This document is a set of Vendor Questions and Answers related to a federal contract opportunity for Project Management services for the Pecos/Las Vegas Ranger District of the Santa Fe National Forest.

The key details are:

  • The contract is for a two-year period of performance, with 12 required trips to the Santa Fe National Forest over that timeframe.
  • The Project Manager is the only key personnel required, and a PMP certification is mandatory.
  • The project is for ongoing post-fire recovery efforts, and the vendor will be provided background information.
  • Proposals are due by April 8th, and private sector experience is acceptable.
  • Travel costs can be billed, and there is an additional line item for other project management services as needed.
  • The solicitation number is 127EAV24R0002 and the opportunity is being issued by the USDA Forest Service.

View the file

Other files

File Type Posted
Combined SS_RFP Project Mgt HPCC 240322.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. Could you confirm whether this position is designated as remote with an expectation of 12 trips to Santa Fe within a two-year timeframe?

The position is remote with an expectation of 12 trips to the Santa Fe National Forest Pecos/Las Vegas Ranger District 12 times within a two-year timeframe.

2. Just to clarify, is the period of performance for this contract set at two years in total, or is it structured as one base year with the possibility of extending for an additional year?

The period of performance is for two years from the date of award.

3. In addition to the Project Manager, are there any other key personnel anticipated to be required under this contract?

The Project Manager is the key personnel required under the contract.

4. Could you please confirm whether the sections marked as N/A in the RFP will be updated at a later stage, or should we consider the current version as final?

The current version should be considered as final.

5. Is there any project documentation such as project charter or project foundation documents?

The project is part of on-going post-fire recovery efforts, and the vendor will be provided with a lot of background information.

5. The person from my firm that I have in mind for this project does not have a PMP (or other certification) but has over 13 years of project management experience. Is the lack of a certification disqualifying for your needs or will you consider someone with extensive experience in project management?

A certified PM is required for this solicitation.

6. Item 0006 refers to 12 trips over 2 years and is listed in the base year and option year. Refer to the response for question #1

7. Is this a new project? Yes.

8. We believe we may be qualified for this opportunity; however our past performance is in the private sector. Do you recommend having a prime or mentor for this opportunity? Or what do you recommend our stance if we apply as a single contractor for this project?

Submit your technical and price proposal as requested as a single contractor. Private sector experience is acceptable.

9. We would like to know if any preexisting artifacts will be made available upon the award of the contract or if this project will be initiated from scratch.

Not sure what “preexisting artifacts” means. The project is part of on-going post-fire recovery efforts, and the vendor will be provided with a lot of background information.

10. Is travel on a regular basis or based on the program of work?

We anticipate 12 trips over 2 years to be scheduled quarterly with 2 additional trips. It will be both regular basis and based on program of work.

11. What is the anticipated duration of each trip?

Probably 2-3 days per trip.

12. Is the contractor expected to bill travel costs or travel hours?

The vendor can bill for travel costs.

13. Can you clarify or provide more information regarding the following:

Line Item 0005 (qty 1)

Other deliverables as identified needed for effective program/project management of projects

This line item is for additional PM services for a new or expanded project. The services would include project development and tracking, scheduling meetings and agendas, and other related tasks.

14. Can you extend the response time to April 15, 2024?

Proposals are due April 8th.