Attachment 1 - SOW Rev.pdf

PDF 133 KB Posted

Attached to
Coronado NF Road Aggregate Federal contract opportunity
Solicitation number
127EAT25Q0068
Issued by
Department of Agriculture Forest Service

About this file

This Statement of Work (SOW) for the Coronado National Forest Sierra Vista Ranger District outlines a road surfacing project for National Forest System Road (NFSR) 158 near Sonoita, Arizona. The project requires a contractor to supply and deliver 500 tons of aggregate base (grade C) and 1,000 tons of surface course aggregate (grade G) to the specified road location. The materials will be hauled and placed in coordination with the Coronado National Forest Road Crew, who will spread, blade, and finish the road. The contractor has 60 days from the Notice to Proceed to complete the project, with the job site located 4.2 miles from the AZ-83/AZ-82 intersection at specific GPS coordinates. The Contracting Officer Representative is Edwin Monin, with Calvin Curtis serving as the secondary point of contact, both providing contact information for further communication.

View the file

Other files for this federal contract opportunity

Other files attached to Coronado NF Road Aggregate, newest first.
File Type Posted
Attachment 7 - Coronado NF Road Aggregate Questions Answers.docx DOCX document
Attachment 6 - Table 703-2 (FSSS).pdf PDF
Attachment 1 - SOW.pdf PDF
Attachment 5 - Wage Determination.txt TXT text file
127EAT25Q0068 - Road Aggregate.pdf PDF
Attachment 3 - Forest Service Supplemental Specifications.docx DOCX document
Attachment 4 - Table 703-3 (FSSS).png PNG image
Attachment 2 - Papago Road Location Map.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Coronado National Forest

Sierra Vista Ranger District

Sonoita, AZ

Papago Road Surface Material

Statement of Work

The Coronado National Forest needs road surfacing material supplied and delivered to National Forest System Road (NFSR) 158. This includes:

1. 500 tons of aggregate base, grade C (Table 703-2, FP-14), or as approved equal.

2. 1000 tons of surface course aggregate, grade G (Table 703-3, Forest Service

Supplemental Specs), or as approved equal.

The aggregate will be hauled and placed along the route identified (See Location Map) in coordination with the Coronado NF Road Crew which will spread, blade, and finish the road as the material is being hauled in. Timing to bring the material in will be coordinated in an eƯort to keep the haul in by contractor and spreading by the Coronado NF road crew a continuous operation. Contractor has 60 days from Notice to Proceed to complete.

NFSR 158 can be located by driving south on AZ-83 for 0.4 miles oƯ the AZ-83/AZ-82 intersection in Sonoita, AZ, taking a slight right on E Papago Springs Road, and driving 4.2 miles before reaching the job site at coordinates 31.6227185229, -110.63895541.

The Contracting OƯicer Representative is:

Edwin Monin edwin.monin@usda.gov

(520)260-0122

Secondary point of contact is:

Calvin Curtis

Calvin.curtis@usda.gov

(928)506-1667