Weir_repairsQA.docx
DOCX document 13 KB Posted
- Attached to
- Weir Repair Project Federal contract opportunity
- Solicitation number
- 1263PX18S0102
About this file
Questions and answers for the 09/05/18 site visit.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| RFP-Fernow_Weir_Project.doc | DOC document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Weir repairs Pre-bid meeting Questions & Answers
1. Q. What material should the 8” drains be made of, and how thick?
A. Drains shall be schedule 40 steel pipe with a minimum 0.322 wall thickness
2. Q. What should contractor do with concrete debris from demolition?
A. Concrete debris will be disposed of on-site as directed by FS
3. Q. Can contract be extended if weather issues arise?
A. Yes, as long as the company is making a good faith effort to complete the project. Reasonable accommodation will be made to contractor to be given enough time to complete project.