ePricing TO 02-2020-BLK 140-240 Reconstruction - Amendment 1.docx
Air Force Technical Order Amendment 1 DOCX document 2 MB Posted
- Attached to
- Road Maintenance - Black Hills National Forest
- Solicitation number
- 1267T020R0003
View the file
Other versions and copies of T.O. 02-2020-BLK
| File | Revision | Posted | Attached to |
|---|---|---|---|
| ePricing TO 02-2020-BLK 140-240 Reconstruction - Amendment 1.docx Same revision and size as this file | Amendment 1 | Road Maintenance - Black Hills National Forest | |
| ePricing TO 02-2020-BLK 140-240 Reconstruction.docx | Revision not stated | Road Maintenance - Black Hills National Forest |
Who attaches T.O. 02-2020-BLK
Other files
| File | Type | Posted |
|---|---|---|
| 1267T020R0003 Amendment 2.docx | DOCX document | |
| ePricing TO 03-2020-BLK NH Road Maintenance - Amendment 1.docx | DOCX document | |
| 1267T020R0003 Amendment 1.docx | DOCX document | |
| ePricing TO 01-2020-BLK NFSR 504 Reconstruction - Amendment 1.docx | DOCX document | |
| 1267T020R0003.docx | DOCX document | |
| ePricing TO 01-2020-BLK NFSR 504 Reconstruction.docx | DOCX document | |
| ePricing TO 03-2020-BLK NH Road Maintenance.docx | DOCX document | |
| Forest Service Supplemental Specifications.docx | DOCX document | |
| Referenced Specifications.docx | DOCX document | |
| ePricing TO 04-2020-BLK BL Roadside Brushing.docx | DOCX document | |
| ePricing TO 02-2020-BLK 140-240 Reconstruction.docx | DOCX document | |
| ePricing TO 05-2020-BLK HC Roads Cattleguard Cleaning.docx | DOCX document |
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Road Maintenance IDIQ – Solicitation #1267T020R0003 Amendment #1 Black Hills National Forest
GENERAL INFORMATION: (Contractor to complete yellow highlighted areas) Task Order Number: 02-2020-BLK 140/240 Reconstruction Contractor's Pricing (to be completed by contractor):
| Item |
| Description |
| measure |
| unit |
| quanitty |
| Unit Price |
| Total Price |
| 151(01) |
| Mobilization |
| LSQ |
| 1 |
| LS |
| $ / |
| $ |
| 301(01)D |
| Aggregate base course, grading D, |
compaction method A, (Government Furnished Aggregate)
| CQ |
| 4968 |
| CY |
| $ / |
| $ |
| 301(01)Q |
| Aggregate base course, grading Q, |
compaction method A. (Government Furnished Aggregate)
| CQ |
| 138 |
| CY |
| $ / |
| $ |
| 303(18) |
| Road reconditioning, roadbed, compaction method D |
| CQ |
| 5.04 |
| Mile |
| $ / |
| $ |
| 602(01)18 |
| Culverts and Drains, Furnish and install 18” pipe culvert |
| AQ |
| 108 |
| Linear foot |
| $ / |
| $ |
Totals
Special Considerations: All specifications, clauses, terms and conditions of the Master IDIQ are part of this task order. Supplemental specifications specific to this task order are included with this package via E-mail. Pricing cover sheet due to Contracting Officer on May 12, 2020 at 10:00a.m.
Contractor is required to provide pricing for every task order issued. If the contractor cannot meet the “Contract Completion Time” identified below, an alternate schedule must be addressed below. The contractor’s ability to meet the “Contract Completion Time” along with price are the evaluation factors considered in the award of this task order. Reference Section G.4 of the master contract.
Alternate Completion Date(s)/Comments:
Contractor's Signature/Company: /s/ Date:
SUPPLEMENTAL SPECIFICATIONS
GENERAL
Scope of Work:
The work shall consist of what is shown on the drawings, stated in the specifications and summarized below:
· Establish traffic control signing and barricades
· Clearing and brushing 8’ from road shoulder for sight distance clearance
· Reconditioning of 4.9 miles of Aggregate roadway
· Placing the proper Quantities of Grading D Aggregate
· Compaction will be obtained by operating hauling and spreading equipment over the entire width of the traveled way
· Properly grade road to provide the road the opportunity to drain
· Clean inlet and outlets of the existing culverts
Project Location: Northern Hills Ranger District Boxelder Forks Road (NFSR 140) is located West the town of Nemo, SD. The road leads to Boxelder Forks Campground approximately 1.8 miles west of Nemo. Contract work will begin at the 2nd Box Culvert along Forest Service system road 140 or MP 0.93.
Dalton Lake Road (NFSR 224) is just north of the town of Nemo, SD approximately 3.5 miles along FH-26. This road leads to Dalton Lake Campground. Roadwork will begin at the Pvt. Land Boundary approximately .5 miles from the FH-26.
Price Range:
The Government’s estimate is between $25,000 and $100,000.
Contract Completion Time: 90 calendar days from issuance of a Notice To Proceed.
· Desired Start Date: June 1, 2020
· Desired Date all work to be completed: August 30, 2020. (unless an alternate schedule is offered by the contractor).
Work Procedure:
All work related to this project shall be done in accordance with all applicable OSHA regulations.
Government Furnished Materials:
Government Furnished Source for this project is Custer Peak Pit. Legal location of this pit is: T3N, R3E, S1.
| Item No. |
| Description |
| Quantity |
| Value |
| 301(01) |
| Aggregate Surfacing |
| 4968CCY |
| $34,776.00 |
Referenced Specifications:
FSR 140 & 224 Surface Rock Replacement project shall conform to the FP-14 Standard Specifications for Construction of Roads and Bridges on Federal Highways Projects
FP-14 Standard Specifications for Construction For Roads and Bridges on Federal Highway Projects are available on the following web page:
(https://flh.fhwa.dot.gov/resources/specs/fp-14/fp14.pdf)
"General Decision Number: SD20200001 01/03/2020
Superseded General Decision Number: SD20190001
State: South Dakota
Construction Types: Heavy and Highway
Counties: South Dakota Statewide.
HEAVY AND HIGHWAY CONSTRUCTION PROJECTS
Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.80 for calendar year 2020 applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2015. If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.80 per hour (or the applicable wage rate listed on this wage determination, if it is higher)for all hours spent performing on the contract in calendar year 2020. If this contract is covered by the EO and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must pay workers in that classification at least the wage rate determined through the conformance process set forth in 29 CFR 5.5(a)(1)(ii) (or the EO minimum wage rate if it is higher than the conformed wage rate). The EO minimum wage rate will be adjusted annually. Please note that this EO applies to the above-mentioned types of contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but it does not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(2)-(60). Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.
Modification Number Publication Date 0 01/03/2020
* SUSD2018-001 03/20/2018
Rates Fringes
CARPENTER........................ $ 27.96 0.00
CONCRETE FINISHER................ $ 21.41 0.00
ELECTRICIAN...................... $ 26.42 3.85
LABORER
| Group 1..................... | $ 18.86 0.00 |
| Group 2..................... | $ 17.51 0.00 |
| Group 3..................... | $ 18.95 0.00 |
| Group 5..................... | $ 27.96 0.00 |
| Group 6..................... | $ 21.41 0.00 |
LABORER CLASSIFICATIONS:
GROUP 1: Air Tool Operator; Common Laborer; Landscape Worker, Flagger, Pilot Car Driver; Trucks under 26,000 GVW; Blue-top Checker, Materials Checker.
GROUP 2: Mechanic Tender; Pipe Layer (except culvert); Form Builder Tender; Special Surface Finish Applicator; Striping.
GROUP 3: Asphalt Plant Tender; Pile Driver Leadsman; Form Setter, Oiler/Greaser.
GROUP 5: Form Builder
GROUP 6: Grade Checker
PAINTER.......................... $ 21.41 0.00
POWER EQUIPMENT OPERATOR:
| Group 1..................... | $ 20.62 0.00 |
| Group 2..................... | $ 20.66 0.00 |
| Group 3..................... | $ 22.02 0.00 |
| Group 4..................... | $ 23.79 0.00 |
| Group 5..................... | $ 24.77 0.00 |
POWER EQUIPMENT OPERATORS CLASSIFICATIONS
GROUP 1: Concrete Paving Cure Machine; Concrete Paving Joint Sealer; Conveyor; Tractor (farm type with attachments); Self-Propelled Broom; Concrete Routing Machine; Paver Feeder;
Pugmill; Skid Steer.
GROUP 2: Bull Dozer 80 HP or less; Front End Loader 1.25 CY or less; Self-Propelled Roller (except Hot Mix); Sheepsfoot/50 Ton Pneumatic Roller; Pneumatic Tire Tractor or Crawler (includes Water Wagon and Power Spray Units); Wagon Drill; Air Trac; Truck Type Auger; Concrete Paving Saw.
GROUP 3: Asphalt Distributor; Bull Dozer over 80 HP; Concrete Paving Finishing Machine; Backhoes/Excavators 20 tons or less; Crusher (may include internal screening plant); Front End Loader over 1.25 CY; Rough Motor Grader; Self-Propelled Hot Mix Roller; Push Tractor; Euclid or Dumpster; Material Spreader; Rumble Strip Machine.
GROUP 4:Asphalt Paving Machine Screed; Asphalt Paving Machine; Cranes/Derricks/Draglines/Pile Drivers/Shovels 30 to 50 tons; Backhoes/Excavators 21 to 40 tons; Maintenance Mechanic; Scrapers; Concrete Pump Truck.
GROUP 5:Asphalt Plant; Concrete Batch Plant; Backhoes/Excavators over 40 tons; Cranes/Derricks/Draglines/Pile Drivers/Shovels over 50 tons; Heavy Duty Mechanic; Finish Motor Grader; Automatic Fine Grader; Milling Machine; Bridge Welder.
TRUCK DRIVER
| Group 1..................... | $ 21.46 0.00 |
| Group 2..................... | $ 21.66 4.22 |
TRUCK DRIVERS CLASSIFICATIONS
GROUP 1: Tandem Truck without trailer or pup; Single Axle Truck over 26,000 GVW with trailer.
GROUP 2: Semi-Tractor and Trailer; Tandem Truck with Pup.
WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year. Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).
The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of ""identifiers"" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).
Union Rate Identifiers
A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than ""SU"" or ""UAVG"" denotes that the union classification and rate were prevailing for that classification in the survey. Example: PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.
Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.
Survey Rate Identifiers
Classifications listed under the ""SU"" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.
Survey wage rates are not updated and remain in effect until a new survey is conducted.
Union Average Rate Identifiers
Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.
A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.
WAGE DETERMINATION APPEALS PROCESS
1.) Has there been an initial decision in the matter? This can be:
* an existing published wage determination
* a survey underlying a wage determination
* a Wage and Hour Division letter setting forth a position on a wage determination matter
* a conformance (additional classification and rate) ruling
On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.) and 3.) should be followed.
With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:
Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:
Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.
3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
4.) All decisions by the Administrative Review Board are final.
END OF GENERAL DECISION
image1.emf image2.emf image3.emf image4.emf image5.emf image6.emf image7.emf image8.emf image9.emf image10.emf image11.emf image12.emf image13.emf image14.emf image15.png image16.emf image17.emf image18.emf