. All Contractor measurements are subject to verification. The Contractor shall submit all field notes, calculation sheets, and other data used to determine quantities. The Contractor shall certify in writing as to the accuracy of the measurements and computations submitted.

The following format or one containing the following information will be acceptable to the Government:

01410 - 4

PROJECT NAME:_______________________CONTRACT No.__________________

Quantity or Pay Item Date Measurement Test By (Initials)

3.7 - Materials

The contractor shall furnish certificates executed by the manufacturer, supplier, or vendor, stipulating that all offsite produced materials incorporated into the work meet the applicable requirements SHOWN ON THE DRAWINGS or stated in the specifications.

Incidental purchases needed to remedy minor shortages of material shall be certified by the contractor. Earth, aggregate, and concrete material shall be certified and accurately completed indicating weights, volumes, and batch times where appropriate.

When the material sources are not designated as Government-furnished or the Contractor elects not to use designated sources, the Contractor shall be responsible for furnishing materials that produce an end product equivalent in performance to that originally designated and that meets contract specifications.

PART 4 - MEASUREMENT AND PAYMENT

4.1 - Measurement

There will be no separate measurement for this section.

4.2 - Payment

This work is incidental to other items in the contract and direct separate item payment will not be made.

END OF SPECIFICATION 01410

01601 - 1

MOBILIZATION - 01601

This work shall consist of preparatory work and operations necessary for the movement of personnel, equipment, supplies, and incidentals to the project site, and for all other work and operations that must be performed or that cause costs to be incurred prior to beginning work on the various items on the project site.

NONE

NONE

Progress payments will be made as follows:

The Contractor can request payment for performance and payment bonds. The amount of the premium, including coinsurance and reinsurance agreements, will be paid upon receipt of evidence of full payment to the surety. When separate payment for bonding cost is made, the bonding cost will be subtracted from the total contract amount for this pay item and the balance paid in accordance with the progress payment schedule outlined below.

(a) When 5 percent or more of the original contract amount is earned from other pay items, 50 percent of the amount for mobilization, or 5 percent of the original contract amount, whichever is less, will be paid.

(b) When 10 percent or more of the original contract amount is earned from other pay items, 100 percent of the amount for mobilization, or 10 percent of the original contract amount, whichever is less, will be paid.

(c) Upon completion of all work on the project, any unpaid amount for mobilization will be paid.

01601 - 2

Any bonding costs in excess of the total contract amount of this pay item will be paid under one or more other pay items under this contract as determined by the Contracting Officer. In no circumstance will the total amount of this contract be increased as a result of bonding costs exceeding the total contract amount of this pay item.

The total of all payments shall not exceed the original contract amount for this item.

Payment will be made per the SCHEDULE OF ITEMS.

END OF SPECIFICATION 01601

01740 - 1

CLEANING - 01740

1.1 – Clean up

A. The work site shall be maintained in a neat condition durning construction. The work site shall be kept free from accumulation of waste materials and rubbish resulting from the work.

B. If work is stopped or delayed for an extended period of time, the Contractor shall clean up the site as determined by the C.O.

C. Before final acceptance of the project, the Contractor shall remove all waste materials and rubbish resulting from the work.

Not Used

Not Used

END OF SECTION - 01740

02071-1

REMOVAL OF STRUCTURES AND OBSTRUCTIONS - 02071

This section specifies work requiring the removal and disposal of all structures and obstructions within the project limits which have been SHOWN ON THE

DRAWINGS.

Existing structures and improvements which are to become an integral part of the planned improvements shall remain even though not specifically noted.

1.2 - Material Classification

Material to be excavated is unclassified.

1.3 - Related Work Specified Elsewhere

02224 - Excavation, Embankment and Backfill

None.

3.1 – Removal of Structures and Obstructions

Remove all structures and obstructions SHOWN ON THE DRAWINGS. Removal shall include all associated footings or foundations to a depth of no less than 2 feet unless otherwise SHOWN ON THE DRAWINGS OR NOTED IN THE

SPECIFICATIONS.

3.2 – Backfill and Disposal

All voids left after removal, not being incorporated into the work, shall be backfilled and compacted in accordance with Section 02224.

Structures and obstructions removed and designated for disposal AS SHOWN ON THE DRAWINGS OR NOTED IN THE SPECIFICATIONS shall be removed from National Forest Lands and disposed of in accordance with local regulations regarding disposal of construction waste.

02071-2

Measurement will be the removal of existing pipe rail and all associated footings AS

SHOWN ON THE DRAWINGS.

The accepted quantities will be paid for at the contract unit price for each item listed in the SCHEDULE OF ITEMS.

All work required for the complete removal and disposal of items SHOWN ON THE DRAWINGS or listed in the Specifications is included. Separate payment will not be made under other items.

Payment will be made under:

Pay Item Description Pay Unit

02071 (01) Removal of Structures and Obstructions..…….. LS

END OF SPECIFICATION 02071

02110-1

CLEARING AND GRUBBING - 02110

PART 1 - General

Clearing limits shall be the minimum possible to accomplish work. The intent is to preserve as much vegetation as possible.

PART 3 - Execution

3.1 - Clearing

Clear all trees, brush and other objects as directed in the field by the C.O.

Do not remove or damage any trees or other vegetation outside the clearing limits without the approval of the Engineer.

3.2 - Grubbing

Grub all stumps, brush and roots within the excavation limits.

3.3 - Tree Removal and Preservation

Fall trees toward the center of the area to be cleared. Use controlled falling to prevent injury or defacement to structures, other trees, or property.

Trees and shrubs damaged by the Contractor shall be treated by trimming branches flush with tree. Within 3 days of the damage, treat all cut or scarred surfaces of trees or shrubs designated to remain. Use a product prepared especially for tree surgery.

3.4 - Debris Disposal

All debris shall be Construction slash shall be deposited within the clearing limits. Piles shall be constructed so that burning does not damage vegetation designated to remain. If burning is incomplete, the remaining slash shall be repiled and burned until pieces are reduced to less than 3 inches in diameter and 3 feet in length. These pieces shall than be buried.

All debris shall be disposed of off National Forest land at a State approved facility.

02110-2

PART 4 - Measurement and Payment

4.1 - Method of Measurement

The work specified herein will not be measured for payment.

This work is incidental to other items in this contract and direct separate item payment will not be made.

END OF SPECIFICATION 02110

02224 - 1

EXCAVATION, EMBANKMENT AND BACKFILL - 02224

This specification stipulates excavation and backfill, hauling, watering, compaction, disposal of excess or unsuitable excavated material, and final grading.

1.2 - Material Classification

Material to be excavated is unclassified. Contractor may expect to encounter boulders of varying size during any excavation below existing grade.

1.3 - Related Work Specified Elsewhere

02071 – Removal of Structures and Obstructions 02710 – Metal Pipe Rail 02840 – Road Closure Devices 02841 – Signs

2.1 - Backfill Material

Backfill material shall be readily compactible excavated material free of frozen or organic material, highly plastic clay or other objectionable material and shall contain no rocks larger than 4 inches in diameter.

2.2 - Water

Water shall be reasonably clean and free of hazardous substances. Water is not available at the site. Water shall be obtained from a commercial source.

3.1 - Excavation

All suitable excavated materials shall be used in construction of slopes and backfill.

No excavated material shall be placed in lakes or live streams.

Rocks too large to be incorporated into embankments shall be broken for incorporation into the embankment or removed from National Forest Lands and

02224 - 2 disposed of in accordance with local regulations regarding disposal of construction waste.

3.2 - Backfill

General backfill shall be placed in horizontal layers not exceeding 12 inches (loose measure) and compacted. Each embankment layer shall be leveled and smoothed before compaction and placement of subsequent layers. Compaction shall be as shown in Section 3.6.

Finished surfaces shall be reasonably smooth, compacted, and shall drain without ponding.

Backfilling Adjacent to Concrete: Remove all forms and clean the excavated area of all debris. Remove any standing water from excavation. Obtain approval from CO prior to placement of backfill. Do not backfill until concrete has been in place for a minimum of 7 days and has attained sufficient strength to withstand imposed loads.

3.3 - Grading

All areas covered by the project including excavation and embankment areas and adjacent transition areas, shall be uniformly graded so that finished surfaces are at elevations indicated and approved by the CO. Slope grade away from structures a minimum of ¼-inch per foot unless otherwise indicated to provide drainage away from structures.

3.4 - Excess Excavated Material

Excess excavated material shall be placed as directed by the C.O. or removed from National Forest Lands and disposed of in accordance with local regulations regarding disposal of construction waste.

3.5 - Haul

Haul is incidental to excavation and borrow excavation.

3.6 - Compaction

Backfill adjacent to concrete shall be compacted to at least 95 percent of the maximum density as determined by AASHTO T 99, Method C or D. Compaction shall be done with mechanical tampers only.

The density of the embankment material shall be determined during the progress of the work in accordance with AASHTO T 191, T 205 or T 238; T 217, T 239, T 255;

and T 224.

02224 - 3

PART 4 – MEASUREMENT AND PAYMENT

This work is incidental to other items in this contract and direct separate item payment

END OF SPECIFICATION 02224

02840 - 1

ROAD CLOSURE DEVICES - 02840

This work shall consist of constructing, furnishing and installing a road closure device.

02224 – Excavation, Embankment and Backfill 03301 - Cast-In-Place Concrete 05100 – Structural Metal 05500 – Metal Fabrication 09900– Painting

2.1 - Product Requirements

Road Closure Swing Gates:

FSR 112, FSR 651, and FSR 899 shall include the removal of all existing gates and footings.

FSR 112 and FSR 899 will require the installation of one 25’ Double Road Closure Swing Gate each – All Steel, as furnished by W. W. Cattle Guards, LLC (928-537- 4488) or an approved equal.

FSR 651 shall require the installation of one 30’ Double Road Closure Swing Gate

– All Steel, as furnished by W. W. Cattle Guards, LLC (928-537-4488) or an approved equal.

2.2 - Submittals

Contractor shall supply shop drawings to the CO for approval.

02840 - 2

3.1 – Excavation, Embankment and Backfill

This section stipulates excavation and backfill, hauling, watering, compaction, disposal of excess or unsuitable excavated material, and final grading. Refer to Specification 02224 – Excavation, Embankment and Backfill for all related work in this section.

3.2 - Construction Performance

All gates shall be placed to the dimensions AS SHOWN ON THE DRAWINGS.

Gate and associated appurtenances shall be installed AS PER MANUFACTURER’S RECOMMENDATIONS. Final location of all gates shall be verified in the field by the CO prior to installation.

Any welding required shall be done in accordance with the best modern practice and the applicable requirements of AWS D1.1.

Measurement will be made for each road closure device furnished and installed, completed and accepted, including footings and painting.

Payment will be made at the contract unit price for road closure devices.

Payment will be made per the schedule of items.

END OF SPECIFICATION 02840

02841 - 1

SIGNS - 02841

This work shall consist of furnishing and/or installing signs. Signs include retroreflective tape or barricade markers, object markers and all panels, hardware, mounting and installation.

1.2 - Submittals

2.1 – Retroreflective Tape or Barricade Markers

Gate arms, shall be fully retroreflective with vertical stripes, alternating red and white at 16-inch intervals measured horizontally.

Barricade Markers shall consist of type III reflective sheeting mounted on a 14 gage (0.080 inch) aluminum backing and shall meet the minimum standards of the current Manual on Uniform Traffic Control Devices.

2.2 – Object Markers

Object Markers shall be an all-yellow vertical retroreflective sign (OM2-2V) and mounted on a 14 gage (.080 inch) aluminum backing. Object Markers shall meet the minimum standards of the current Manual on Uniform Traffic Control Devices.

2.3 - Hardware

All hardware shall be furnished by the Contractor and shall be vandal-resistant. Any special tools required for maintenance removal and installation shall be furnished to the CO.

3.1 – Retroreflective Tape or Barricade Markers

The Contractor shall install retroreflective tape or barricade markers in accordance with the U.S. Forest Service Sign and Poster Guidelines and at locations directed by the C.O. If installing barricade markers, they must be placed at a minimum of 32” above natural ground.

02841 - 2

3.2 – Object Markers

The Contractor shall install object markers in accordance with the U.S. Forest Service Sign Installation Guide and at locations directed by the C.O.

Measurement shall be for each barricade marker and object marker fabricated and installed.

This item will be included in the cost of the gates. No separate pay item.

END OF SPECIFICATION 02841

03301 - 1

CAST-IN-PLACE CONCRETE - 03301

This section specifies concrete to be used for cast-in-place concrete construction.

02224 – Excavation, Embankment and Backfill 03100 – Concrete Formwork 03201 – Concrete Reinforcement 03345 – Concrete Finishing

(a) Mix Design: A mix design showing the proposed weights of aggregate, water, cement and other components per cubic yard of concrete shall be furnished to the CO a minimum of 72 hours prior to the placement of concrete. No concrete shall be placed without prior approval of this mix design.

(b) Admixtures: Complete information on proposed admixtures, as specified herein, shall be submitted for the CO's approval a minimum of 72 hours prior to the placement of concrete.

2.1 - Cement

Type I or Type II portland cement unless otherwise specified - ASTM C-150. Only one brand of cement shall be used.

2.2 - Aggregate

Aggregate shall meet the requirements of ASTM C 33, "Specifications for Concrete Aggregate". Coarse aggregate shall be Size Number 67 as specified therein.

03301 - 2

2.3 - Admixtures for Concrete

(a) Air Entrainment: Air-entraining admixtures shall meet the requirements of

ASTM C-260.

(b) Water Reducers: Water-reducing, set-retarding, and set-accelerating admixtures shall meet the requirements of ASTM C 494.

(c) Submittals: Furnish the following information to the CO for approval:

1. Brand name of the admixture

2. Amount of admixture to be used per cubic yard of concrete.

3. Reason for requesting the use of the admixture.

2.4 - Curing Materials

Curing materials shall meet the following requirements:

(a) Burlap cloth made from jute or kenaf. . . . AASHTO M 182

(b) Sheet materials for curing concrete . . . . . ASTM C 171

(c) Membrane-forming curing compounds. . ASTM C-309, Type 1 or 1-D

2.5 - Water

Potable water shall be used for mixing, curing, or other applications.

2.6 - Proportioning Concrete

Minimum compressive strength of concrete shall be 3000 psi. Proportion concrete to meet MAG A requirements. Compressive strength of concrete used for footings of Heavy-Duty Gate shall meet manufacturer specifications.

2.7 - Proportioning Concrete for Cold Weather

For concrete placed under "Cold Weather Concreting and Curing" conditions, the Contractor may elect to alter the required proportions in one of the following ways:

Type III Cement: Type III cement may be substituted in equal quantities for Type I or II cement.

Additional Cement: An additional sack per cubic yard of Type I or Type II cement may be added.

03301 - 3

2.8 - Temperature Limits for Cold Weather Concrete

Provide concrete having a minimum temperature of 50 degrees F and a maximum temperature of 90 degrees F at the time of placing. The temperature of the mixing water shall not exceed 140 degrees F. If aggregates are heated, heat uniformly with steam or water coil. Aggregate temperature shall not exceed 95 degrees F.

Aggregate water mix temperature shall not exceed 80 degrees F. Do not use materials containing frost or icy lumps.

2.9 - Temperature Limits for Hot Weather Concrete

Provide concrete having a maximum temperature of 90 degrees F at time of placing. If the ambient temperature is above 90 degrees F, the forms, reinforcing steel, steel beam flanges, and other surfaces which will come in contact with the mix shall be cooled to below 90 degrees F by means of a water spray or other approved methods. Water reducing admixtures shall be used so the maximum amount of water or slump is not exceeded. The mixing of the concrete and the time between mixing and placing shall be kept to a minimum. Chipped or crushed ice may be substituted for a portion of the mixing water on a pound-for-pound basis. If ice is used, all ice shall be entirely melted at the completion of the mixing period.

If concrete temperature exceeds 75 degrees F, concrete shall be in accordance with

ACI 305.

2.10 - Mixing

(a) Plant Batched and Transit Mixed:

1. Batch at a central plant and mix en route to the project in transit mix trucks in compliance with ASTM C-94. (ASTM C 94 Sections 3 and 17 shall not apply).

2. Place concrete within a maximum of 1-1/2 hours or before the drum has revolved 300 revolutions, whichever comes first after the introduction of cement into the batch. In hot weather or due to other contributing factors, a time less than 1-1/2 hours may be required by the CO.

3. Time interval between placement of batches shall not exceed 30 minutes.

(b) Hand Mixed:

Hand mixing will not be allowed.

03301 - 4

2.11 - Mix Adjustments

(a) Water: Water may be added once for purposes of acquiring minimum slump, provided the specified water-cement ratio is not exceeded. For all project mixed concrete, water shall not be added later than 15 minutes from start of mixing. For transit-mixed or agitated concrete, such water may be added upon arrival at the job site. Adding water beyond these conditions constitutes retempering which will not be allowed. When water is added, an additional 20 revolutions at mixing speed is required.

(b) Admixtures: Air-entraining admixtures shall not be added after the start of mixing.

3.1 - Construction

(a) Excavation: Excavation shall be made to the required dimensions to permit the installation and bracing of the forms. The foundation shall be compacted to a firm even surface. All soft, yielding material shall be removed and replaced with acceptable material.

(b) Forms: Forms shall meet the requirements of Specification 03100 - Concrete Formwork.

(e) Mixing and Placing: The concrete shall be struck off to the cross section SHOWN ON THE DRAWINGS, after which it shall be finished to a smooth and even surface.

(f) Reinforcement: All reinforcing steel shall meet the requirements of Specification 03201 – Concrete Reinforcement.

(g) Placement: Concrete shall be discharged into the forms within 1-1/2 hours after the introduction of the cement to the aggregate. Retempering concrete shall not be permitted. The cement shall be added to the mixer at the jobsite whenever this condition cannot be met.

(h) Temperature: Concrete shall not be mixed or placed when the daily minimum atmospheric temperature is, or is expected to be, less than 40 degrees F unless adequate provisions are made to protect the concrete. No concrete shall be placed when the concrete temperature reaches 90 degrees F.

(i) Consolidation: Concrete shall be placed to avoid segregation. High-frequency internal vibrators shall be used for consolidating concrete in the forms. Vibrators

03301 - 5 shall be operated to produce concrete free of voids, but shall not be held so long in one place as to result in segregation or formation of laitance on the surface.

(j) Handling: The use of aluminum pipe, conduit, or troughs for transporting concrete will not be permitted. When concrete is pumped, sampling shall be from the discharge stream at the point of placement.

(k) Finishing: For the purpose of matching adjacent concrete finishes or for other reasons, the CO may permit other methods of finishing than those specified. No plastering will be permitted.

(l) Concrete Placement: Notify the CO a minimum of 24 hours prior to placement.

Place concrete in the forms as near final position as practical in a manner which will prevent segregation or loss of materials.

Place concrete in maximum 18" horizontal layers.

Immediately after placing, thoroughly compact concrete with mechanical vibrators.

Provide minimum of two vibrators. Provide minimum of two power sources unless commercial power is available at site. Hand tamping, when permitted, will be approved in writing by the CO.

Place each concrete section in a continuous operation, such as slab, footing, columns.

Do not drop concrete freely more than 4 feet.

Do not place concrete in water or allow water to rise over freshly placed concrete until a set is sufficient to prevent damage.

(m) Backfilling: After the concrete has set sufficiently, it shall be backfilled to the required elevation with selected material placed in horizontal layers, not over 6 inches (loose measure) in depth, to the level of the original ground surface.

Backfill shall be readily compactable material free of frozen lumps, chunks of highly plastic clay, or other objectionable material. Rocks larger than 3 inches in diameter shall not be used within 1 foot of the structure.

(n) Protection from Rainfall: Protect flat work during rainy periods with adequate waterproof covering. Support covering so that finishing may be performed and initial set obtained without damage. Dragging of tarpaulins or other covering across unset concrete will not be permitted.

(o) Curing: Commence curing and protection of concrete immediately after completion of the finishing. Cure Type I and Type II cement for 7 days

03301 - 6 continuously. The work shall be moistened and kept moist during this time, or curing shall be accomplished by the use of membrane-forming curing compound.

(p) Cold Weather Concreting and Curing: When the descending air temperature at the project falls below 40 degrees F the Contractor shall cease placing concrete unless the procedures described below are followed. Normal concreting operations may resume when the ascending temperature at the site exceeds 40 degrees F.

Provide cover and heating equipment sufficient to maintain the temperature of the concrete at not less than 50 degrees F for a period of period of 3 days for Type I and Type II cement. Maintain the temperature at not less than 50 degrees F for a period of 2 days for Type III cement or when one additional sack of Type I or Type II cement is added.

Provide additional protection to prevent the concrete temperature from dropping more than 40 degrees F in the 24 hour period following the required protection period.

Keep concrete and forms wet. Remove and replace any concrete damaged by frost or freezing when directed by the CO.

(q) Hot Weather Concreting and Curing: If curing temperatures as placed are expected to exceed 75 degrees F, placing and curing shall be in accordance with

ACI 305.

The accepted quantities will be included in other contract items.

END OF SPECIFICATION 03301

03345-1

CONCRETE FINISHING - 03345

This section specifies finishing of concrete surfaces.

03100 - Concrete Formwork 03201 - Concrete Reinforcement 03301 - Cast-In-Place Concrete

1.3 - Locations

Unless otherwise SHOWN ON THE DRAWINGS, provide a Class 1 finish to all vertical concrete surfaces except in crawl spaces, and finish all exterior slabs and sidewalk surfaces to Class 5 finish. Finish all interior slabs as SHOWN ON THE DRAWINGS or required in other specifications.

3.1 - Class 3, Float Finish

Immediately after placing concrete for horizontal surfaces, vibrate, tamp, and strike off with screed or templates if crowns are required. Hand finish to smooth, even surface with wood float. After excess moisture has dissipated but concrete is still plastic, check for proper grades, crowns, and uniformity. Fill or cut down incorrect surfaces; refloat for final finish. Use no mortar for leveling.

3.2 - Grading

Slope concrete down and away from gate posts to direct drainage and to prevent footing structures from collecting drainage from rainfall runoff.

03345-2

This work is incidental to other items in this contract and direct separate payment

END OF SPECIFICATION 03345

03345-3

05100-1

DIVISION 5 - METALS

STRUCTURAL METAL - 05100

1.1 - Scope

Perform all work necessary and required for the construction of the project as related to the…