Request for Information No1.docx

DOCX document 13 KB Posted

Attached to
GAOA FC Almanor CG ADA Toilet Replacements and Accessibility, Lassen National Forest
Solicitation number
127EAW22R0038
Issued by

About this file

This document provides details of a federal contract opportunity to remove and replace vault toilets in the Almanor Campground on the Lassen National Forest in Plumas County, California. The USDA Forest Service Southwest Zone has a requirement to furnish all labor, equipment, and materials to demolish seven existing vault toilet buildings including five double, one triple, and one quadruple vault toilets, and replace them with eight new precast concrete double vault toilet buildings. Outdoor accessible routes to the new vault toilet buildings must be constructed per the Forest Service Outdoor Recreation Accessibility Guidelines. The contract will have a period of performance of 270 calendar days from the notice to proceed. A request for proposal will be released on May 16, 2022 and close on June 16, 2022, with an anticipated start date of July 5, 2022. This will be competed as a Hubzone small business set-aside with an estimated value between $250,000 to $500,000.

View the file

Other files

File Type Posted
SF30.docx DOCX document
Signed Plans FC- Almanor CG ADA Toilet Replacments.pdf PDF
RFP FC Almanor.docx DOCX document
SOW-Specifications_Almanor CG ADA Toilet Replacements.docx DOCX document
Project Maps_FC- Almanor CG ADA Toilet Replacments.pdf PDF
wage determination.pdf PDF
Fire Plan - Almanor RD.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Request for Information No. 1 Solicitation: 127EAW22R0038

Question No. 1:

The vault toilet manufactures are currently showing lead times of 120 to 180 days out after submittal/design approval. Will the demo be allowed this fall and placement of the new vault toilets next spring leaving a hole for the new vault? Or, will a winter suspension cover enough contract time for demo and placement of the vault toilets in the spring?

Response: In order to allow for delivery lead times, site work, weather shutdown and make safe items the period of performance of 120 days set forth in Block 11, SF-1442 and Section F, 52.211-10 is hereby revised to 270 calendar days from issuance of the Notice to Proceed.