1. Statement of Work - Revision 001.pdf
PDF 572 KB Posted
- Attached to
- 127EAW23R0008 - Mountain Chief Metal Barriers
- Solicitation number
- 127EAW23R0008
- Issued by
-
Department of Agriculture Forest Service
View the file
Other files
| File | Type | Posted |
|---|---|---|
| A00002 - Width Limiter Gates Locations.pdf | ||
| A00001 - Time Extension SOW revision RFI Responses.pdf | ||
| RFI Official Responses - 1.pdf | ||
| 1. Statement of Work.pdf | ||
| 3. Fire Plan.pdf | ||
| 2. Schedule.docx | DOCX document | |
| 5. Davis-Bacon Act WD # CA20230007.pdf | ||
| 127EAW23R0008 - Mountain Chief Metal Barriers.pdf | ||
| 4. Specifications and Map.pdf | ||
| 6. RFI Form.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US Department of Agriculture (USDA)
Statement of Work
Contents Project
General Information
1.0 Scope of Work
2.0 Background
Contractor Requirements
3.0 Technical Requirements / Tasks
4.0 Government Furnished
5.0 Deliverables / Schedule
6.0 Travel
7.0 Contractor’s Key Personnel
8.0 Security Requirements
Project Mtn Chief Barriers Proejct
General Information
1.0 Scope of Work
• Fabricate and deliver 145 End Panels as shown below and in spec sheet.
• End panels shall be offloaded and stacked in a manner appropriate for forklifts to move. Contractor must coordinate delivery and COR shall be on site for delivery.
• Contractor is responsible for offloaded all panels at delivery site.
• Deliver to 24125 Racetrack Street Foresthill CA 95631
• Fabricate and install 3 width limiter gates along Mtn Chief Road Forest Road 10-6 where the road junctions OHV
Trails Tie 3-3 (several locations) and Loop 3. See map and design specs. Width limiter Gates ONLY shall be painted Forest Green or similar to the color shown below.
2.0 Background
These end panels and width limiter gates are needed to supplement existing cable and post materials acquired last year by Tahoe NF/ARRD to construct 2.2 miles of steel post cable fencing. Width Limiter gates will be installed at junctions along the Mtn Chief Road 9FR 10-6) where three OHV trails leave the road. Width limiters will restrict ATV’s from accessing the trails but permitting dirt bikes. Swing gate design will allow emergency vehicle access when needed.
Contractor Requirements
3.0 Technical Requirements / Tasks
• Fabricate 145 end panels as shown on the attachment, deliver to 24125 Racetrack, Foresthill CA 95631.
• Fabricate and install 3 width limiter gates along Mtn Chief Road Forest Road 10-6 where the road junctions OHV Trails Tie 3-3 (several locations) and Loop 3. See map and design specs. Contractor shall notify the
COR to coordinate installation and final inspection of gates prior to arrival. Delivery must be within normal office hours
Monday-Friday 0800-1630. Gates shall be painted Forest Green or similar to the color shown above.
DETAIL & NOTES BELOW ONLY FOR FOOTING REQUIREMENTS
DETAIL & NOTES BELOW FOR WIDTH DATE LOCKING DESIGN & REQUIREMENTS
4.0 Government Furnished
N/A
5.0 Deliverables / Schedule
Key Deliverables
Item No. Deliverable Objective Due
1 Proposed Project Plan Defining the responsibilities, timeline, risks and milestones of contract objectives. Ref. Subtask 4.1.3
No later than five (5) business days after contract award
2 Delivery of End Panels Provide materials to American River Ranger District No later than forty-five (45) business days after contract award
3 Installation of three (3) Width Limiter Gates
Installation of gates No later than sixty (60) business days after contract award
6.0 Travel
• Deliver end panels to 24125 Racetrack Street in Foresthill CA at the American River Ranger District Work Center. Contractor must have unload capabilities.
• Install three width limiter gates along Mtn Chief Road Forest Road 10-6 where the road junctions OHV Trails Tie 3-3 (several locations) and Loop 3. See map and design specs. Access to job site is 12 miles east of Foresthill CA along the paved Foresthill
Divide Road. The Mtn Chief Road is a flat wide dirt road.
7.0 Contractor’s Key Personnel
• Project Superintendant
8.0 Security Requirements
• End panels shall be secured safely for transport and storage.
• Width limiter gates shall be constructed at the semi-remote Mtn Chief Road jobsite. Contractor shall be cautious as to minimize theft of property during installation.