A-7 QnA Version 1 - 03.08.21.docx

DOCX document 16 KB Posted

Attached to
Critical Water System Repair Phase 1 - Plaskett Meadows CG
Solicitation number
127EAW21Q0003
Issued by

View the file

Other files

File Type Posted
A-7 QnA Version 3 - 03.17.21.pdf PDF
A-6.0 127EAW21Q0003-0002.pdf PDF
A-6 127EAW21Q0003-0001.pdf PDF
A-6.1 Specifications (Rev 1).pdf PDF
A-6.2 Project Plans (Rev 1).pdf PDF
A-7 QnA Version 2 - 03.15.21.pdf PDF
A-6.3 WD CA20210007, Mod 5, dated 02.19.2021.pdf PDF
A-6.1 Specifications.pdf PDF
A-6 Questionaire.docx DOCX document
A-6 127EAW21Q0003.pdf PDF
A-6.2 Project Plans.pdf PDF
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers Document

Critical Water System Repair Phase 1 - Plaskett Meadows CG (127EAW21Q0003)

Version 1: 03/08/2021

Q1: What is the diameter of the CMP to receive new lids?

A1: The CMP sizes vary between 24"- 36"; exact sizes will need to be field verified by the Contractor.

Q2: Is there a spec on the new Hose Bibs for the option bid item?

A2: Hose bibbs will not be replaced. The bid option is for the replacement of PVC distribution line only.