Questions and Answers for Solicitation 127EAU21Q0002
Q: There is a minimum 8-9 week lead time to receive material from the manufacturer. I saw in the SOW it needs to be received within 4 weeks. Will this be allowed?
A: The 4 week delivery is the requirement, If it is impossible to meet this for all contractors then the delivery date will become a primary evaluation criteria.
Q: We can deliver to the site but will need others to unload material from truck. Will the US Forest staff unload material from the truck?
A: Yes, Forest Service personnel can assist with the unloading of the materials.
Q: In regards to the above mentioned RFQ, would 48” wire stays be acceptable?
A: This will be acceptable. But will be evaluated accordingly by deviating from the original requirement.