This document appears to be a set of questions and answers related to a federal solicitation for a fence construction project at the Gila National Forest.

The solicitation, numbered 127EAV24Q0072, is for a firm fixed-price construction contract with a magnitude less than $25,000. The Forest Service is seeking quotes from qualified small business contractors to provide and install fencing materials. Key details include:

  • The contract requires approximately 2,000 feet of fencing rails and 500 feet of fence posts/uprights, with posts spaced 10-12 feet apart.
  • Corner posts must be set in concrete, while t-posts can be pounded directly into the ground.
  • The performance period is anticipated to begin around August 12, 2024 and complete by November 30, 2024.
  • Quotes are due by 5:00 PM EDT on August 5, 2024 and must be submitted via email to the Contracting Officer, Fareedah Vaughn.
  • This is a 100% small business set-aside under NAICS code 238990.

The document also includes responses to several technical questions from prospective offerors regarding the fencing materials and installation requirements.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions - 127EAV24Q0072 - Stewart Fence

1. Do you have pipe or is it used 2 5/8” well bore tubing. I ask because drill stem/tubing is usually magnetized after use. Magnetization makes weld process more difficult.

It is brand new pipe.

2. Length of provided pipe says 2500’. 2000’ for rails and 500 for uprights/posts.

• General Description Section States: Uprights will be placed 10 to 12 ft apart depending on lay of land.

• So, assuming you will be able to follow the 10’ spacing over 90% the fence project the pipe required is minimum of 40’ and as high as 100’ more than what is provided.

• 1000/10’ spacing = 100 – 10% = 90 posts. 90 posts at 6’ is 540’ of pipe used as posts. 2-4 of joints extra on top of the 2540’ required might be needed for cut offs.

We will provide whatever pipe is required to get the project completed.

3. Is the less than 25k magnitude going to remain firm?

Yes.

4. Is gate provided equipped with hinges?

No, we do not have hinges for the gate.

5. Should vendors contact you directly if they request a site visit?

Yes. A site visit can be arranged on an as needed basis.

6. Is it possible to drive posts, or do they all need to be augered and filled with Sakrete?

Corner posts need to be set in sakrete, but T-posts just need to be pounded in the ground.