QUESTIONS_AND_ANSWERS_WITH_CLARIFICATIONS.docx
DOCX document 14 KB Posted
- Attached to
- OTT - Lake Ottawa Fishing Pier
- Solicitation number
- 12569R18Q0012
About this file
Pre-Bid Questions, Answers, & Clarifications
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment_to_Proposal_Instructions.docx | DOCX document | |
| Lake_Ottawa_Fishing_Pier_New_&_Replacement_Drawings.pdf | ||
| Lake_Ottawa_Fishing_Piers_Project_Pre-Bid_Sign_In_Sheet.pdf | ||
| Lake_Ottawa_Specifications.doc | DOC document | |
| SF_30_SOLICITATION_AMENDMENT.pdf | ||
| ATTACHMENT_A_-_STATEMENT_OF_WORK_.docx | DOCX document | |
| ATTACHMENT_B_-_PLANS_&_DRAWINGS.pdf | ||
| 12569R18Q0012_OTT_Lake_Ottawa_Fishing_Pier.rtf | RTF text file | |
| ATTACHMENT_C_-_WAGE_DETERMINATION_MI48.txt | TXT text file | |
| ATTACHMENT_D_-_TECHNICAL_EVALUATION_-_EXPERIENCE_QUESTIONNAIRE.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
QUESTIONS AND ANSWERS - CLARIFICATIONS
Question(s) regarding sill / wall (abutment):
1. Is the sill / wall (abutment) being tied back to the shore / earth?
0. If so, how is the concrete sill / wall (abutment) being anchored (or tied back) to the shore?
1. How is deep is the sill / wall (abutment) buried in the earth?
1. To mid-point vertically?
1. Not at all?
1. How is the permanent dock tied to the sill / wall (abutment)?
Answer(s) regarding sill / wall (abutment) provided during meeting:
1. See the revised drawings / amendment to the solicitation for answers / details regarding this question.
1. See the revised drawings / amendment to the solicitation for answers / details regarding this question.
1. See the revised drawings / amendment to the solicitation for answers / details regarding this question.
Question(s) regarding stringer height above water and / or water elevation:
1. How high are the stringers supposed to be set (for the permanent pier) above water.
Answer(s) regarding stringer height above water and / or water elevation:
1. See the revised drawings / amendment to the solicitation for answers / details regarding this question.
Question(s) regarding permit(s):
1. Who’s responsible to obtain permits?
Answer(s) regarding permit(s):
1. According to FAR 52.236-7, Permits and Responsibilities, the contractor is responsible for obtaining all permits.
Question(s) regarding work hours:
1. Between what hours of the day can work take place?
Answer(s) regarding work hours:
1. Between 8 am & 5 pm local time.
0. The contractor can provide a written request to the CO to adjust daily working hours.
Attached Lake Ottawa Fishing Pier Drawing Replacements (to Attachment B – Plans & Drawings) are as follows:
Drawing sheet no. A-01 (first sheet of new attachment) replaces drawing sheet no. A-01 in Attachment B – Plans & Drawings (pg 2 of original document).
Drawing sheet no. A-02 (second sheet of new attachment) replaces drawing sheet no. A-02 in Attachment B – Plans & Drawings (page 1 of original document).
Drawing sheet no. C-01 (third sheet of the new attachment) is in addition (new) to the existing Attachment B – Plans & Drawings.
Additional Specifications have also been added as an addenda to the solicitation.
Response date has been extended to June 1, 2018, 4:30 p.m. EST.
File details come from the government source that posted it.