- Replacement of Fire Hydrants, Edinburg, Texas
- Solicitation number
- 12639522R0009
About this file
This amendment modifies a solicitation for the replacement of fire hydrants in Edinburg, Texas. The scope of work includes replacing existing Kennedy and Muller fire hydrants and adding or replacing metal bollards around hydrants. An attachment provides a map of numbered existing hydrants and details on hydrant and bollard requirements. The due date for receipt of proposals is extended to January 28, 2022 at noon central time.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 12639522R0009-0002.pdf | ||
| 12639522R0009-0001.pdf | ||
| Attachment 1_Fed Constr wage rates_TX20210255.pdf | ||
| Attachment 2_map of hydrant locations.pdf | ||
| 12639522R0009.pdf | ||
| Attachment 3.doc | DOC document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
12639522R0009 x x copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
APHIS-MN-126395
01/20/20220003
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
USDA APHIS
250 MARQUETTE AVE
SUITE 410
MINNEAPOLIS MN 55401
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
12/16/2021
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Tax ID Number: Not Available
DUNS Number: Not Available
- This amendment is written to incorporate a new Attachment 2, map of numbered hydrants;
incorporate Attachment 4, bollard requirements; and provide information on existing hydrants and valves.
- Fire hydrants currently installed are Kennedy K81A 5 1/4, with 6" Clow resilient wedge gate valve (shut off valve). Preference is to stay with Kennedy fire hydrants as they have replacements parts in stock and are easily repaired. An alternate brand is Muller, which has parts readily available and are also easily repaired.
- The due date for receipt of proposals is extended to Jan 28, 2022, at noon central time.
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
JAMES G. ROLOFF
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
01/20/2022
VS
B ar n
A R
S
En d of M is si on
D riv e
Ph as e
Ph as e
Ph as e
AE
O
At ta ch m en t 2
, a m en dm en t 3
Fire Hydrant Existing Install
1 None 4 Metal Bollards 6" 2 4 Metal Bollards 4" 4 Metal Bollards 6" 3 4 Metal Bollards 6" None 4 4 Metal Bollards 6" None 5 2 Metal Bollards 4" 4 Metal Bollards 6" 6 2 Metal Bollards 6" 2 Metal Bollards 6" 7 None 4 Metal Bollards 6" 8 None 4 Metal Bollards 6" 9 None 4 Metal Bollards 6"
10 4 Metal Bollards 6" None 11 2 Metal Bollards 6" 2 Metal Bollards 6" 12 2 Metal Bollards 6" 2 Metal Bollards 6" 13 2 Concrete 2 Metal Bollards 6" 14 4 Metal Bollards 6" None 15 None 4 Metal Bollards 6" 16 3 Metal Bollards 6" 2 Metal Bollards 6" 17 2 Concrete 2 Metal Bollards 6" 18 4 Metal Bollards 6" None 19 None 4 Metal Bollards 6" 20 None 2 Metal Bollards 6" 21 None 4 Metal Bollards 6" 22 4 Metal Bollards 6" None 23 None 4 Metal Bollards 6" 24 None 4 Metal Bollards 6" 25 None 4 Metal Bollards 6" 26 4 Metal Bollards 6" None 27 4 Metal Bollards 6" None 28 4 Metal Bollards 6" None
Moorefield Fire Hydrants Bollards Attachment 4, amendment 3
Note: Fire Hyrant #2 and #5 have existing 4" Bollards and need to be replaced with 6" Bollards. Fire Hydrant #13 and #17 have existing concrete bollards and need to add 2 6" Metal Bollards. All bollards need to be painted safety yellow.
| ADP4E18.tmp |
| Sheet1 |
| 2022-01-20T11:01:08-0600 | |
| JAMES ROLOFF |
File details come from the government source that posted it. Updated .