A00001 - RFI Responses.pdf

PDF 886 KB Posted

Attached to
127EAW24R0019 - Crystal Lake and Coldbrook CG Roads
Solicitation number
127EAW24R0019
Issued by

About this file

This document is an amendment to a solicitation for the contract 127EAW24R0019 - Crystal Lake and Coldbrook CG Roads. The solicitation is a total small business set-aside between $500,000 and $1,000,000 for road and infrastructure work at the Crystal Lake and Coldbrook Campgrounds in the Angeles National Forest.

The amendment includes responses to 23 Requests for Information (RFIs) submitted by potential offerors. The RFI responses provide clarification on items such as the Deer Flats road crossing, restroom demolition, culvert replacement, asphalt patching and crack sealing requirements, gate details, water availability, and work schedule. The amendment also incorporates additional drawings and specifications into the solicitation. Offers must acknowledge receipt of the amendment prior to the due date. The amended solicitation retains a May 14, 2024 deadline for RFI submissions and a site visit on May 7, 2024.

View the file

Other files

File Type Posted
1. Statement of Work.pdf PDF
5. Supplemental Specifications.pdf PDF
8. RFI Form.docx DOCX document
7. Davis-Bacon Act WD # CA20240022.pdf PDF
3. Project Drawings.pdf PDF
2. Schedule.docx DOCX document
4. Fire Plan.pdf PDF
6. Forest Service Supplemental Specifications.pdf PDF
127EAW24R0019 - Crystal Lake and Coldbrook CG Roads.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

A00001

GREGORY L. CUNNINGHAM

The purpose of this amendment is to post RFI round 1 responses and gate drawing.

Attached is "RFI Official Responses - 1" and "Crytal Lake Coldbrook Gate Specs" which are hereby incorporated into any subsequent contract award. Failure to use the revised documents and requirements revised within will result in your proposal being non-responsive.

USDA FOREST SERVICE

PROCUREMENT & PROPERTY SERVICES (PPS)

CONTRACT SERVICE AREA (CSA) 6 – CONSTRUCTION

3237 PEACEKEEPER WAY, SUITE 101

MCCLELLAN PARK, CA 95652

ALL INTERESTED VENDORS 127EAW24R0019

1 10

05/20/2024

04/25/2024

FOR OFFICIAL USE ONLY

REQUEST FOR INFORMATION (RFI) OFFICIAL RESPONSES

127EAW24R0019 - Crystal Lake and Coldbrook CG Roads

RFI responses will be responded to as necessary in amendment format which will be posted to the solicitation via beta.SAM.gov

Telephone requests for information will not be accepted or returned.

RFI #1 – Deer Flats access road: Is there a plan with elevations for site clearing at the Deer Flats road crossing?

For the upstream section, would the 50 feet of sediment removal result in a level pad next to the road? Or would it slope up to daylight at 50 feet?

And is any clearing necessary downstream since any obstructions are not impeding flow?

Should pricing just be based on the 50 cy quantity of export listed on the Schedule of Items?

At the site visit, there was discussion of clearing the Deer Flats access road - Where on the Schedule of Items should this cost be included?

USFS Response – See C-08 of the Contract Drawings for elevations for Deer Flats Road

Crossing. Sediment removal will result in an up slope to daylight on the upstream side. No side clearing for the downstream side of the water crossing. Pricing for debris removal is an estimate quantity and could be more or less than the 50 CY called out in the Schedule of Items (SOI). For bidding purposes, please bid on the 50 CY quantities.

After reviewing with the Eng. Department, no road clearing will be needed for Deer Flats Road – work will be done in-house by ANF Road Crew prior to the commencement of contract work.

RFI #2 – Restrooms: Will the restroom demo at Deer Flats require pumping and cleaning of tanks?

If so, what size tanks are they?

Since assessment of access was not possible during the site visit, what is the access to the demo site? Can a 10-wheel dump truck access the site?

Will sediment removal around restrooms need to be hauled off site for disposal?

What are the overall sizes of the restrooms?

Deer Flats Demolition Specifications A2 states “Leave existing vaults beneath buildings in place.

The vault contents, excluding the vault floor, shall be completely removed from the site.

The vault floor shall be broken in place, and remaining hole shall be filled with clean washed sand.”

While A3 states “Demolition shall include removal of the structure, its foundation (to a depth of 1 foot) and associated flatwork around the buildings.” Is the vault to be removed completely (except for the floor)?

Specification also states “Contractor shall perform their own independent site inspection of the site conditions during the pre-work site inspection.” And “Hazardous Materials: It is the responsibility of the contractor to identify and remove any hazardous materials present in the building materials prior to any demolition work. All hazardous materials abatement work shall be done by a California certified Lead Based Paint and asbestos abatement contractor.” Since access was not possible, how should bidders assume conditions for Price Proposals?

USFS Response – An abatement survey was previously conducted in 2020. Results showed no traces of asbestos or lead based paint for the buildings. Demolition debris will be disposed of as construction waste with no other requirements and should be bidded accordingly. Sediment removal around the restroom will need to be hauled off site. As for the size of each building, please see table on C-11 of the Contract Drawings.

Demolition of restroom will require the vault toilets to be pumped of all debris before decommissioning. Restrooms and vault toilets shall be decommissioned as outlined in Section 02

41 00 – Demolition, Part 1 – General, Section 1.01 A2 and A3 – see below:

A1. Remove all waste from within the vault. Crush the top and perforated the bottom of the vault to promote percolation of water. The top 12 inches shall be filled to grade with clean material meeting the requirements of “General Backfill” material and shall be compacted in 6-inch lifts to 90% maximum dry density. Site shall be left in a natural state.

A2. Demolition of restroom shall include removal of the structure, its foundation (to a depth of 1 foot) and associated flatwork around the buildings. Existing utilities shall be capped in place and buried. Use methods required to complete the work within limits of governing regulations. Utilities shall be terminated 36 inches below grade and capped at both ends. Disposal shall be in accordance with Section 01 74

00, Cleaning and Waste Management and Section 01 74 19 Construction Waste

Management for disposal requirements.

Although road design width is 10-12 feet, sections of Deer Flats Road may be reduced to a smaller width. Car with a track width of 8 feet have been able to clear Deer Flats Road all the way to Deer Flats Campground.

RFI #3 – Culvert replacement: During site visit, significant flow was observed though this culvert.

Should dewatering be included or is it anticipated that this stream channel will be dry during construction? If dewatering is required, what procedures will be necessary for capture and discharge? What gauge steel should be used for the 18 inch culvert?

USFS Response – Dewatering will not be required, it is anticipated that the stream will be dry during construction. 16 Gauge Steel should be used for the culvert.

RFI #4 – B.2 states quantities listed are estimated but should price proposal be based on listed quantities only?

USFS Response – Proposal shall be based on quantities listed in schedule.

RFI #5 – Traffic Spike installation: Will only the spike strip be replaced? Or will the concrete footing also need to be replaced? What is the axle weigh requirement for the spike strip? Will warning signage and a speed bump also need to be provided and installed as usually required?

USFS Response – Only the Spike Strip is to be replaced, no concrete work will be required.

Warning signs must be used with traffic spikes to warn drivers that a one-way traffic lane condition exist. Speed bumps must always be used with traffic spikes. Speeds in excess of 5-MPH over the spikes can cause tire damage and create excessive wear on the spike system. The minimum Axle Weight requirement is 8,000 Lb. per axle. All items should be included in the 0.00

Replace Existing Tire Spike Traffic Control Device Base Bid Coldbrook CG.

RFI #6 – Gates: Are there drawings of the new gates with footing details? Will the existing gates and footings need to be removed and if so, is there any info on the installation of the old gates? The entry gate is a single closure heavy weight pipe gate which can have a massive footing with concrete filled posts which can take significant effort to remove.

USFS Response – The new gate details are attached. Single Lane Light Duty Gate G4-1 (2

Pages). Assume the existing single closure heavy gate had a 24”x 48” footing, see attached drawing G4-13.

RFI #7 – Plans: Where should the costs of plans be included in the Price Proposal? Construction

Waste Management Plan, Sampling and Testing Work Plan, Abatement Work Plan, Accident

Prevention Plan, etc.

USFS Response – Not required. Abatement survey has been completed and will no longer be a requirement under this contract.

RFI #8 – SWPPP: Are there any specific erosion control measures required and/or is a SWPPP required for this project?

USFS Response – Ground Disturbance will be limited in size and thus does not require a

SWPPP.

RFI #9 – POP- Statement of work states POP starting August 16, 2024 with a POP of 180 days and winterization of the site in October. Will weather related delays be excluded from the 180 day

POP? Or should it be assumed the project must be completed by the winterization date since the end of the POP will be in February, still during the winter?

USFS Response – USFS will allow contractors to start earlier than August 16, 2024 as long as the Deliverables/Schedules required are submitted 14 days prior to the prework meeting. It is anticipated that the 180 days should be a sufficient POP including weather delays. The

Statement of Work includes no mention of October Winterization.

RFI #10 – WATER- What is the status of water availability in the area? Can we draw from the river?

USFS Response – Water cannot be drawn from the river/creeks. There are hydrants and other apparatuses that will allow the contractor to use water from the USFS Crystal Lake Campground

Water System. Water cannot be guaranteed if there is emergency needs by Fire Personnel.

RFI #11 – ASPHALT PATCHING - Will an approximate number of locations or a number range of locations for patching on each specific loop throughout the Campgrounds be provided?

USFS Response – See Table Below

Segment Loop A LENGTH Width

LF

Sawcut

SF

Asphalt

#18 4 4 16 16

#17 3 5 16 15

#15 3 3 12 9

#13 44 2 92 88

#10 10 6 32 60

#10 3 25 56 75

#5 2 2 8 4

Total 232 267

Segment Loop B LENGTH Width

Sawcut

SF

Asphalt

Entrance 20 2 44 40

Entrance 4 9 26 36

#20 3 3 12 9

#32 45 2 94 90

#31 2 6 16 12

#30 6 12 36 72

Total 228 259

Segment Loop C LENGTH Width

Sawcut

SF

Asphalt

#36 13 8 42 104

#35 7 4 22 28

Total 64 132

Segment Loop D LENGTH Width

Sawcut

SF

Asphalt

#47 13 16 58 208

#48 7 12 38 84

Total 96 292

Windy Gap PL LENGTH Width

Sawcut

SF

Asphalt

#1 175 16 382 2800

#2 14 16 60 224

#3 3 6 18 18

#4 40 150 380 6000

Total 840 9042

RFI #12 – CRACK SEALING – Prior to crack fill is routing & an air lance required?

USFS Response – Please Refer to FP-14 414.03 Equipment and 414.04 Routing

RFI #13 – SLURRY SEAL – IS rubber tire rolling required thereafter slurry placement?

USFS Response – Please Refer to FP-14 410.05 Equipment. (c) Sweeper. See Subsection

409.05(c). (d) Pneumatic-tire rollers. See Subsection 409.05(d).

(e) Auxiliary equipment. See Subsection 409.05(e).

RFI #14 – PAINT – What type of paint is required – Standard Traffic Pain (2 coats) or

Thermoplastic plastic Paint?

USFS Response – Please refer to FP-14 634.05 (a) Type B

634.05 Waterborne Traffic Paint (Type B and Type C). Apply paint when pavement and air temperatures are 50 °F (10 °C) and rising.

(a) Type B. Do not heat the paint above 120 °F (49 °C). Spray paint at a 15 mil (0.38 millimeters) minimum wet film thickness or at a rate of 107 square feet per gallon (2.6 square meters per liter).

Apply Type 1 glass beads on the paint at a rate of 6 to 8 pounds per gallon (0.72 to 0.96 kilograms per liter) of paint.

On new asphalt pavements or new asphalt surface treatments, apply two coats.

RFI #15 –Please provide the specification for crack and slurry seal.

USFS Response – FP-14, Section 414 – Asphalt Pavement Crack Sealing and Filling FP-14, Section 410 – Slurry Seal (Type II)

RFI #16 – For the debris that is to be removed from the low water crossing on Deer Flats road (C-

08), is there a designated drop off area where the debris can be deposited or is line item 201.01

Clearing and Grubbing include hauling cost

USFS Response – No designated drop off area has been identified. Therefore, please include hauling cost into your bid.

RFI #17 – Can you specify the design width for Deer Flats road?

USFS Response – Design Width is 12’

RFI #18 – Concrete vs. Cement headwall for Deer Flats Washout? Please specify.

USFS Response – Concrete headwall

RFI #19 – Will Crystal Lake Campground be completely closed to the public while work is being performed.

USFS Response – Crystal Lake Campground will not be completely closed to the public.

Individual loops can be closed once a schedule is presented by the contractor. Up to 3 sections/Loops of the contract may be closed at one time. USFS personnel will be responsible for ensuring closures on proposed dates and making sure no camping in active work areas is occurring.

RFI #20 – On Crystal Lake Road over by where the culvert is being proposed for install, a galvanized pipe was observed running parallel with the road just 1 foot off the edge of the pavement. Can you confirm what utility this is and if it is active?

USFS Response – We believe this is an active water utility

RFI #21 – For the OSD to be installed on Deer Flats road, can the contractor remove a tree(s) for the proper alignment of the OSD device.

USFS Response –Prior to the removal of a tree, the contractor will be required to consult with FS

Botany and Natural Resource Officer through the COR for proper clearances. For example a nesting bird clearance may be required that only last for 7 days.

RFI #22 – Deer Flats Road – can the contractor trim back branches for equipment clearance.

USFS Response – Prior to the trimming of a tree, the contractor will be required to consult with

FS Botany and Natural Resource Officer through the COR for proper clearances. Trimming will be limited to the minimum necessary to allow for equipment access.

RFI #23 – Deer Flats Road – cut slope unstable. Will the contractor be required to do any road maintenance in the event of a landslide. If so, please provide specifications and pay items.

USFS Response – Cut slope excavation shall be limited to the least amount necessary. In the case of a debris slide, earth moving shall be considered incidental to the road work outlined in the contract. If there is a change in site conditions, notify to COR immediately.