Q n A.pdf
PDF 789 KB Posted
- Attached to
- R10, Tongass NF Twin Peaks Shelter and Install
- Solicitation number
- 12760422Q0045
- Issued by
-
Department of Agriculture Forest Service
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Q n A.pdf | ||
| Shelter PWS January_05_2022.pdf | ||
| 20223834 001 BOM R10.xlsx | XLSX spreadsheet | |
| Request for Quote Twin Peaks.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation 12760422Q0045 Twin Peaks Communications Shelter Questions and Answers
1. BOM Manufacture Line 5 – What kind of equipment rack is required, 19” or 23” and how many RU’s tall? 19” x 84”
2. BOM Manufacture Line 5 – Asked for Battery tray to be installed on rack closest to wall, however line 5 only asked for one rack, how many racks are required? 1 rack, 1 battery tray
3. BOM Manufacture Line 30 – What is the ice shield’s purpose? Is it to protect the building or comm equipment? It is to protect the RF cables from falling ice where they enter the building
4. BOM Manufacture Line 25 – calls for a roof and wall mount solar, however line 38 states Mast Mount Solar. Where is the solar to be installed, building or solar mounted? Solar will be installed on both the roof of the building and on the mast
5. Does this system require any AC circuits or wiring? This is a DC power building
6. I would like to request an extension to the RFQ Due Date? No, with the timeline required to manufacture and meet the installation window of June 2022 we cannot see any additional delays to this project.
1. Will lights be required in this installation? Yes provide (1) 12VDC light installed on ceiling near center of shelter include light switch located next to door
2. What size battery bank is expected, how many amp hours or capacity. The battery bank will be made up of (2) Rolls S6-275AGM batteries and will be installed in the rack mounted battery tray. Batteries will be provide and installed by customer
3. What is the anticipated daily power consumption? This is dependent upon the duty cycle of the radio equipment, shelter will house (1) CODAN VHF repeater with 30W PA
4. How many Watt of solar is requested for this site? The solar array will consist of (4) 200W panels wire in parallel
5. You stated the existing shelter has a foundation with 4 poured concrete footings (sonotubes) which were placed and poured by the Forest Blaster greater than 15 years ago. The new shelter spec calls for no permanent foundations, are we to remove the existing foundation or abandon in place? The existing concrete foundation can be abandoned in place.
6. Will you be publicly posting all questions asked on this RFQ? Yes
7. In your answer to my previous question you state a “timeline required to manufacture and meet the installation window of June 2022”. The RFQ states “FOB Destination – The vendor shall be capable of procuring and delivering the equipment listed in the BOM by 30 September 2023.” Can you clarify this projects period of performance? The current plan is to install in June or July of 2022 or 2023 due to expected weather constraints in the area.
Attached are two photos of Twin Peaks from the air in 2021. I have also included photos from 2014, though there has been cleanup done at the site since then, to include the removal of the 15’ Sinclair shelter.
The site is on a very remote Alaskan peak, with a mix of granite boulders and peat soil with low scrub brush. There is no overland access to the site, it is helicopter only.
I do not have a drawing for the existing 4’x6’ Vertex shelter. However, the foundation is 4 poured concrete footings (sonotubes) which were placed and poured by the Forest Blaster greater than 15 years ago.