This Statement of Work details a trail bridge construction project for the US Department of Agriculture's Eldorado National Forest under the Great American Outdoors Act (GAOA). The project involves fabricating, constructing, and installing three multi-user trail bridges at Caples, Schneider, and Jobe crossings on the Lake Margaret trail, with an optional trail re-route totaling 0.8 miles. The primary scope includes two 42'6" prefabricated steel truss bridges on concrete foundations and one 28' treated timber bridge, along with four trail approaches and up to one mile of moderately developed trail construction.
The project is located in Alpine and Eldorado Counties, California, with an estimated start date of September 2025 and a 120-calendar day performance period. The bridges will replace existing fire-scarred and rotting log crossings to improve trail safety and recreational opportunities. The solicitation is a total small business set-aside with a project magnitude between $1,000,000 and $5,000,000. Key dates include a site visit on July 7th, 2024, and an RFI submission deadline of July 10th, 2025. The contractor will be responsible for comprehensive site preparation, bridge fabrication, installation, and adherence to specific Forest Service trail construction standards and environmental requirements.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US Department of Agriculture (USDA)
Statement of Work
Contents Project
General Information
1.0 Scope of Work
2.0 Background
3.0 Location
4.0 Estimated Start Date / Period of Performance
5.0 Drawings and Specifications
6.0 Restrictions on Work
6.0 Camping and Housing
7.0 Required Submittals from FP-14 or Supplemental Spec 557
Contractor Requirements
8.0 Technical Requirements / Tasks
9.0 Government Furnished
10.0 Deliverables / Schedule
11.0 Travel
12.0 Contractor’s Key Personnel
13.0 Security Requirements
14.0 Site Visit
15.0 Additional Specifications / Requirements
A. Attachment 1
B. Lake Margaret Trail Bridges (17E46)
C. Lake Margaret Trail Bridges (17E46)
D. Lake Margaret Trail Bridges (17E46)
E. Lake Margaret Trail Bridges (17E46)
Project GAOA, Trail Bridges at Caples, Schneider, and Jobe
General Information
1.0 Scope of Work
Fabricate, construct, and install two multi-user trail bridges on the Lake Margaret trail at the Caples and Schneider Creek crossings.
Option 1: Fabricate, construct, and install one multi-user trail bridge on the Lake Margaret trail at the Jobe crossing.
Option 2: Construct two sections of new trails that connect the existing Lake Margaret trail with the trail bridge locations totaling 0.8 miles following a pre-determined & flagged route.
2.0 Background
This is a 2021 approved GAOA project. Currently the three water crossings (Jobe, Caples, Schneider) consist of old, fire-scarred, and rotting logs with no handrails. Structurally sound bridges are needed at the three sites to allow the safe walking of the trail to Lake Margaret and improve or enhance recreational opportunities in the area.
3.0 Location
The project is located on the Amador Ranger District of the Eldorado National Forest, which is in Alpine and Eldorado Counties, California, in T10N R17E Sections 15,16, & 22. The Lake Margaret trailhead is located along Highway 88, approximately 56 miles Northeast of Jackson, CA and 0.5 east from the Kirkwood Mountain resort turnoff. The Caples Lake Caltrans Maintenance Station (helicopter staging area) turnoff is 2.3 miles east from the Kirkwood Mountain Resort turnoff. Exact location of helicopter staging area TBD. The Jobe trail bridge site (option 1) is 0.3 miles from the trailhead parking/staging area. The Caples trail bridge site is 0.75 miles from the trailhead parking/staging area. The Schneider trail bridge site is 2.2 miles from the trailhead parking/staging area. The trail re-routes are located before and after the Caples trail bridge site & before and after the Schneider trail bridge site. Both are flagged with pink ribbon.
4.0 Estimated Start Date / Period of Performance
September, 2025 / 120 Calander days
5.0 Drawings and Specifications
Included in the attachment “Drawings for Lake Margaret”. See also attached “Supplemental Spec 557”. Refer to “Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects” FP-14.
6.0 Restrictions on Work
• Work hours are limited to non-holiday weekdays, Monday – Friday, 0700 – 1900.
• In accordance with the fire plan.
• When the Contracting Officer (or designated representative) determines that adverse weather has made access too dangerous or if too high of a volume of water in the stream channels hinders safe working conditions.
• When the Contracting Officer or designated representative determines that work must stop due to the presence of archaeological artifacts.
• The Contractor is responsible for the security of their tools, equipment, and material/supplies at all times during the terms of the contract.
• The contractor is responsible for removal and disposal all excavated dirt and shall not leave excavated dirt scattered over the site, unless approved by the COR.
• All trash and loose materials shall be secured by the contractor daily.
• The Contractor is responsible for installing sediment control devices, such as straw wattles and filter fabric fencing, to prevent sediment runoff to nearby areas. Excavation work shall not commence until sediment control devices have been installed and approved by the COR.
• The Contractor shall not use Government trash facilities without the COR’s approval.
• All construction debris remains the property of the Contractor and shall be properly disposed of off National Forest Land.
• The contractor will be able to utilize the Forest Service Roads that access the parking lots; however, the contractor will be responsible for any damage to the roads due to construction activities. The contractor shall be responsible for obtaining permission to use all other roads and staging areas.
• Any work performed while the helicopter is in operation that is not sanctioned by the helicopter crew.
6.0 Camping and Housing
Housing is not available. Camping is only allowed in developed designated campgrounds and must be pre-arranged with the campground concessionaire in the area and not with the Forest Service.
7.0 Required Submittals from FP-14 or Supplemental Spec 557
Caples & Schneider Trail Bridges:
Section 155. – Schedules for Construction Contracts, 05. – Initial & Baseline Construction Schedule Section 104. – Control of Work, 03 – Specifications & Drawings, (a)(2)(b)(1) – Submit drawings for the following:
(d),(g),(j) Section 714. – Geosynthetic Material, 01 – Geotextile or 02 – Geocomposite Drain Section 601. – Minor Concrete structures, Table 601- 1 Composition of Minor Concrete Section 709. – Reinforcing Steel, 01(a) General Section 564. – Bearing Devices, 04 – Elastomeric Bearings Section 710. – Fence & Guardrail, 02 – Woven Wire Section 716. – Material for Timber Structures, 03 - Treated Structural Timber and Lumber Section 717. – Structural Metal, 01 – Structural Steel (c) High-strength quenched and tempered steel Section 717. – Structural Metal, 01 – Structural Steel (d) Bolts and nuts Section 104. – Control of Work, 03 - Specifications & Drawings, [c] – As-built drawings
Jobe Trail Bridge (Option 1):
Section 155. – Schedules for Construction Contracts, 05 – Initial & Baseline Construction Schedule Section 557. – Timber Structures, 02 – Requirements: Provide shop drawings for all timber Section 714. – Geosynthetic Material, 01 – Geotextile or 02 – Geocomposite Drain Section 104. – Control of Work, 03 – Specifications & Drawings, (B)(1)(b) – Specific requirements for Section 601. – Minor Concrete structures, Table 601-1 Composition of Minor Concrete Section 709. – Reinforcing Steel, 01(a) - General Section 716. – Material for Timber Structures, 03 - Treated Structural Timber and Lumber Section 716. – Materials for Timber Structures, 04 - Structural Glued Laminated Timber Section 557. – Timber Structures, 05 – Holes for . . . Bolts and Lag Screws, 06 – Treating Timber Section 717. – Structural Metal, 01(d)- Bolts and Nuts, 07 – Galvanized Coatings Section 564. – Bearing Devices, 04 – Elastomeric Bearings Section 563. – Painting, 03 – Qualifications, 04(a) – Submittals Section 557. – Timber Structures, 08 – Hardware Section 104. – Control of Work, 03 - Specifications & Drawings, [c] – As-built drawings
Trail Re-Routes (Option 2): N/A use of native material only
Contractor Requirements
8.0 Technical Requirements / Tasks
• Design, fabricate, deliver, and the installation of two 42’ 6” prefabricated steel truss superstructures on poured in place concrete substructure/foundations with reinforcing steel, anchored into native rock/soil.
Construct four trail approaches that ties into the bridges.
• Design, deliver, construct, and the installation of one 28’ treated timber and lumber superstructure.
• Construct up to 1 mile of Class 2-3 moderately developed trail in four sections to access bridge sites.
9.0 Government Furnished
The Government will provide the contractor with a set of plans w/details and specifications for the three trail bridges and the trail re-routes. The Government will provide a qualified representative to oversee the project and to ensure that the project is built to the approved set of plans. The government will review and respond to reports, invoices, and final products within 5 working days upon receipt.
10.0 Deliverables / Schedule.
Item No. Deliverable Objective Due
1 Mobilization Initiation of project Within Notice to Proceed
2 Trail re-routes Provide a clear path to the bridge sites
14 days after start date
3 Structural evacuation (Schneider only), sediment control, structural backfill, site preparation
Project site stabilization and dimensional layout
28 days after start date
4 Foundational anchors, construct forms and apply reinforcing steel, pour in place concrete, install Gabions (Jobe only)
Substructure/Foundation installation
44 days after start date
5 Design, fabricate, deliver, and install prefabricated bridge superstructure 12 days after concrete is poured
Superstructure installation 92 days after start date
6 Install deck and run planks (all), posts, rails, and curbs (Jobe only)
Bridge surfacing completed 106 days after start date
7 Install approach rails (Caples only) & Geocomposite sheet drain systems, backfill and armor approaches, de-mobilize
Project completion 120 days after start date
11.0 Travel
N/A
12.0 Contractor’s Key Personnel
Contractor’s representative or work site superintendent is a required key personnel. Must be present at all times when the sub-contractor(s) and/or contractor’s employees are working on the site and when the contractor is not present. Must have experience in projects with similar levels of deliverables, complexity, and value. A resume of this key personnel shall be provided for review to the government before work starts. The government reserves the right to deny or accept this personnel after reviewing their qualifications.
13.0 Security Requirements
N/A
14.0 Site Visit
A preproposal site conference will be held with the below information provided. In no event shall failure to inspect the site constitute grounds for a claim after contract award.
Organized Site Visit Details:
• Date / Time: July 7th, 2025/ 9:30 to 2:30
• Address / bldg. #: Lake Margaret Trailhead parking lot, Hwy. 88, 0.4 miles east of the Kirkwood Ski Area turnoff
FS personnel leading Site Visit Contact Info
• Title: Contractor Officer Representative
• Name: Don Morrill
• Phone #: 530-957-0740
• Email: don.morrill@usda.gov
15.0 Additional Specifications / Requirements
A. The Government’s general and specific requirements for the Lake Margaret Trail Bridge project are as follows:
1) Fabricate, construct, and install two multi-user trail bridges on the Lake Margaret trail, Caples and Schneider crossings.
2) Option 1: Fabricate, construct, and install one multi-user trail bridge on the Lake Margaret trail, Jobe crossing.
3) Option 2: Construct two sections of new trails that connect the existing Lake Margaret trail with the trail bridge locations totaling 0.8 miles following a pre-determined & flagged route.
4) Commence and complete all the work described herein within 120 days from the Notice to Proceed.
B. Location and Mileage to the Staging Areas and the Bridge Sites:
1) The Lake Margaret Trailhead parking area and trail access staging area is 0.5 miles east from the Kirkwood Mountain Resort turnoff.
2) The Caples Lake Caltrans Maintenance Station (helicopter staging area) turnoff is 2.3 miles east from the Kirkwood Mountain Resort turnoff. Exact location of helicopter staging area TBD.
3) The Jobe trail bridge site is 0.3 miles from the trailhead parking/staging area.
4) The Caples trail bridge site is 0.75 miles from the trailhead parking/staging area.
5) The Schneider trail bridge site is 2.2 miles from the trailhead parking/staging area.
C. Performance Period. It is expected that the Notice to Proceed will be issued in spring of 2026 after design and procurement of bridge materials. The performance period is 120 calendar days after the issuance of the NTP. All work as described in this Statement of Work, applicable attachments, and other contract documents shall be completed within that period.
1) Work shall be performed during daylight hours between 0600 hours and 1900 hours local time. Exceptions to these times are:
i. In accordance with the fire plan, if included in Section J.
ii. When the Contracting Officer (or designated representative) determines that adverse weather has made access too dangerous or that continued vehicular travel would cause unacceptable road damage.
D. Specific Requirements:
1) Trail construction standards for the Lake Margaret trail shall adhere to the ROS class: semi-primitive non-motorized trail class 2/3. Tread width is 18-36”, Clearing height is 8’, Clearing width is 5-6”, trail tread linear slope does not exceed 8% grade, trail tread cross slope averages 3% grade. Trail erosion control measures (water bars, rolling dips, reverse grades) average five features every 0.1 miles. Logs for no deck puncheon are on-site.
2) For the Schneider Creek trail bridge and the Caples Creek trail bridge: The bridge structure, and approach rail posts shall be constructed from "Weathering Steel" per the contract drawings. Horizontal rails on the approach railing shall be #1 Redwood. Deck planks shall be Douglas Fir-Larch #1, and pressure treated as specified on the contract drawings.
mailto:don.morrill@usda.gov
3) For the Jobe Crossing trail bridge (option 1), Forest Service standard trail bridge design for a wooden major trail bridge applicable to the appropriate length. See attached trail bridge drawings.
4) Minimum dimensions for all trail bridges are: 72” width between top railing which shall be no less than
54” above top of deck. The maximum opening of side railings shall be no more than 4”.
5) Design all trail bridges per requirements listed in FSH 7709.56b, Section 82.2 and 82.3, and the AASHTO specifications listed on the contract drawings. The design Pedestrian Live Load, Snow Load, Equestrian
Load, Wind Load, and Seismic Load shall be as listed on the contract drawings.
6) The deck tread surface shall be wear and slip resistant. The Government’s preference for deck material is pressure-treated rough-cut hem/fir, #1 or better. Other materials meeting these basic requirements may be proposed. All guard/hand railings 12” or more above the deck shall be non-corroding metal, un-treated splinter resistant wood or recycled HDPE.
7) Construction of the bridge’s footings/foundation shall have been completed at least 18 days before attachment and installation of the superstructure to allow concrete to cure and harden.
8) The contractor shall supply and install all prefabricated steel bridge sections, dimensional lumber, concrete, associated hardware and appurtenances, as shown in the drawings. The contractor is responsible for verifying the correct length of each trail bridge prior to fabrication.
E.Adherence to Standards and Codes:
1) The following standards and codes govern all design and construction:
i. Standard Specifications for Construction of Trails and Trail Bridges on Forest Service Projects, 2014.
ii. AASHTO LRFD Bridge Design Specifications, Ninth Edition, 2020.
iii. Forest Service Handbook (FSH) 7709.56b – Transportation Structures, Chapter 80 - Trail Bridges.
iv. AASHTO: LRFD Guide Specifications for the Design of Pedestrian Bridges, 2nd Edition.
v. Forest Service: The Built Environment Image Guide.
F. Additional Specific Requirements:
1) Before construction activities begin, the Contractor shall prepare and submit for Government review and approval the following plans:
i. Health and Safety (Accident Prevention) Plan. Reference Attachment 2, HEALTH AND SAFETY
REQUIREMENTS.
ii. Soil Erosion and Pollution Prevention Plan. Reference Attachment 3, SOIL EROSION AND
POLLUTION PREVENTION REQUIREMENTS.
iii. Contractor Quality Control Plan. Reference Attachment 4, CONTRACTOR QUALITY CONTROL
REQUIREMENTS.
iv. Personnel, Material and Equipment Transportation Plan. Reference Attachment 5, SITE TRANSPORTATION PLAN. (NOTE The Government does not approve a Transportation Plan except as the proposed activities affect or may affect Government lands, resources, and/or personnel.
v. Equipment Cleaning: All off-road equipment used on this project shall be washed before moving into the project area so that the equipment is free of soil, seeds, vegetative material, or other debris that could contain or hold seeds of noxious weeds. “Off-road equipment” includes all logging and construction equipment and such brushing equipment as brush hogs, masticators, and chippers; it does not include log trucks, chip vans, service vehicles, water trucks, pickup trucks, and similar vehicles not intended for off-road use. Equipment will be considered clean when visual inspection does not reveal soil, seeds, plant material, or other such debris. Disassembly of equipment components or specialized inspection equipment is not required. Contractor shall notify the Contracting Officer at least five days in advance of moving equipment in so that arrangements can be made for inspection. If the project area is known to contain noxious weeds, the equipment shall be cleaned before moving to other Forest Service system lands which do not contain noxious weeds.
vi. Archeological and Historic sites: Location of known archaeological, historic, or prehistoric materials – such as Native American sites or artifacts and/or historic mining, logging, or fur trapping remains protected by the American Antiquities Act (16 USC 433)--will be identified for the contractor before work commences.
G. Upon award, the contractor shall, within fifteen days and before construction activities begin, perform the following work:
1) Confirm applicability and accuracy of any previously submitted Project Schedule.
2) Progress payments will be made according to the Schedule of Values.
H. The Contractor shall submit the following for Government review to insure compliance with contract requirements:
1) Additional plans, drawings, and specifications generated during the course of the project shall be submitted to the Government for review as soon as available.
2) The Government shall have no less than 15 calendar days to reply to these submittals. If a submittal is rejected, the Government shall have a further 10 days to review and reply to any subsequent submittal(s).
I. Except as provided for in F. “Additional Specific Requirements”, after award, the Government’s review of submittals shall be limited to insuring compliance with the requirements of the contract and specifically the Statement of Work.
1) Not less than 15 calendar days prior to completion of site work the Contractor shall submit, for Government approval a plan for closeout procedures.
2) Not more than 20 calendar days after completion of site work, the contractor shall provide the following: A full set of “As Builts” plans that include:
i. The layout and Lat/Long location (within five feet) of the trail bridge sites.
ii. Construction drawings of the trail bridges in sufficient detail so as to facilitate repairs, remodeling, or reconstruction of the finished structures(s).
iii. A site plan with all constructed features (landings, trails, and pathways/trails) located either by
GPS or data survey.
iv. Final clean-up: Before final acceptance, all areas occupied by the Contractor in connection with the work shall be cleaned of all contractor’s rubbish, excess materials, temporary structures, and equipment, and all parts of the work area shall be left in a neat and presentable condition.
J. Government Inspections:
1) Government Inspections are for the purpose of satisfying the Government that the services are acceptable and do not relieve the Contractor of the responsibility for maintaining quality control. The Contracting Officer's Representative or designated inspector will conduct all inspections. The Contractor (or designated representative) is encouraged to be present to observe inspections.
Summary results will be made available on request.
2) Compliance Inspections are visual compliance inspections that will be made on a periodic basis while work is in progress. Inspections are not final and do not constitute acceptance by the Government but are made for compliance with the terms of the contract.
3) Final (formal) inspections for payment will be made on completed sub-items only. The contractor shall request final inspections in writing and give the Forest Service at least two working days advanced notice. Inspections will be completed within four working days after the notice is received. If the work is not ready for inspection at the time specified by the contractor, the cost associated with the inspection attempt may be charged to the contractor.
4) Disputed Inspections: The Contractor may request re-inspection without rework if the results are unacceptable. Re-inspection must be requested in writing within 48 hours after receiving written notice of the inspection results. Re-inspection will be completed within five working days after receiving compensation of the contractor's written request. The same sampling and inspection procedures will be used, but new samples will be taken. The inspection pattern will be shifted so that new samples will not overlap previously inspected samples. Results will be rounded to the nearest whole percent. If re-inspection results are within five percentage points of the first inspection, the original inspection result will be used in determining acceptability and payment. If re-inspection results are greater than five percentage points above or below the first inspection, the re-inspection results will be used. If the re-inspection results are within five percentage points of the first inspection.
the Contractor shall pay the actual costs of the re-inspection.
5) Reinspection after rework: Where re-work after a failed inspection may improve the inspection results, the Contractor may rework the area and request (in writing) a second inspection. The Government will charge the Contractor the cost of this additional inspection. Re-inspection will be completed within five working days after the notice is received. The results of the second inspection will be final, and no further rework will be permitted. Areas not ready for re-inspection at the time specified by the Contractor will not be reinspected, and the results of the first inspection will be final.
Work on this contract will be deemed acceptable when the Government’s visual inspections show compliance with all requirements of FAR Clause 52.246-12.
6) Public officials not personally liable: There shall be no personal liability upon the Contracting Officer or Contracting Officer Representative (COR) in charge, their agents or employees, for any act performed in the discharge of any duty imposed or the exercise of any power or authority conferred upon them by, or within the scope of the contract, it being understood that in all such maters they act solely as agents and representatives of the Government.
References and Specification Sources (as of 07/01/2022)
Standard Specifications for Construction of Trails and Trail Bridges on Forest Service Projects, 2014:
https://www.fs.fed.us/recreation/programs/trail-management/documents/plans/supporting_documents/Trail_Specifications.pdf
FSH – 7709.56b Transportation Structures, Chapter 80-Trail Bridge Design https://www.fs.fed.us/im/directives/fsh/7709.56b/wo_7709.56b_80.doc
Forest Service Trail Accessibility Guidelines, 2013 (FSTAG):
https://www.fs.usda.gov/sites/default/files/FSTAG-2013-Update.pdf
Forest Service Outdoor Recreation Accessibility Guidelines, (FSORAG) https://www.fs.usda.gov/sites/default/files/FSORAG-2013-Update.1.pdf
Forest Service: The Built Environment Image Guide.
https://www.fs.fed.us/recreation/programs/beig/
AASHTO: LRFD Guide Specifications for the Design of Pedestrian Bridges, 2nd Edition https://store.transportation.org/Item/PublicationDetail?ID=1552
AASHTO, Guide for the Planning, Design, and Operation of Pedestrian Facilities, 2nd Edition https://aashtojournal.org/2021/12/17/aashto-issues-revised-pedestrian-facilities-guide/
AWPA. American Wood Protection Association (AWPA) Standards https://awpa.com/info/publications/standards
AASHTO LRFD Bridge Design Specifications, Ninth Edition, 2020 http://www.fs.fed.us/recreation/programs/trail-http://www.fs.fed.us/im/directives/fsh/7709.56b/wo_7709.56b_80.doc http://www.fs.usda.gov/sites/default/files/FSTAG-2013-Update.pdf http://www.fs.usda.gov/sites/default/files/FSORAG-2013-Update.1.pdf http://www.fs.fed.us/recreation/programs/beig/
A. Attachmen t 1
Lake Margaret Trail bridges (17E46)
Notes on Statement of Work
Section 2 A. The contractor is expected to deliver the bridge(s) to the various sites in the fewest separate sections possible. The government does not want “Erector-Set” structures composed of many fields assembled components. Except for minor adjustments to accommodate a proper fit to the foundations, field cutting or welding on the bridges shall not be permitted. Any steel components shall conform to ASTM A-588.
Fasteners used in any steel structure shall conform to ASTM A-325.
B. It is presumed that the deck and rub/handrails will be attached on site however, the contractor is under no obligation to do so. In either event, care shall be taken to protect the deck and railings from damage during transit and installation
C. The contractor shall provide to the Government, with the design submittals, the results and reports generated from site surveys. Submittals shall be in pdf format wherever possible.
D. As-Built drawings shall be provided in electronic form both as .pdf files in 11 X 17 format and .dwg files. All other documents shall be provided in .pdf format. Survey data files shall be submitted as .dwg files. Other .dwg compatible formats may be proposed. Dimensional tolerances shall be:
K.1 For geographic locations (GIS): Not greater than ten feet. For the bridges, locations shall be recorded at the center of the span.
K.2 For construction drawings: tolerances shall meet generally accepted industry standards. In no event shall tolerance be greater than 0.4 inches for structural components except bearing pads with slotted bolt holes.
B. Lake Margaret Trail Bridges (17E46)
Attachment 2
HEALTH and SAFETY REQUIREMENTS
Before construction begins, the contractor shall submit for approval a Site-Specific Health and Safety (Accident Prevention) Plan, which contains, at a minimum, the following information.
Accident Prevention Program:
The Contracting Officer (CO) will review the proposed program for compliance with OSHA and project requirements. If the program requires any revisions or corrections, the Contractor shall resubmit the program within 10 days. No progress payments will be processed until the program is approved. The program shall include:
A. Name and phone number of responsible on-site supervisor to carry out the program.
B. Weekly and monthly safety meetings
C. First aid procedures.
D. Outline of each phase of the work, the hazards associated with each major phase, and the methods proposed to ensure property protection and safety of the public*, Government personnel, and the Contractor's employees (Job Hazard Analyses). Identify the work included under each phase by reference to specification section. *Trail will be closed to the public.
E. Training, both initial and continuing.
F. Submit a brief report of safety meetings and of inspections.
G. Upon request, submit proof of employees' qualifications to perform assigned duties in a safe manner.
Accident Reporting
A. Reportable Accidents: A reportable accident is defined as death, occupational disease, traumatic injury to employees or the public, property damage by accident in excess of $100, and fires. Within 7 days of a reportable accident, fill out and forward to the CO a DI-134 form, which may be obtained from CO.
B. All Other Accidents: The Contractor shall report all other accidents to the CO as soon as possible and assist the CO and other officials as required in the investigation of the accident.
Personal Protective Equipment
A. Shall meet requirements of OSHA and CalOSHA.
B. Damaged or defective personal protective equipment shall not be used
C. Employees operating chain saws:
1. Shall wear foot protection that is constructed with cut resistant materials which will protect against contact with a running chain saw
2. Shall be provided with by the contractor, at no cost to the employee, chain saw chaps approved by Underwriter’s laboratory or meet Forest Service specification 6170-47.
D. The Contractor shall ensure that employees use and employ all personal protective equipment appropriate to each task as it is performed.
C. Lake Margaret Trail Bridges (17E46)
Attachment 3
SOIL EROSION AND POLLUTION PREVENTION REQUIREMENTS
Before construction begins, the contractor shall submit a Site-Specific Soil Erosion Control and Pollution Prevention Plan for Government approval. The plan shall contain, at a minimum, the following information.
Permanent and temporary erosion control measures to minimize erosion and sedimentation during and after construction.
Plan to incorporate all permanent erosion control features into the project at the earliest practicable time, as outlined in the approved plan.
Mitigation plan if and when erosion control measures are not functioning as intended, immediately take corrective action.
Do not modify the type, size, or location of any control. An alternative erosion control plan with all necessary permits shall be submitted 15 days before intended use.
The submitted and incorporated plan shall conform to all applicable state and federal standards and requirements.
This plan shall serve as the Storm Water Pollution Prevention Plan. The Government has determined that the total area that may be disturbed is less that one acre. A California Storm Water Pollution Permit is not required.
D. Lake Margaret Trail Bridges (17E46)
Attachment 4
CONTRACTOR QUALITY CONTROL REQUIREMENTS.
Before construction begins, the Contractor shall submit for Government approval a Project Specific Contractor Quality Control Plan, which contains, at a minimum, the following information:
A A list of personnel responsible for quality control and assigned duties. Include each person's qualifications.
B A copy of a letter of direction to the Contractor's Quality Control Supervisor outlining assigned duties.
C Names, qualifications, and descriptions of laboratories to perform sampling and testing, and samples of proposed report forms.
D Methods of performing, documenting, and enforcing quality control of all work.
E Plan to submit all Daily Reports (Diaries) to the C.O. weekly in electronic format (PDFs).
The Quality Control Plan shall contain the following elements of a Three-Phase CQC program.
A. Preparatory Phase: Perform before beginning each feature of work.
1. Review all applicable specifications sections and drawings related to the features of work and ensure that copies of all referenced standards related to sampling, testing, and execution for the features of work are available on site.
2. Verify all field dimensions and advise the Contracting Officer of discrepancies with contract documents.
3. Ensure that necessary equipment and materials are at the project site and that they comply with approved shop drawings and submittals and that provisions have been made for field control testing.
B. Initial Phase: Perform as work on each feature begins.
1. As soon as work begins, inspect and test a representative portion of a particular feature of work for quality of workmanship.
2. Review control testing procedures to ensure compliance with contract requirements.
3. Prepare a report on all initial phase activities and discussions. Attach report to Contractor's Quality Control Daily Report. Location of initial phase shall be indicated for future reference and comparison with follow-up phases.
C. Follow-Up Phase: Inspect and test as work progresses to ensure compliance with contract requirements until completion of work. Additional Preparatory and Initial Phases: Additional preparatory and initial phases may be required on the same feature of work for the following reasons:
1. The quality of on-going work is unacceptable.
2. Changes occur in the applicable quality control staff, on-site production supervision, or work crew.
3. Work on a particular feature of work is resumed after a substantial period of inactivity.
E. Lake Margaret Trail Bridges (17E46)
Attachment 5
SITE TRANSPORTATION PLAN
Before construction begins, the Contractor shall submit for approval a Site Transportation Plan, which contains, at a minimum, the following information.
The movement of personnel, equipment, and materials from the on-the-ground staging area (Lake Margaret Trailhead) and the helicopter landing zone (CalTrans Caples Lake Maintenance Station) to the various work sites.
As appropriate, this plan may reference the:
• Health and Safety Plan
• Soil Erosion and Pollution Prevention Plan.
• The Contractor Quality Control Plan
The following specific points shall be addressed in the plan:
F. Means of travel for construction personnel between the staging area and the construction sites
G. Means of transport for equipment and materials between the staging area and the construction sites.
H. Personnel safety issues directly related to their travel on the job.
I. Personnel safety issues related to the movement of equipment and materials.
J. Potential hazards to government lands and resources resulting from the movement of equipment and materials and any mitigation measures.
K. Procedures to be employed to minimize or eliminate damage to materials during transit.
Considerations in the plan
A. The Contractor should presume that Government personnel will be present during the transport of materials as observers including at the various construction sites
B. Government employees shall not engage or assist with any transportation operations except in the event of an imminent threat to life. The Contractor shall not presume or plan on assistance from Government personnel for routine or emergency situations during their operations.
C. Small wheeled and tracked vehicles have been recently operated on the trail and the Contractor may utilize trail-scale equipment along the full length of the Lake Margaret trail. Where possible, the trail tread may be leveled and temporally widened up to 10” beyond the current template.