A00001 - RFI Responses.pdf

PDF 242 KB Posted

Attached to
127EAW24R0027 - Inyo NF Vault Toilets
Solicitation number
127EAW24R0027
Issued by

About this file

This document is an amendment to a solicitation for the Inyo NF Vault Toilets project. The amendment provides responses to Requests for Information (RFIs) submitted by prospective offerors. The key details are:

The solicitation number is 127EAW24R0027, with an effective date of May 15, 2024. The project is for the construction of vault toilets on the Inyo National Forest, with an estimated value between $100,000 and $250,000. It is a total small business set-aside. The amendment addresses RFIs related to slope requirements, concrete specifications, material sources, and excess dirt disposal. The last day to submit RFIs is May 15, 2024. The roads to most sites are currently open, but the road to the Mammoth Lakes Basin sites is closed due to snow, with an unknown reopening date.

View the file

Other files

File Type Posted
Schedule with Quantity Locations.xlsx XLSX spreadsheet
5. Fire Plan.pdf PDF
3. Project Drawings.pdf PDF
1. Statement of Work.pdf PDF
4. Project Specifications.pdf PDF
2. Schedule.docx DOCX document
7. RFI Form.docx DOCX document
127EAW24R0027 - Inyo NF Vault Toilets.pdf PDF
6. Davis-Bacon Act WD # CA20240020.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

A00001

GREGORY L. CUNNINGHAM

This purpose of this amendment is to post RFI round 1 responses.

Attached is "RFI Official Responses - 1" which is hereby incorporated into any subsequent contract award. Failure to use the revised documents and requirements revised within will result in your proposal being non-responsive.

USDA FOREST SERVICE

PROCUREMENT & PROPERTY SERVICES (PPS)

CONTRACT SERVICE AREA (CSA) 6 – CONSTRUCTION

3237 PEACEKEEPER WAY, SUITE 101

MCCLELLAN PARK, CA 95652

ALL INTERESTED VENDORS 127EAW24R0027

1 3

05/15/2024

05/15/2024

FOR OFFICIAL USE ONLY

REQUEST FOR INFORMATION (RFI) OFFICIAL RESPONSES

127EAW24R0027 - Inyo NF Vault Toilets

RFI responses will be responded to as necessary in amendment format which will be posted to the solicitation via beta.SAM.gov.

Telephone requests for information will not be accepted or returned.

RFI #1 – The plan calls for a maximum 2:1 cut and fill slope. This will not be possible in some case, since the vault was installed up against the cut slope. How do we address this?

USFS Response – Each case will be taken on an individual basis. When not feasible to construct a 2:1 cut and fill slope, COR may approve cut and fill slopes above the maximum or forego them all together.

RFI #2 – In some cases it won't be possible to stay below the maximum sidewalk slope since the vaults were installed too high. How do we address this?

USFS Response – Each case will be taken on an individual basis. Contractor could submit proposed course of action to meet sidewalk slope requirements or COR could approve a more than maximum slope segment.

RFI #3 – The concrete specs call for 4,000psi. Will the contractor be required to have testing done, or will the mix design suffice?

USFS Response – The mix design shall suffice.

RFI #4 – The concrete spec calls for a 3-1/2" slump, will slump tests be required or will the COR inspecting suffice?

USFS Response – The mix design submittal and COR inspection shall suffice.

RFI #5 – The local quarry does not have 6" crushed rip rap. Will 3"-6" crushed rip rap suffice?

USFS Response – If the local quarry does not have 6” crushed rip rap, 3”-6” crushed rip rap shall suffice.

RFI #6 – Does the contractor need to provide submittals for the concrete and road base?

USFS Response – Yes, contractor shall submit specifications for the concrete and road base.

RFI #7 – Can we use barrier rocks from other sites on the forest instead of importing from the quarry?

FOR OFFICIAL USE ONLY

USFS Response – No, contractor must import material as required.

RFI #8 – What is the last day to submit RFIs?

USFS Response – 15 May 2024.

RFI #9 - The road to Mammoth Lakes Basin is closed according to the visitor center, presumably due to snow. Three of the sites are located in the Mammoth Lakes Basin. Are the roads to the other sites open and if not, when will we be able to access them, as well as the ones in the Basin?

USFS Response – The roads to the other sites are currently snow free. The Town of Mammoth is currently working on plowing the road, not sure on when it will be open.

RFI #10 – Will any excess dirt need to be hauled off from any of the sites, or will it be dispersed on site?

USFS Response – The Contractor is responsible for removal and disposal of all excavated dirt and shall not leave excavated dirt scattered over the site, unless approved by the COR.