RFI Official Responses - 1.pdf

PDF 128 KB Posted

Attached to
127EAW24R0071 -Road 6N06 Slide Repair
Solicitation number
127EAW24R0071
Issued by

About this file

This document is a Request for Information (RFI) containing official responses from the U.S. Forest Service regarding the 127EAW24R0071 - Road 6N06 Slide Repair solicitation. The key details are:

The RFI response clarifies that for Site #2, 30 tons of asphalt is needed for the replacement. The estimated start date for the project is June 9, 2025. The solicitation will be amended to include additional line items under Option 1 for 24" culvert removal/replacement, roadway excavation, base rock, and asphalt. Interested parties must submit Requests for Information by 1300 hours PST on September 3rd, 2024. An organized site visit will be held on August 27th, 2024 at 10:00 AM PDT, and failure to inspect the site will not constitute grounds for a claim after contract award. The solicitation is a Total Small Business Set-Aside with an estimated value between $500,000 and $1,000,000.

View the file

Other files

File Type Posted
A00001 - Schedule and RFIs Round 1.pdf PDF
2. Schedule of Items - REVISION 001.docx DOCX document
6. Davis-Bacon Act WD # CA20240004.pdf PDF
7. RFI Form.docx DOCX document
5. Road 6N06 Slide Repair Project Drawings.pdf PDF
3. Supplemental Specifications.pdf PDF
4. Fire Plan.pdf PDF
1. Statement of Work.pdf PDF
2. Schedule.docx DOCX document
127EAW24R0071 - Road 6N06 Slide Repair.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FOR OFFICIAL USE ONLY

REQUEST FOR INFORMATION (RFI) OFFICIAL RESPONSES

127EAW24R0071 - Road 6N06 Slide Repair

RFI responses will be responded to as necessary in amendment format which will be posted to the solicitation via beta.SAM.gov

Telephone requests for information will not be accepted or returned.

RFI #1 – What is the tonnage of site #2 for the asphalt replacement?

USFS Response – For Site #2, 30 tons is needed for the asphalt replacement.

RFI #2 – What is the estimated start date?

USFS Response – Start date June 9, 2025

RFI #3 – These items are on the plans but not on the schedule of items:

Base Bid- 24”culvert to be removed and replaced

Option 1-20407- Roadway Excavation

Option 1- 30102 Base Rock

Option 1- 40304- Asphalt

USFS Response – For the “Base Bid- 24” culvert to be removed/replaced”, there is a line item for a 24” culvert and drain, type CMP. The removal and replacement should be part of this line item, therefore consider that in the unit/total cost.

As for the following Option items: 20407-Roadway Excavation, 30102-Base Rock, 40304-

Asphalt. An amendment to the solicitation must be made to include these in the schedule of items under Option 1. Please refer to the revised document “2. Schedule of Items - REVISION 001”.

File details come from the government source that posted it. Updated .