This document is a Supplementary Statement of Work (SOW) for the procurement of a new communications shelter for the USDA Forest Service at the Rosies Ridge site in the Bridger-Teton National Forest. The SOW details precise requirements for a PEPRO LLC 8'x8'x8' shelter with an integrated 40' articulating mast, specifying extensive technical specifications including equipment rack configurations, power and RF cable management, lighting, battery systems, grounding, surge protection, ventilation, solar panel mounting provisions, and specific antenna mounting requirements.

The SOW also outlines comprehensive installation and demolition instructions, requiring the contractor to deliver the shelter to a specified location in Moran, WY at least 4 weeks prior to installation, safely offload and install the new shelter at the Rosies Ridge communications site, and completely demolish and remove the existing 6'x6' CMU shelter and 25' ROHN tower. Additional requirements include disconnecting existing commercial power and telecom circuits, with all demolition debris to be disposed of in accordance with state and federal environmental regulations. The project involves site-specific design compliance with TIA-222 standards and OSHA safety requirements.

View the file

Other files

File Type Posted
PEPRO Brand Name JA 12760425Q0043_Redacted.pdf PDF
12760425Q0043.pdf PDF
Attachment 1 - Bill of Materials.xlsx XLSX spreadsheet
Attachment 2 - Performance Work Statement.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

7.1 Supplementary Statement of Work (SOW)

The contractor must provide all materials and services for the work required to complete the installation of a new communications shelter at Rosies Ridge. The site is located on the Black Rock/Buffalo Ranger District, Bridger-Teton National Forest at the following coordinates: Lat 43N 49’ 45.97” Long 110W 20’ 6.78”. The work provided by the contractor shall satisfy the following:

7.1.1 Shelter Design Requirements

A. The Manufacturer of the shelter shall comply with all applicable nationally recognized building and electrical codes.

B. The shelter shall be a PEPRO LLC. 8’x8’x8’ shelter with an integrated 40’ mast. The mast shall articulate to allow access to the antennas while in the horizontal position.

C. The shelter shall include the following equipment.

a. (1) 19” x 84” equipment racks

b. Overhead cable ladder rack to allow for the distribution of power and RF cables from their respective entry points to the equipment rack

c. Standard Pepro DC lighting fixtures with LED bulbs, connected to a 1-hour rotary timer switch installed near the shelter entrance

d. (1) Rack mounted battery trays, each capable of supporting (3) NorthStar 155

AGM batteries

e. (1) Rack mounted bus bar

f. (1) Main Ground Bus bar (MGB) installed below the RF entry panel

g. (1) Filtered DC entry port tied to the faraday cage

h. (1) Filtered AC entry port tied to the faraday cage

i. Standard 8’x8’ Pepro AC power layout

j. (1) Surge protection devices (SPD) for solar array connections, SPDs shall be rated for a 12VDC Solar array

k. (1) Surge protection devices (SPD) for AC power connection, SPDs shall be rated for use with commercial power

l. (2) Passive ventilation ports that include hoods, louvers, and screens to prevent insects from entering the shelter

m. Previsions to mount solar panels to both the roof and south face of the shelter

n. Solar panel mounts designed to work with the building attachment points

o. The door shall be installed on the East face of the shelter

p. The integrated mast shall be attached to the West side of the shelter and shall articulate to the East over the top of the shelter

q. The Manufacturer shall provide (1) double 18” and (2) 4” mounts to attach (1)

Telewave ANT150F2 antenna at 40’, (1) RFS BA1012-0 antenna at 35’, (1) Sinclair SY303-SF1CNM(ABK) antenna at 40’ to the mast

D. The shelter design shall include a faraday cage to protect the equipment from transient voltage spikes

E. The shelter shall include an RF entry panel with 9 ports; the appropriate quantity of boots and cushion inserts to support (4) ½” Heliax cables. The RF entry port, boots, and cushion inserts shall be integrated into the faraday cage. The remaining unused RF entry ports shall be capped with covers that are integrated into the faraday cage.

F. The shelter design shall be such that it can be deployed on bare unimproved land without the need for excavation or foundation construction.

G. The shelter shall be grounded through Ufer pads placed on native surface; due to the no ground disturbance requirements a traditional ground system cannot be part of the solution.

H. The shelter shall be anchored to the land without the use of guy wires or stakes.

I. The shelter and mast system shall be designed on a site-specific basis and must comply with the current version of TIA-222. The mast system shall be designed to support the following antennas and feedlines:

a. Telewave ANT150F2, 40’, feedline LDF4-50, 18” standoff, USFS

b. RFS BA1012-0, 35’, feedline LDF4-50, 4” standoff, USFS

c. Sinclair SY303, 40’, feedline LDF4-50, 18” standoff, USFS

d. CommScope DB224-A, 25’, feedline LDF4-50, 4” standoff, Cooperator

J. The roof of the shelter shall include an integrated anchor point that meets OSHA standard 29 CFR 1926.502(d)(15) capable of sustaining 5,000lbs. (22.2KN) of force.

K. The contractor shall also reference the provided PWS, BOM, Shelter Request Form, and this document for design details.

7.1.2 Shelter Delivery and Installation

A. Prior to installation the shelter shall be delivered to:

20250 Hwy 26/287 Moran, Wy. 83013

B. The shelter shall be delivered at a minimum of 4 weeks prior to installation.

C. The contractor shall schedule and provide the means to safely offload the shelter at the delivery location.

D. The contractor shall schedule, coordinate, and install the new shelter at the Rosies Ridge communication site.

E. The road system used to access the Rosies Ridge communications site is in good condition. However, the use of a lowboy to transport to and from the site may be a challenge due to tight switchbacks.

F. The shelter shall be installed in the location marked out on the ground by the Forest Service Land Mobile Radio staff.

7.1.3 Demolition of Existing Shelter and Tower

A. The contractor shall demolish and dispose of (1) 6’x6’ CMU type shelter to include demolition of the foundation to 18” below grade and backfill with native soil.

B. The contractor shall demolish and dispose of (1) 25’ ROHN tower C. The removal of the existing telecommunications shelter will be done in such a way that no damage will occur to the remaining structures/equipment.

D. The new shelter will be placed on the in the footprint of the old shelter.

E. Any damage caused by the removal of the structure will be the responsibility of the contractor to repair.

F. Disposal of all demolition debris is the responsibility of the contractor and shall be discarded in accordance with state, federal environmental regulations as applicable.

7.1.4 Commercial Power

A. The contractor shall disconnect commercial power from the existing shelter, cap and protect the lines and conduit for future use or termination to the new shelter.

7.1.5 Telecom circuits

A. Three existing audio circuits in existing shelter will be disconnected. The cabling should be cut below grade and covered with native soil.

7.1 Supplementary Statement of Work (SOW)
a. Telewave ANT150F2, 40’, feedline LDF4-50, 18” standoff, USFS
b. RFS BA1012-0, 35’, feedline LDF4-50, 4” standoff, USFS
c. Sinclair SY303, 40’, feedline LDF4-50, 18” standoff, USFS
d. CommScope DB224-A, 25’, feedline LDF4-50, 4” standoff, Cooperator
J. The roof of the shelter shall include an integrated anchor point that meets OSHA standard 29 CFR 1926.502(d)(15) capable of sustaining 5,000lbs. (22.2KN) of force.
K. The contractor shall also reference the provided PWS, BOM, Shelter Request Form, and this document for design details.
7.1.2 Shelter Delivery and Installation
A. Prior to installation the shelter shall be delivered to:
20250 Hwy 26/287
Moran, Wy. 83013
B. The shelter shall be delivered at a minimum of 4 weeks prior to installation.
C. The contractor shall schedule and provide the means to safely offload the shelter at the delivery location.
D. The contractor shall schedule, coordinate, and install the new shelter at the Rosies Ridge communication site.
E. The road system used to access the Rosies Ridge communications site is in good condition. However, the use of a lowboy to transport to and from the site may be a challenge due to tight switchbacks.
F. The shelter shall be installed in the location marked out on the ground by the Forest Service Land Mobile Radio staff.
7.1.3 Demolition of Existing Shelter and Tower
7.1.4 Commercial Power