Request for Information No1.docx
DOCX document 13 KB Posted
- Solicitation number
- 127EAW22R0038
- Issued by
-
Department of Agriculture Forest Service
About this file
This document provides details of a federal contract opportunity to remove and replace vault toilets in the Almanor Campground on the Lassen National Forest in Plumas County, California. The USDA Forest Service Southwest Zone has a requirement to furnish all labor, equipment, and materials to demolish seven existing vault toilet buildings including five double, one triple, and one quadruple vault toilets, and replace them with eight new precast concrete double vault toilet buildings. Outdoor accessible routes to the new vault toilet buildings must be constructed per the Forest Service Outdoor Recreation Accessibility Guidelines. The contract will have a period of performance of 270 calendar days from the notice to proceed. A request for proposal will be released on May 16, 2022 and close on June 16, 2022, with an anticipated start date of July 5, 2022. This will be competed as a Hubzone small business set-aside with an estimated value between $250,000 to $500,000.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SF30.docx | DOCX document | |
| Signed Plans FC- Almanor CG ADA Toilet Replacments.pdf | ||
| RFP FC Almanor.docx | DOCX document | |
| SOW-Specifications_Almanor CG ADA Toilet Replacements.docx | DOCX document | |
| Project Maps_FC- Almanor CG ADA Toilet Replacments.pdf | ||
| wage determination.pdf | ||
| Fire Plan - Almanor RD.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Request for Information No. 1 Solicitation: 127EAW22R0038
Question No. 1:
The vault toilet manufactures are currently showing lead times of 120 to 180 days out after submittal/design approval. Will the demo be allowed this fall and placement of the new vault toilets next spring leaving a hole for the new vault? Or, will a winter suspension cover enough contract time for demo and placement of the vault toilets in the spring?
Response: In order to allow for delivery lead times, site work, weather shutdown and make safe items the period of performance of 120 days set forth in Block 11, SF-1442 and Section F, 52.211-10 is hereby revised to 270 calendar days from issuance of the Notice to Proceed.